Delegated Report - Code - Planning OPW18 0028

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Author	Coordinator Engineering, Mark Lewis
Development Assessment

APPLICATION DETAILS
Application No.	OPW18/0028
Applicant	Rodney Peter Wilcox
Proposal	Operational Works - Drainage Works, Landscaping, Roadworks, Vehicle Crossover
Properly Made Date	28 March 2018
Information Request Date	Not required
Information Response Date	Not applicable
Decision Due Date	29 May 2018
Report Completed Date	21 May 2018
Number of Submissions	Not Applicable

PROPERTY DETAILS
Property Address	8 Supplejack Ct Lake Macdonald Qld 4563
RP Description	Lot 35 SP 103503
Land Area	4000.0000 m²
Existing Use of Land	Residential

STATUTORY DETAILS
SEQRP Designation	Regional Landscape and Rural Production
Locality	Cooroy and Lake Macdonald
Zone	Rural Settlement
Overlays	Biodiversity (enhancement), Natural Hazards (bushfire)
Assessment Type	Code
PROPOSAL
The application seeks approval for Operational Works - Drainage Works, Landscaping, Roadworks, Vehicle Crossover.
site details
Background
The application was submitted to address a condition in the associated Material Change of Use for the residence constructed on the site.
The existing formation in Supplejack Court consists of a 3m wide concrete driveway extending from Kamala Drive to a point approximately 6m across the frontage of the subject site. The remainder of Supplejack Court is not formed and is a track. It is noted that a parcel of land (Lot 100 on SP103503) exists between Supplejack Court and the adjoining Killawarra Road road reserve to the east. This parcel of land acts as an access restriction strip. Council’s Civil Operations section is aware of the public utilising the lot to travel from Killawarra Road to Supplejack Court and Kamala Drive. Council’s Civil Operations section has advised that it is intended to install barriers to prevent the access of through traffic.
The applicant’s proposed “road base” driveway was proposed as he considered that the road was a through route and was not his responsibility to construct a “road”. The situation was clarified with the Civil Operations section and the applicant that the intention is not for a through road.
The driveway formation requirements were discussed with Civil Operations section and it has been determined that the works must be an extension of the existing formation in Supplejack Court to the access point to the subject site. It is understood that this decision has been verbally discussed with the applicant. In order to clarify the requirements in the approval the submitted plan has been annotated by Council and relevant conditions included.
assessment
Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development:
State Planning Policy;
South East Queensland Regional Plan;
Planning Regulation 2017
The Noosa Plan.
The following codes from the Noosa Plan are applicable to this development:
Engineering Works Codes
Detached House Driveways Code
cONSULTATION
Referral Agencies
Not applicable
Other Referrals
The application was forwarded to the following internal Council officers:
Civil Operations
conclusion & reasons for decision
The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW18/0028 for Operational Works - Drainage Works, Landscaping, Roadworks, Vehicle Crossover situated at 8 Supplejack Ct Lake Macdonald Qld 4563 and described as Lot 35 SP 103503, it is recommended the application be approved in accordance with the following details for the Decision Notice:
application details
Application No:	OPW18/0028
Street address:	8 Supplejack Ct Lake Macdonald Qld 4563
Real property description:	Lot 35 SP 103503
Planning Scheme:	The Noosa Plan (27 November 2017)
Decision details
Council decided to issue the following type of approval:
Development Permit for Operational Works - Drainage Works, Landscaping, Roadworks, Vehicle Crossover
CURRENCY PERIOD of approval
The currency period for this development approval is 1 year starting the day that this development approval takes effect.
assessment manager conditions
APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
No Number		Plan submitted as part of application As Annotated by Council	Undated. Received by Council 8 March 2018
SITE SPECIFIC CONDITIONS
The formation and width of the new access driveway extending from the existing formation in Supplejack Court to the access driveway to the subject site must be the same as the existing formation of the concrete access driveway in Supplejack Court.
Works associated with this permit must not adversely impact on the existing drainage conditions on other properties or in the road reserve (eg by blocking, interfering with or redirecting natural overland flows).
This approval relates to works in the Supplejack Court road reserve only. The works indicated on the approved plans within the site are not approved by this permit.
Copies of the approved plans, duly signed by a Registered Professional Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer Construction at the “pre start” meeting.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
All necessary approvals from external service providers (eg Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council.
Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council at the prestart meeting.
Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245. The pre-start meeting must include the relevant parties for the following aspects of the works:
Civil engineering works;
Erosion and sediment control works;
Other relevant parties
A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following:
appropriate traffic signage in accordance with the Manual of Uniform Traffic Control Devices (MUTCD)
provision for safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased.
Prior to the commencement of municipal works associated with this development, Council requires the provision of a bank guarantee, or a cash bond, of not less than 10% of the value of the municipal works or $2500 whichever is the greater.
