Attachment J - Sewage Treatment Assessment
Table 1: Summary of typical flows for similar developments from available guidance
Guidance Development Type Typical Flows Estimated Centre Flows (existing
(L/person/day) + expansion)
(L/day)
Chapter 5: Table A of the Hostel 150 – 400
Planning Guidelines for Water Accommodation Total: 18,271 - 51,600
Supply and Sewage 2010
Table H4 of Australian / New Motels/hotels
Zealand Standard 1547:2012
Guests and resident
On-site Domestic Wastewater 220 28,380
staff
Management. 25 - 30 3,225 – 3,870
Restaurant (per diner)
Total: 31,605 – 32,250
Based on current flow data (72 – 114 L/person/day) it estimated that the expansion (129 persons) will generate
between 18,712 and 13,794 L/day. This is significantly less than the volumes provided by the guidance,
however, is reflected in similar developments that FPE have reviewed. On this basis the adopted hydraulic
loading for the Centre post development is 120 L/person/day to allow for variable flows. This equates to a total
daily flow rate of 15,480 L/day.
Peak design capacity
Given the increase in population and associated flow rates it is anticipated that the expansion will trigger the
requirement for the Centre to obtain a permit for an Environmentally Relevant Activity (ERA).
In accordance with section 63(4) of schedule 2 of the Environmental Protection Regulation 2008, the daily
peak design capacity for sewage treatment works is calculated using the following formulae—
EP = V/200 Where — V is the volume, in litres, of the average dry weather flow of sewage that can be treated
at the works in a day.
The peak design capacity for the development has been calculated using the above formula and the peak
occupancy flows to provide the number of Equivalent Persons (EP). This equates to an EP of 78 at full
occupancy during the Centres residential courses.
With reference to the Environmental Protection Regulation 2008 the following Environmental Authority will be
sought:
ERA 63 Sewerage treatment threshold 1(a)(i) – operating sewerage
treatment works, other than no-release works, with a total daily peak design
capacity of 21 to 100EP, if treated effluent is discharged from the works to an
infiltration trench or through an irrigation scheme.
p: 07 5357 9169 e: [email protected] PO Box 1250, Buddina Q 4575
f: 07 3102 9399 www.future-plus.com.au ABN 57 626 889 094
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.