Council archive · source document
08/0975 - Operational Works - Landscaping [As Published] · 142008.975
sunshine Coast Checklist - Applications Involving Land Regional Council Development & Land Use Sections IDAS APPLICATION This checklist should be used for any IDAS application. Please check each of the following items before accepting an application at the counter. 4. APPLICATION FORMS 1.1 Form 1 Part A 4.1.1. Ensure that the form is fully completed and is a current version. S 1.14.2 Inthe case of an MCU or Op Works below the high-water mark, owner's consent is required. 1.1.2.1 If there are multiple owners, the consent of each owner is required. 1.1.2.2 If the owner of the land is a company, either ACN No, Company name clearly indicated by signatory) or Company Seal required. 4.2 Form1 Part B-R Supporting Information 1.1.2 Ensure that for each box checked on Form A, the relevant additional Forms B-R are attached. [[email protected] Ensure that each of Forms B-R which are attached are fully completed. | /| 2. IDAS ASSESSMENT CHECKLIST * , . 2.4 Ensure that relevant sections have been checked and/or completed with regard to referrals Al isle . 2.2 Ensure correct parts of Form 1 are provided where required (ie most common are Part J for Clearing Vegetation, Part N for Contaminated land and Part P for Prescribed Tidal Works) f=] 3. ENVIRONMENTALLY RELEVANT ACTIVITIES 3.1. Ensure that Part G is completed if EPA referral is required. 3.2. Where EPA is delegated to Council (see * in ERA checklist), ensure that the correct application fee is paid and recorded on the application. (Refer Environmental Health for fees) 4. FORM 2 - REQUEST TO CHANGE APPROVAL 4.1 Ensure that relevant items have been checked and/or completed including information regarding applicant details along with owners consent if not current owner of land as shown on Council records. If over multiple properties on one or more sites, consent of Body Corporate is required. PLANS . e 5.1 Ensure that generally at least 6 sets of the Plan of Development (5 for Reconfiguration and Operational Ss Works) accompany the application. In addition ensure that each set is complete. 5.2 Ensure that 1 of the copies of the Plan of Development is in an A3 or A4 format and is - unbound. 6. SUPPORTING INFORMATION 6.1 Ensure that generally at least 6 copies of any report accompanies the application (5 for Reconfiguration | — and Operational Works). If the application is accompanied by a covering letter, ensure that it is capable of reproduction. _— 6.2 In the case of reports, ensure that 1 of the copies is in an A3 or A4 format and is unbound. 6.3. Additionally an electronic version is preferred where possible for ease of electronic record keeping _— 7. FEE 7.4 Ensure that the application fee, as determined from the Council’s adopted scale of fees, accompanies the application or has been paid. L « Land Use MCU applications; MCU applications including a Lot reconfiguration; Prescribed Tidal Works; Operational Work if Jetty or if including Landscaping. e Land Development Lot Reconfiguration applications and Operational Work not including Landscaping Please DO NOT leave the application at the counter and DO NOT deliver the application to Records. NSC g:Manduse\administrative processes\application checklist.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 20 pages
Page 2
