Log in to see the plans as drawn Part 4 Local Government Infrastructure Plan
4.1 Preliminary
(1) This local government infrastructure plan has been prepared in accordance with the requirements of the Planning Act 2016.
(2) The purpose of the local government infrastructure plan is to:
(a) integrate infrastructure planning with the land use planning identified in the planning scheme
(b) provide transparency regarding a local government’s intentions for the provision of trunk infrastructure
(c) enable a local government to estimate the cost of infrastructure provision to assist its long term financial planning
(d) ensure that trunk infrastructure is planned and provided in an efficient and orderly manner.
(e) provide a basis for the imposition of conditions about infrastructure on development approvals.
(3) The local government infrastructure plan:
(a) states in Section 4.2 (planning assumptions) the assumptions about future growth and urban development including the
assumptions of demand for each trunk infrastructure network
(b) identifies in Section 4.3 (priority infrastructure area) the prioritised area to accommodate urban growth up to 2031
(c) states in Section 4.4 (desired standards of service) for each trunk infrastructure network the desired standard of
performance
(d) identifies in Section 4.5 (plans for trunk infrastructure) the existing and future trunk infrastructure for the following networks:
(i) stormwater
(ii) transport
(iii) parks and land for community facilities
(e) provides a list of supporting documents that assist in the interpretation of the local government infrastructure plan in the
Editor’s note – Extrinsic material at the end of Section 4.
(f) this local government infrastructure plan excludes water supply and sewerage networks as these networks are the
responsibility of Unitywater as distributorretailer and are subject to their Netserv Plan.
4.2 Planning assumptions
(1) The planning assumptions state the assumptions about:
(a) population and employment growth
(b) the type, scale, location and timing of development including the demand for each trunk infrastructure network
(2) The planning assumptions together with the desired standards of service form a basis for the planning of the trunk infrastructure
networks and the determination of the priority infrastructure area.
(3) The planning assumptions have been prepared for:
(a) the base date (2016) and the following projection years to accord with future Australian Bureau of Statistics census years:
(i) mid (2021)
(ii) mid (2026)
(iii) mid (2031)
(b) the LGIP development types in column 2 that include the uses in column 3 of Table 4.2.
(c) the projection areas identified on Local Government Infrastructure Plan Maps LGIPPIASC1 to LGIPPIASC11 Priority
Infrastructure Area and Service Catchments in Schedule 3 —Local government infrastructure plan mapping and tables.
(4) Details of the methodology used to prepare the planning assumptions are stated in the extrinsic material.
Table 4.2—Relationship between LGIP development categories, LGIP development types and uses
Column 1 Column 2 Column 3
LGIP development LGIP development type Uses
category
Residential development Attached dwelling Caretaker’s accommodation
Dual occupancy
NOOSA PLAN 2020 Page 1 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.