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans/documents and conditions detailed in this Decision Notice
The relevant conditions of the higher order Material Change of Use approval viz. MCU17/0526 to which this approval relates
All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines
The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site
Roadworks
All new pavement must join neatly to the existing pavement so that there are no irregularities in line or level resulting at or adjacent to the join for the length of the construction.
Pavement Design and Construction
The pavement designs shown on the approved drawings are not approved. To attain approval for the pavement design, the pavement design details must be certified by an RPEQ and submitted to Council for approval.
Works within Road Reserve/Reinstatement
Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with.
Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council.
Site Access
The access driveway to the subject site must be constructed generally in accordance with Council’s Standard Drawings RS-049 and RS-050
Stormwater Drainage
Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets.
Environment
All trees within the Supplejack Court road reserve must be protected and retained unless prior written approval has been obtained from Council.
Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site. The erosion and sediment control measures must be designed, installed and maintained in accordance with current best practice standards (refer to advisory notes).
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL ACCEPTING THE WORKS
Certification
Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit.
Bonds
The bond will be refunded less any costs incurred by Council in ensuring compliance with these conditions or any additional inspections incurred for substandard work or work undertaken not in accordance with this permit.
Bonds must:
meet the requirements of council’s relevant Planning Scheme Policy for performance and uncompleted works.
be calculated using a schedule of works and relevant bond equation
include GST
have approval of the bond calculations and amount from Council prior to lodgement
be lodged with Council and accompanied by the Bond Administration Fee/s.
be requested for release by writing to Council, when relevant approval requirements have been met.
As Constructed Plans and ADAC XML Files (Council)
Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory “As-Constructed” records must be submitted to Council. The bundle of “As Constructed” information shall include:
As-Constructed Drawings. Data is to be submitted in an electronic drawing file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
Please Note: Further information and advice relating to the as-constructed drawing presentation, as-constructed survey capture and associated guidelines for preparation of a compliant ADAC XML digital file are available on the webpage titled “As-Constructed Guidelines” and accessible at the Noosa Council Website: Planning & Development / Development Tools & Guidelines / As-Constructed Guidelines.
The “As-Constructed” drawings will require certification by a:
Qualified experienced Civil Engineer (RPEQ) confirming design intent and conformance with applicable standards and specifications, along with the relevant descriptions of assets, services and structures and;
The data must be in accordance with Council’s “Planning Scheme Policy 5 – Engineering Design Standards – Roads, Drainage and Earthworks”, and fully detail the levels for all engineering works including but not limited to the drainage network and structures, finished ground and pavement surface levels.
On Maintenance
All municipal works must be accepted ‘On Maintenance’ by Council in accordance with Council’s relevant Planning Scheme Policy prior to acceptance of the works. To achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
certification that all works have been undertaken and completed in accordance with the requirements of this Permit
as Constructed details in accordance with Council’s Planning Scheme Policy
Off Maintenance
Prior to requesting an Off Maintenance inspection the developer must provide a written request for the Off Maintenance inspection.
A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged where:
a Council inspection reveals works do not comply with approval requirements
submitted certification falsely states works comply with approval requirements.
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
Council has undertaken an audit check of the Operational Works drawings in relation to the proposed works.  The developer bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
Contact Council on 5329 6245 to arrange a prestart or an inspection giving a minimum of 5 business days notice of preferred inspection time.
If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time.
A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise
Environmental Advisory Notes
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
Accepted best practice standards include:
the Sunshine Coast Regional Council Manual for Erosion and Sediment Control V1.2 or other superseding document subsequently adopted by Council;
Best Practice Erosion and Sediment Control, International Erosion Control Association (2008)
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations under the ACH Act.
property notes
Not applicable.
VARIATION approval
Not applicable.
further development permits required
Not applicable.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

[word/footer1.xml]
Page 8 of 8

[word/header1.xml]
3

[word/header2.xml]
DEVELOPMENT ASSESSMENT DELEGATED REPORT
Log in to download the original file

Delegated Report - Code - Planning OPW18 0028.docx · 37 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.