Appendix D - Erosion and Sediment Control Plan

Attached to the e-mail Operational Works Application - DA Form 1 - Town Planning Report - Global Stability Assessment Report - Earthworks Compaction Report - Erosion and Sediment Control Plan - 36 Tunba Court Cooroy Mountain.

of 8

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
 

 

Catchments & Creeks Pty Lid

 

 

 

(b) Anchoring base of fabric

   
    
 
  

 

 

 

 

 

 

 

 

 

    

Woven or I 2000 mm (max) without
composite , tl support wire
sediment
fence fabric
L_

  
 
  
  
   
  

Fabric B

Fabric A

Fabric to fold around each stake one full turn.
Stake B to be drive tightly against Stake A.

The tops of both stakes to be secured with wire.

(c) Joining fabric - Method 1
(d) Installation without backing support

 
 
      
 

w Fabric 3000 mm (max) with top wire
>| Woven or [Ps OD mesh backing
7 a Straw bale ah Staple/tack Fabric B composite |
. 7 4 300 mm (min) rp sediment P< Post
om NM as, if . % fence fabric
H | 7 at NY? Lo
— rg - Sediment ( Fabric A yoo . 4m (max) *
We er OS Safety cap 200 (min)| | | secure fabric Top wire
~ HS Bis wee “ Support post option 1 hy to wire support
osx! nd SLY ‘ { 1500 mm¢ hardwood stake 4
Support post option 2

 

 

is

(e) Spill-through weir

 

(f) Placement of up-slope straw bale

‘Returns’ placed at 20 m spacing (max) if fence is located

3 m (max) with wire backing,
along the contour, otherwise 5 to 10 m depending on siope

otherwise 2 m (max) 1

   
   

  

Direction of flow 1.5 m (min)

All support posts placed
down-slope of fabric

   
 

buried
200 mm

Sediment fence fabric,

not filter cloth or shade cloth (i) Installation of sediment fence

1.5 kg/m steel star picket

(g) Joining fabric - Method 2

 

(h) Installation with top wire support

Notes:

1. Sediment fence to be installed along a line of constant ground elevation
wherever practical.

2. Both end of the sediment fence to extend up the slope at least 1m.

3. Support post to be spaced a maximum 2m unless the fence is supported
by a top wire or wire mesh backing, in which case 3m maximum spacing.

4. Fence ‘returns’ shail be installed at maximum 20m spacing if fence is
installed along the contour, otherwise 5 to 10m maximum spacing.

5. Minimum 4 staples or tie wires per stake.

 

Date:

Dec-09

Drawn:

GMW Sediment Fence SF-01

 

 

 

 

 

 

 
Log in to download the original file

Appendix D - Erosion and Sediment Control Plan.pdf · 7.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.