IDAS REFERRAL AGENCIES TRIGGERS (Most frequent referrals) Please refer to IDAS Checklist for complete list YES COMMENT Please tick v Department of Main Roads (Concurrence or Advice) e State Controlled Road Dept Natural Resources & Water e Acid sulphate soils (Advice) e Clearing of native vegetation on freehold land (Concurrence) Environmental Protection Agency (Concurrence) * Contaminated land + Environmental Management/Contaminated Land Register * UXO "Land recently used as a ‘notifiable activity’ * Industrial land changed to sensitive uses (eg school) * Coastal related development. * Koala habitat e Wetlands (Advice only) * Environmentally Relevant Activity (for non-devolved Council as EPA) Queensland Transport (Concurrence) e Railway . Public Passenger Transport Energex or other responsible entity (Advice) ° Electricity Easements/Substations OUM (Concurrence) . SEQ Regional plan VARIOUS ° Conservation estate (Advice) . OTHER STATE AGENCIES + TRIGGERS OWNER’S CONSENT (State land) Department of Natural Resources and Mines EPA For further clarification refer to DAS Guides prepared by Department of Infrastructure & Planning. NSC g:\landuse\administrative processes\application checklist.doc
Page 3
© comiskeyGRoup Monday, June 02, 2008 Sunshine Coast Regional Coast PO Box 141 TEWANTIN Qld 4565 Subject: 71 Pacific Avenue Sunshine Beach Operation Works Application (Landscape) Please find attached application for landscape operation works. Attachments e (4) copies of landscape plans e Cheque for $1,625.00 e From1A&1B Yours sincerely, KR of Robert Comiskey Director p 07 3882 2533 £07 3882 5255 e [email protected] a 150 Todds Rood, Lawnton Qld 4501 PO Box 46, Lawnton Qld 4501 Comiskey Management Services Pty Ltd ABN 20 115 254 307
Page 4
INTEGRATED PLANNING ACT 1997 Part A, Version 3.1, 3 March 2008
Form 1 Development Application
Part A
Common details
OTE: Answer all questions unless directed to go to a particular question. Refer to the end of the form for advice on how to complete this form.
pplicant details (he App cents the perso respons ‘he for sir ag the pp’ caten and need nthe the owner ofthe Sad The Apo‘cants respons'hes fr ensuing the
ad an the (DAS Aps*: satan Fone comect Ths iin 7s re 2d upon by the Aszessouent Monger urd. ry eer et gone Whe Atens iy cad
ncztion By ioagng th noe App nts Reek grt aD respurns Stes presse od by the VA Any developirett pemstor pe. 2. sary
La OP ry be sued M 2 comsequerice Of th: 2pp ‘catun ar he nsued the pe eerty
Company/organisation name (if applicable) [Comiskey Group
(ndividual applicant/Contact person (if there is more than one applicant provide additional applicant details on an attachment to this form)
Title First name Lastname —|Comiskey
Postal address [Po Box 46 Lawnton
Contact telephone number |07 3882 2533 Mobile phone number 0407 522 298
Facsimile number 07 3882 5255 e-mail address [email protected]
[Details of the premises (re te land on whch the deveprcent proposed refer wo the udu at the end of ie fr.) }
1. Identify the premises by completing Table A, or Table B and/or Table C (ensure adequate information is given to identify the premises)
Table A {f the application is for a mobile and temporary E nvironmentally R elevant A ctivity (ERA), complete Table A only. Then go to Q2.
| "Name of each local government area in which the mobile and temporary ERA is proposed to operate. Od
| 4
OR
TableB Street address for the premises (tick applicable boxes below and insert property description in the table. Identify each lotin a separate rom)
() BX] Street address / lot on plan for the premises (Appropriate for most applications including building applications): Of
(ii) [] Street address /lot on plan for the land adjoining or adjacent to the premises (Appropriate for development in water e.g jetty,
pontoon etc) (Note: L oton plan details may be obtained from t#e documents, a ‘Rate’ notice, or from the local goverment}
Street Address Lot on plan description a
Tat Steet Pian bpe and Local government area (e.g. Logan
Na | No. StreetN ame and official suburbdocality name —_| PostCode} LotNo, Plan Number Caims)
1 71 | Pacific Ave, Sunshine Beach 31 RP149005 Sunshine Coast Regional Council
AND /OR
TableC Coordinates and/or a map of the premises (Appropriate for development in remote areas, over part of a fot in water (e.g. channel dredging in Moreton
Bay) etc.)
