Amended Noosa Project Restoration Plan V12_5

Attached to the e-mail OPW22/0029 - SRA application correspondence - Referral agency response – with conditions.

of 75

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Construction works (deployment of the restoration substrates) is planned between October and April
(2021-2023), subject to permitting. This timeframe takes advantage of natural oyster spawning and
recruitment in the Noosa River during this period.

Phase I restoration sites are presented in the plans, and have already been subject to:

    a.   Detailed bathymetric mapping
    b.   Detailed habitat mapping
    c.   River user analysis
    d.   Habitat suitability modelling
    e.   Restoration suitability modelling
    f.   Community consultation
    g.   Detailed site engineering

Phase II –2022 to 2024

Phase II works will take place the following spring through autumn period (2022-2023), and if
resources allow the following spring through autumn (2023-2024). Specific sites for this work have yet
to be identified, and authorities will be approached separately to approve plans for Phase II works,
possibly as an addendum of some form to this restoration plan approval.

In Phase II, works will entail:

    •    Augmenting restoration sites 1-4 from Phase I with additional restoration substrate, as
         required; and,
    •    Identifying new restoration sites in Restoration Zones 1 to 5 and deploying restoration
         substrates into those sites in accordance with the restoration processes outlined in this
         submission.

For phase II works, the process includes:

   I.    Identifying additional restoration sites using the restoration suitability model and stakeholder
         discussions
  II.    Checking, and, if necessary, remapping habitats at the new proposed sites
 III.    Consulting publicly on the additional proposed restoration sites
 IV.     Undertaking detailed bathymetric mapping
  V.     Applying existing engineering and design criteria and mapping restoration substrates onto the
         sites
 VI.     Submitting updated restoration plans to agencies
VII.     Undertaking construction works
VIII.    Applying site demarcation and management measures to the new sites
 IX.     Submitting ‘as built’ maps of new substrates to authorities

1.6 Governance

The Noosa Oyster Ecosystem Restoration Project is a partnership between The Nature Conservancy
(TNC) and Noosa Shire Council (NSC) formed to deliver oyster ecosystem restoration in the Noosa River.

The Project is framed by a formal partnership agreement between TNC and NSC. This partnership is
specified in the Alliance and Funding Agreement, which came into effect on 25 th July 2019. The
agreement is effective for three years and two months and the project is scheduled to be completed
                                                                                                      10
Log in to download the original file

Amended Noosa Project Restoration Plan V12_5.pdf · 6.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.