Decision Notice - Approved by Delegation of Authority MCU19 0013

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Officer: 	Billy Glover
Direct Telephone: 	53296109
Our Reference:	MCU19/0013 & RAL19/0003
Your Reference:	n.a
9 May 2019
RF Erharter
C/- Pivotal Perspective Pty Ltd
4/59 Mary St
NOOSAVILLE  QLD  4566
[email protected]
Dear Sir
Decision Notice
Planning Act 2016
I refer to your application and advise that on 9 May 2019, Council decided to approve the application, subject to conditions.
Details of the decision are as follows:
application details
Application No:	MCU19/0013 & RAL19/0003
Street address:	10 Opal St Cooroy Qld 4563
Real property description:	Lot 6 RP 82318
Planning Scheme:	The Noosa Plan (8 June 2018)
Decision details
Council decided to issue the following type of approval:
Development Permit for Material Change of Use - Multiple Housing - Type 2 Duplex
Development Permit for Reconfiguration of a Lot - Community Titles Scheme (2 Lots)
CURRENCY PERIOD of approval
The currency period for this development approval for Material Change of Use and Reconfiguring a Lot is 6 years starting the day that this development approval takes effect.
assessment manager conditions
Material Change of Use
PLANNING
When Conditions must be Complied With
Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
-	-	Site, Subdivision and Preliminary Services Layout Plan As annotated by Council	29/01/2019
V.1 – 29.04	-	Site Cover Plan, drawn by Toth Environmental	10/04/2019
GJGSCN190173 2	E	Site Plan, drawn by G. J Gardner Homes	17/01/2019
GJGSCN190173 3	E	Lower Floor Plan, drawn by G. J Gardner Homes	17/01/2019
GJGSCN190173 4	E	Elevations, drawn by G. J Gardner Homes	17/01/2019
GJGSCN190173 6	E	Roof Catchment Plan, drawn by G. J Gardner Homes	17/01/2019
Nature and Extent of Approved Use
Both dwellings must be fully constructed prior to the issue of the Plan Seal approval for the Community Titles Scheme.
The total site cover of the development must not exceed 40%.
Building Height
The maximum height of the development must not exceed 8 metres above the finished ground level and the natural ground level.
Performance Bond
Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the issue of a Development Permit for Operational Works. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions.
Screening Vegetation
Screening vegetation must be planted along the eastern boundary for the extent of the new dwelling on the new lot 2, in accordance with PSP 3 Landscaping Plants and Guidelines and an Operational Works approval.
Water & Sewer Connections
An underground connection to reticulated water and sewerage must be provided to the development site in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater).
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to the development site.
Building Appearance
All air conditioning units or other mechanical equipment must be located at ground level, or otherwise fully enclosed or screened such that they are not visible from the street frontages nor adjoining properties.
Roof Form
Eaves on the new dwelling unit must be 600mm in width. 450mm wide eaves will achieve this solution provided there is a 150mm wide gutter that brings the total width to 600mm.
Protection of Privacy
To ensure privacy is protected between adjoining properties, any window/s, deck or the like that overlooks or has the potential to overlook the private open space or habitable room windows of neighbouring properties must either:
have a minimum window sill height or 1.5 metres above floor level.
be fitted with translucent glazing.
be fitted with a fixed external screen positioned in such a way to obscure direct view.
Fencing and Walls
Any street fencing must be set back an average of 1 metre from the front property boundary. Any fencing on the front boundary must either:
not exceed a maximum height of 1.2m.
be of open construction.
The area of land between the fence and the front property boundary must be densely landscaped to screen any fencing from the street.
The existing fence along the Opal Street frontage may be retained, however any future fencing must comply with the fencing and walls conditions of this Decision Notice.
Clothes Drying Areas
Each dwelling unit must be provided with access to an outdoor clothes line which is screened from public view.
Community Management Statement
Any proposed Community Management Statement required for the development pursuant to the Body Corporate and Community Management Act 1997 must be submitted to Council for endorsement at the same time as submission of the Building Format Plan (or similar) to Council for compliance assessment.
All clauses and by-laws of the proposed Community Management Statement must accord with the requirements of this Decision Notice.
External Works
Opal Street must be upgraded for the length of its frontage to the subject site.  The works must be undertaken in accordance with an Operational Works approval and must include in particular:
kerb and channel on an alignment that is an extension of the existing kerb and channel to the west of the subject site and joins smoothly to the kerb and channel to the east of the site
widening and sealing of the existing road pavement
any necessary adjustments or modifications to the existing surface and piped stormwater drainage systems in Opal Street
any necessary adjustments to the existing property access
In this regard, specifications and plans detailing this work must be prepared in accordance with Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads, Drainage and Earthworks.
Site Access and Driveways
A sealed access driveway must be provided from Opal Street and Opal Lane to all parking and manoeuvring areas of the development. The works must be undertaken in accordance with an Operational Works approval and must include in particular driveway crossovers generally in accordance with Council’s Standard Drawings RS-049 and RS-050.
Stormwater Drainage
The site must be provided with a stormwater drainage system connecting to a lawful point of discharge.
All stormwater drainage (including roof water overflow from the rainwater storage system) must be collected and discharged so there is no net increase in stormwater runoff from the site.  The works must be undertaken in accordance with an Operational Works approval and be generally in accordance with the Proposed Duplex Integrated Water Management Plan – Version 0 dated April 2019 prepared by Callaghan & Toth Civil, Environmental and Hydraulic Engineers.
Electricity and Telecommunication Services
Reticulated electricity and telecommunication services must be provided to each lot in accordance with the standards and requirements of the relevant service provider.
Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications.
Certification must be submitted to Council from all relevant service providers which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction.
Easements
Unless otherwise agreed in writing by the relevant service provider, any public or third party infrastructure located on the subject site must be placed within an easement registered against the title of the property.
All easements must be designed in accordance with the planning scheme and granted at no cost to the Grantee.  Where the Grantee is Council or a service authority, the easement documentation must be in accordance with the Grantee’s standard easement terms.  Draft easement documentation must be submitted to Council for endorsement.
All works must be kept clear of any existing or proposed easements on the subject land, unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
All earthworks and associated batters/walls must be contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
Reconfiguration of a Lot
When Conditions Must Be Complied With
Unless otherwise stated, all works required by the conditions of this Decision Notice must be completed prior to submission of the subdivision plan to Council for compliance assessment.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
V.1 – 29.04	-	Site Cover Plan, drawn by Toth Environmental	10/04/2019
All lot numbering on the subdivision plan to be submitted to Council for compliance assessment must remain as shown on the Approved Plans.
The development must be undertaken and operated in a manner that causes no detrimental effect upon the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other emissions.
referral agencies
Not applicable.
Advisory notes
Building and Construction Industry (Portable Long Service Leave) Levy
The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
Co-ordination of Operational Works Assessment
Additional application fees apply to Operational Work applications where the different aspects of the works are lodged separately. Significant savings in application fees will result if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
A preliminary Construction Management Plan must be submitted with the Operational Works application and must address the following:
appropriate traffic signage in accordance with the Manual of Uniform Traffic Control Devices (MUTCD)
provision for safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased.
traffic management during all aspects of the construction phase including:
a Traffic Management Control Plan in accordance with the Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction.
maintenance of safe pedestrian access for the areas affected by the works during and after daily construction has ceased.
proposed fencing to the site during the construction phase of the development.
approval of the Traffic Management Control Plan by the Department of Transport and Main Roads (DTMR) for any works on State controlled roads.
provision for worker car parking.
maintenance and protection of water quality and existing drainage lines through the construction site, through the implementation of appropriate erosion and sediment control measures.
works programme identifying key components of the works and their respective durations.
establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic, services and other relevant issues.
identification of complaint management procedures including:
contact details for the on-site manager.
dispute resolution procedures.
it is acknowledged that the preliminary Construction Management Plan will be a draft document requiring finalisation upon appointment of the Principal Contractor employed to construct the works and a final document will be required to be submitted at the Pre-Start Meeting for the project.
Community Title Scheme - Private Infrastructure
All private infrastructure for the development must be designed to meet the planning scheme requirements unless otherwise agreed by the relevant authority.
Infrastructure Charges
This Development Permit will trigger an “Infrastructure Charge Notice” to be issued in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue.
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Type of Development Permit Required	Subject of the required Development Permit
Development Permit for Operational Works	Frontage Works, Access, Landscaping & Stormwater
Development Permit for Building Works	All building works
Compliance Certificate	Plan Sealing
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.

OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

Yours faithfully,

Billy Glover
Development Planner

Enc:	Appeal Rights
Approved Plans/Documents
Infrastructure Charge Notice
cc.	Unitywater

	Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1)	Schedule 1 of the Planning Act 2016 states –
(a)	Matters that may be appealed to –
(i)	either a tribunal or the P&E Court; or
(ii)	only a tribunal; or
(iii)	only the P&E Court; and
(b)	The person-
(i)	who may appeal a matter (the appellant); and
(ii)	who is a respondent in an appeal of the matter; and
(iii)	who is a co-respondent in an appeal of the matter; and
(iv)	who may elect to be a co-respondent in an appeal of the matter.
(2)	An appellant may start an appeal within the appeal period.
(3)	The appeal period is –
(a)	for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or
(b)	for an appeal against a deemed refusal – at any time after the deemed refusal happens; or
(c)	for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or
(d)	for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or
(e)	for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or
(f)	for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person.
Note –
See the P&E Court Act for the court’s power to extend the appeal period.
(4)	Each respondent and co-respondent for an appeal may be heard in the appeal.
(5)	If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal.
(6)	To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about-
(a)	the adopted charge itself; or
(b)	for a decision about an offset or refund-
(i)	the establishment cost of trunk infrastructure identified in a LGIP; or
(ii)	the cost of infrastructure decided using the method included in the local government’s charges resolution.
230 Notice of appeal
(1)	An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that-
(a)	is in the approved form; and
(b)	succinctly states the grounds of the appeal.
(2)	The notice of appeal must be accompanied by the required fee.
(3)	The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to –
(a)	the respondent for the appeal; and
(b)	each co-respondent for the appeal; and
(c)	for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and
(d)	for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and
(e)	each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and
(f)	for an appeal to the P&E Court – the chief executive; and
(g)	for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate.
(4)	The service period is –
(a)	if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or
(b)	otherwise – 10 business days after the appeal is started.
(5)	A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6).
(6)	A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person.
231 Other appeals
(1)	Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable.
(2)	The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error.
(3)	A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter.
(4)	In this section –
decision includes-
(a)	conduct engaged in for the purpose of making a decision; and
(b)	other conduct that relates to the making of a decision; and
(c)	the making of a decision or failure to make a decision; and
(d)	a purported decision; and
(e)	a deemed refusal.
non-appealable, for a decision or matter, means the decision or matter-
(a)	is final and conclusive; and
(b)	may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and
(c)	is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground.
232 Rules of the P&E Court
(1)	A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal.
(2)	However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court

[word/footer1.xml]
Page 9 of 9

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 9

[Attachment: image3.png (image text)]
ee) NOOSA COUNCIL
Log in to download the original file

Decision Notice - Approved by Delegation of Authority MCU19 0013.docx · 325 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.