~ Coordinates
(Note: place each set of coominates in a separate row} Zone Local government area
. . . : Reference Daturn (applicable)
Easting Northing Latitude Longitude
1 (I pepass
CO weses
(FJ Other -
2. Identify if any of the following apply to the premises by completing Tables D, E, or F. (ow: in most instances, the premises will not involve any of
the folowing characteristics, however some applications may involve one or more of these characteristics - complete only if applicable)
Page 5
INTEGRATED PLANNING ACT 1997 Part A, Version 3.1, 3 March 2008
Table D Complete if the premises are adjacent t to or associated with a water body, watercourse or aquifer (e.g river, creek lake, canal}
[L
Table £ Complete if the premises are on Strategic Port Land under the Transport infrastructure Act 1994
Lot on plan description for strategic port land Port Authority for the lot
{1
Table F Complete if the premises are in tidal water
[1
3. _ Indicate the total area of the premises on which the 'e development is proposed: (Note: The total area may include land both above and below water}
Name of water body, _ watercourse or aquifer @fknown)
Name of local government for the tidal area {ifapplicable} Name of port authority for the tidal area (f applicable)
Total area of premises
1,614.00 Km [J hectares (Tick applicable unig
Fisting use of the premises }
4. Current use/s of the premises: (e.g. vacantiand, house, townhouses, apartment building shop, service station school sugar cane farming etc.)
[= |
5. Are there any existing easements on the premises? (e.g. for vehicular access, electricity, overland flow water etc)?
K No oO Yes - Ensure the type. location and dimensions of each easement are included in plans, submitted with the application
Proposal details 7]
6. Brief description of the proposal (e.g. 6 unitapartment building 30 fot residential subdivision a bore, aquaculture)
construction of childcare
7. Does the poposal include new buildings or operational work (including any services) on the premises?
O No XJ Yes - Ensure the nature, location and dimensions of the proposed works are included in plans, submitted with the application
Resource entitlement «'rpe'cctie! further 2 for: iiss peevicwd an the cian ser’ on tthe end of the fore ]
8. Does the application involve taking or interfering with a State resource and therefore require a resource entitlement? (eg the application
involves State land {leased and freehold), declared F ish Habitat areas, taking quarry material taking or interfering with water under the Water Act 2000, etr.}
oO No -Gowa9 | Yes - Complete Table 6 - provide details for each evidence required on a separate row, if applicable. £ vidence of resource
allocation or entitement must be submitted with the applicaton. You do not need to answer Q9 - go to the next section.
{Owner's consent (feppicen's) further eon ticns piu. dt-d 7 Ne advice secton at the end of the unt, ]
9. Complete Table H for applications involving a material change of use; reconfiguration of a lot; work on land below high-water mark and
not within a canal as defined under the Coastal Protection and ManagementA ct 1 995; or work on rail corridor land defined under the
Transport Infrastructure Act 1994 - provide details for each owner on a separate row or on an attachment tp this form if applicable.
Date consent
was obtained
1 Marcoola Custodians 71 Pacific Ave, Sunshine beach KCL 2 “e Oe
* Owner's signature cannot be provided on the farm if you intend to submit the application electronically. Owner's consent must be provided to the assessment manager on an
attachment containing appropriate written documentation of the owner's consent. If the owner is a company, 5127 of the Corporations Act 2001 (Cwealth) details how a
company may sign as owner. Templates for the provision of owner's consent are available on the IPA website .
Premises Owner's name/s Details of the premises owned
Table H
‘ .
and postal address (street address or loton plan description) Owner's signature
‘Attachments and supporting information :-« se 1 be! Use 2 sep rate rew &r exch ype of attechrenter-afarmeton aclu ng atu iten iequed
peer thes P 219 Please ensure all documentation submitted vath this form, including other P arts of F orm 1, or ovmer's consent ett, are securely attached to this Partof the F orm,
Description of attachment or information a .
