Geotechnical Stability Assessment · MCU19/0008

of 33

Text shows just the words. Original shows the document exactly as it was published.

Project No. PG-2096                                                                                                         Page | 4
April 2019
Ref: PG-2096, 2019-02-21, GR VER 2
Andrew and Michelle Douglas – Geotechnical Stability Assessment - Proposed Residence, 22 Arakoon Crescent, Sunshine Beach




4.0 GEOTECHNICAL MODEL

The subsurface profile encountered in the boreholes consisted of initially very loose
to loose sands to depths of 1.9m in BH01 and 0.8m in BH02, overlying medium dense
to dense sands to the termination of testing. In Borehole 1, 600mm of very loose
gravelly sand was encountered.

The density of the sand has been interpreted on the basis of the DCP testing results.

Detailed borehole record sheets are appended to this report.

Groundwater or subsurface seepage was not encountered in the boreholes at the
time of drilling.

5.0 EARTHWORKS AND SITE PREPARATION CONSIDERATIONS

Earthworks are expected to comprise of a cut operation of up to 4m to create an
underground plant room and water tank. Minor filling removed from the excavation
and primarily adjacent Arakoon Crescent is expected.

Consideration should be given to maintaining the stability of the excavation
immediately adjacent Arakoon Crescent during earthworks.

It is recommended that the following site preparation and earthworks procedures be
carried out as part of the earthworks procedures during development.

          All earthworks operations should be carried out in general accordance with
           AS 3798-2007 "Guidelines on Earthworks for Commercial and Residential
           Developments".
          Trafficability across the site at the time of the investigation was assessed to be
           poor due to the steepness of the site.
          All topsoil (i.e. soil containing organic matter) and soils containing deleterious
           matter should be stripped from the construction area at the commencement
           of the earthworks operation.
          The majority of the soils on site will be suitable for re-use as structural fill,
           provided material is free of organic matter and deleterious material. It is likely
           that the soils require conditioning to bring the soils to optimum If the soils were
           overly moist, difficulty in achieving compaction of the materials will be
           encountered and moisture conditioning will be required.
          Imported fill should be of fair to good quality with a minimum Soaked CBR
           value of 10%, a maximum Iss=1.0% and a maximum particle size of 75mm or a
           ‘clean’ sand.
          All filling should be undertaken in layer thicknesses of approximately 250mm
           (or as appropriate for the compaction equipment being used). Fill should be
           compacted to a minimum dry density ratio of 95% Standard in accordance

Used in these records

About this file

File size
4.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Geotechnical Stability Assessment.pdf · 4.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.