Amended Noosa Project Restoration Plan V12_5
Attached to the e-mail OPW22/0029 - SRA application correspondence - Referral agency response – with conditions.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnSECTION 8 – PERFORMANCE MEASURES
The objectives of the performance management framework are to:
• Maximise public safety
• Maintain visual amenity of the Noosa River (through optimal signage)
• Enact environmental safeguards to protect marine plants and natural processes
• Monitor for potential erosion
• Monitor and manage community feedback or complaints
• Ensure contingency measures are in place
8.1 Public Safety
The key hazards associated with public safety at the restoration sites during construction and site
management, their likelihood and consequence, and proposed treatment are presented in Table 8.1.
Public safety is further analysed and presented in Annex 8: Safety in Design Report.
Table 1: Primary hazards of restoration substrates to public safety and their treatment
Hazard Likelihood Consequence Treatment
Physical interaction LOW MEDIUM Gaps around oyster reef patches to be 1m-4m
with the restoration at seabed. Rock stable under its own weight
substrate (Monitoring and by interlocking of material. Oyster shell to
Personnel or Public) be placed towards the middle of individual
reef patches to minimise potential of
displacement from structure. Works to be
appropriately signposted in consultation with
MSQ. Works to be certified by a coastal
engineer on completion as conforming with
the specifications.
Works pose a risk to LOW MEDIUM Oyster reef patches laid as per specifications
navigation and locations selected with wide consultation
and MSQ input. Restoration sites marked as
per MSQ requirements.
Public information products imbedded locally
through public and social media to advise of
site locations and hazards including signage at
boat ramps or as directed by authorities.
Works pose a risk to LOW LOW Restoration sites selected to avoid all known
public access to river shoreline access points. No works within 10m
shoreline either side of a public park, shoreline beach
(of any size) or shoreline or within 30m of a
pontoon or jetty. No site directly adjacent to
shoreline houses or public or commercial
facilities.
66
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.