Table | (0g Parte ofF orm 1, nner’ consent endonce of escurce Title (applicable) Date Method of delivery to
‘allocation ntifement plans, cravings, reports} {eg General Authority James Street! rafic R epor) assessment manager
Page 6
INTEGRATED PLANNING ACT 1997 Part A, Version 3.1, 3 March 2008
Portable Tong Service Leave (PLSL) levy ape ects be com: abu stag od amestuactont work « ‘hed ever $E2.000 only; ]
10. The Portable Long Service Leave Levy (PLSL) is not applicable to this application if any of the following apply: ( Tick box if applicable)
{J the application seeks a preliminary approval only;
(C1 the application is not for building and construction work under the Building and C onstruction Industry (P ortable L ong Service
Leave) Act 1997, section 3AA (e.g the application is only for a change of use, or for the following types of work carried out solely for
farming purposes: land clearing site preparation earthworks, fences, fodder harvesting clearing of encroaching vegetation, clearing of
regrowth, thinning vegetation or controlling weeds or pests):
L all costs, that relate to the work both directly and indirectly, are less than $80,000, inclusive of GST; or
( the work is being carried out under an owner-builder permit issued under the Queensiand Building Services Authority Act 1991 -
Complete and submit a Ql eave Notification and Payment F orm (no payment required if owner-builder permit number stated). The receipted form must be
sighted by the assessment manager before a development permit can be given
11. Is payment of a PLSL levy applicable to this application? (R efer Q10 and the Advice below for more information)?
C1 No - End ofParta
Yes - Answer 012 below
12. Has the PLSL levy been paid?
& No -(NOTE: An application can be lodged prior to payment of the applicable PLSL levy. However, the levy must be paid and the receipted form sighted by
the Assessment Manager before a development permit may be given for this application. To pay the levy you will need to complete and submita
Notification and PaymentF arm to QL eave.}
0 Yes - Complete Table J and submit with the application the ‘yelow’ {Local G ovemment’s (Council) /Private Certifier's) copy of the receipted QL eave F orm
OFFICE USE ONLY (Foruse by the Assessment Manager /P rivate Certifier) (Optional)
. “ ; Receiving officer’ ft
Fee (8)| lu, 7 -<~ | Date received | 3 / (oF eens ters ms & Refefence oe/ G78
2
NOTIFICATION OF ENGAGEMENT OF PRIVATE CERTIFIER
To: Council. | have been engaged as the private certifier for the building work referred to in this application.
Name BSA Certification number Building classification/s
| Date of
, engagement
QLEAVE NOTIFICATION AND PAYMENT (for completion by assessmentmanager or private certifier if applicable)
Date receipted
a - . . form sighted by 7 Name of officer who sighted the
Description of the work QLeave Project Number {Amount paid ($)| Date paid assessment form
manager _
[1
Privacy Statement
The information collected on F orm ? will be used by the 0 epartment of Infrastructure and Planning (D/P) in accordance with the processing and assessment of your Application.
Your personal details will not be disclosed for a purpose outside of the IDAS process, except where required by legislaton (including the F reedom of Information Act 1992) or as
required by Parliament This informaton may be stored in a DIP database. The information collected will be retained as required by the Public R ecords Act 2002.
Advice for completing Part A
Generat advice
. Part A of IDAS Development Application Form 1 must be completed and accompany all development applications. The applicant is responsible
for answering all questions fully and correctly, unless following a response there is a statement to go directly to another question. The
Assessment Manger may refuse to receive an application that is not properly made.
° The IDAS Assessment Checklist must also be completed for all development applications, other than those requiring assessment against the
Building Act 1975 only, i.e. those applications requiring the completion of Parts A and B only.
Page 7
INTEGRATED PLANNING ACT 1997 Part A, Version 3.1, 3 March 2008 ‘Applicant details . If the applicant is a company or organisation, a contact person must be nominated. The applicant's signature is not required to be provided under the IPA. Details of the premises ° The term ‘premises’ is defined by the IPA, schedule 10 to mean a building or other structure, and land (whether or not a building or other structure is situated on the land). The term ‘land’ is also defined to include the estate in, on, over or under the land. * Details of the land are not required if the application involves a mobile and temporary Environmentally Relevant Activity onty. Instead complete Table A. * The premises may be identified in a number of ways -- « Street address and lot on plan are most common and will apply to most applications. + Coordinates may provide the best means of accurately identifying the location of development proposed in waters, or on a relatively small development site distant from property boundaries on a large lot. Sufficient coordinates need to be provided to identify the boundary of the premises the subject of the application. Eastings and northings using GDA94 datum is preferred, but longitude and latitude and other (specified) datum such as Zone Reference or GS84 may be provided. e The definition of ‘water body' and ‘watercourse’ can vary from Act to Act. . StrategicPortLandis within a local government area but a local government's planning scheme does not apply onStrategicPortLand. StrategicPortLandis declared under the Transportinfrasbucture Act 1994, For further information go to IDAS Guide 11 (Development on strategic port land) and the Queensland Transport (Ports) website, le “Tidal water' is defined in the C oastal Protection and Management Act 1995 (Schedule) and ‘tidal area’ for a local government and for strategic Port land is defined in the IPA (schedule 10). Generally, the area below “high-water mark' (defined by the C oastal Act in relation to high water mark at spring tides) establishes the boundary of a tidal area. Land below high water mark is not within a tocal government's area unless provided for under the £ ocal G ovemmentA ct 1993. Unless otherwise provided for by legistation, a local government has no jurisdiction below high water mark. A tidal area for strategic port land is within the jurisdiction of the relevant port authority, while the Environmental Protection Agency generally has jurisdiction for a local government tidal area. However, the IPA gives focal governments jurisdiction for assessing and deciding applications for prescribed tidal works within the local government tidal area, and the planning scheme may be applied to that assessment (to the extent provided for in the code for prescribed tidal work). Resource entitlement . Section 3.2.1(5) of the IPA requires evidence of resource entitlement be given for applications if they involve taking or interfering with a prescribed State resource. Schedule 10 of the /ntegrated Planning Reguiaton 1998 (IPR) prescribes the State resources, including State- owned land, where evidence is required to be given, and the evidence required to support the application. Link to Integrated Planning Regulation. Section 3.2.1(10)(a)(ii) states an application cannot be taken to be properly made without the required evidence. . For applications involving the taking or interfering with water under the Water Act, the development application may be made at the same time as the request for resource entitlement, and the Department of Natural Resources and Water will accept the application as properly made. ° For S tate-controlled roads, a resource entitlement is not required for an activity that is exempt ancillary works or encroachment (identified by gazette notice under the Transport infrastructure Act 1994, section 50}, or if the activity requires referral to the Department of Main Roads. je Evidence may be required from more than one Department responsible for a State-owned resource, e.g. from the Environmental Protection Agency for quarry material below high water mark, and the Department of Natural Resources and Water in relation to the State-owned land above high water mark. Owner's consent . Section 3.2.1(3) of the IPA prescribes that an application must contain, or be supported by, the written consent of the land owner/s, if the application involves: a material change of use; reconfiguration of a lot; work on land below high-water mark and not within a canal as defined under the Coastal Protection and Management Act 1995, ot work on rail corridor tand defined under the Transport Infrastructure A ct 1994. . Evidence of this consent may need to be provided before the application will be accepted as properly made by the Assessment Manager, during the processes of the application or in the event of an appeal about the outcome of the application. . ‘Owner’ for the purpose of a lodging an IDAS development application means the person at the time of lodging the application, entitled to receive the rent for the land (or would be entitled to receive the rent for it if it were let to a tenant at a rent). . Templates are available from the IPA website for the provision of owner's consent as an attachment to this form. However other documentation may be used for providing owner's consent provided it is clear the documentation relates to the development application for the premises. ° Owner's consent, if required, must be provided even if the applicant is the owner. Owner's consent is not required for a mobile and temporary ERA. Portable L ong Service L eave (PLSL) Levy . The Building and Construction Industry Portable Long Service Leave Scheme provides long service leave entitlements to workers in the building and construction industry who would be unlikely to accrue enough service with one employer to qualify for long service leave. To fund the scheme, a Portable Long Service Leave Levy (PLSL levy) is collected on certain building and construction work carried out inQueensland. * The PLSL levy amount and other prescribed percentages and rates for calculating the levy are stated in the Building and Construction Industry (Portable Long Service Leave} Regulation 2002. Included in the amount collected by QLeave is the Workplace Health and Safety Fee and the Building and Construction IndustryTrainingLevy. * The Building and C onstuction Industry (Portable L ong Service L eave) Act 1991 (PLSL Act) defines the building and construction work subject to the PLSL levy and includes renovating, relocating, constructing, altering, demolishing, maintaining or repairing buildings, pools, roads, jetties, pipelines, fences or earthworks, and works for subdividing, irrigating or draining land. . The PLSL levy need not be paid when the application is made, but the PLSL Act requires the levy to be paid before a development permit may be issued. . The Assessment Manager must sight an approved form issued by QLeave advising of the status of the payment of the PLSL levy. Building and Construction Industry Notification and Payment Forms are available from anyQueenslandpost office or agency, on request from QLeave, or can be completed on the QLeave website at www.gleave.qid.gov.ay. For further information contact QLeave (Tel: 1800 803 481 Web: leave. gld.gov.au }
Page 8
Page 1 of 1 Trish Sweeney From: Robert Comiskey [[email protected]] Sent: Tuesday, 10 June 2008 11:49 AM To: Trish Sweeney Subject: Noosa Childcare, 71 Pacific avenue Sunshine Beach Warning: Email may contain offensive content. You are advised not to view email or attachments unless sent from a known and trusted source. Trish, Checklist and form E attached Thanks you Rob Comiskey - Director @ COMISKEY © GROUP 150 Todds Rd, Lawnton, Qid 4501 PO Box 46 Lawnton, Qld 4501 p. (07) 3882 2533 f, (07) 3882 5255 m. 0407 522 298 e. [email protected] 10/06/2008
Page 9
INTEGRATED PLANNING ACT 1997
» Form 1 Development Application
Part E
Building &4r operational works assessable
against a planning scheme
Part E, Version 3.1, 3 March 2008
‘Nature of the works) -
1, Nature of work that requires assessment against a planning scheme:
(1 Building work - Complete Table A (XJ Operational work - Complete Table 8
Table B
(i) What is the nature of the operational work?
[_] Roadworks (2) Stormwater [] Water infrastructure {[] Sewerage infrastructure
DX] Landscaping {([] Earthworks [J Drainage Works ([] Signage
(CJ Clearing vegetation under the planning scheme [_] Other - Specify below
DX] Development Permit (7) Preliminary approval
(iii) Is the operational work necessary to facilitate the creation of new lots (ie. subdivision)?
EJ No = [[] Yes - Specify the number of lots being created
atop
(No Yes - Complete Table 8 (a)
(ii) What type of approval is being sought? (wa7E: Ifyou have indicated muttiple operatonal works in question (i) above and your answers to this
question would be different for different operational work, it may be mare appropriate t provide these details in an attachment @ this forn)
(J Both (5 pecity boow)
(iv) Are there any current approvals associated with this application? (e.g DevelopmentPenmit or Preliminary Approval for MCU or reconfiguring
Table B (a) List of approval references Date approved
Date approval lapses (ifknown)
1 06/1180 5th March 2008
2. Whatis the dollar value of this operational work? (ie. the total value including GS, materials and laboup |$ 10000
‘Mandatory Information
3, Confirm that the following mandatory information accompanies this application
|
Confirmation of
lodgement
Method of lodgement
Plans, andspecifications if applicable, showing the nature and location of the proposed works (including the
extentofany cutand fil)
Confirmed
e-mail
OFFICE USE ONLY
Date Received Reference Numbers
Page 10
INTEGRATED PLANNING ACT 1997 Part E, Version 3.1, 3 March 2008 Advice for completing Part E General advice * — Part A must also be completed for all (DAS development applications. « The applicant is responsible for answering all questions fully and correctly, unless fotlowing a response there is a statement to go directly to another question. Qi A development permit authorises development to occur, while a preliminary approval is a step in the approval process and does not authorise development to occur
Page 11
INTEGRATED PLANNING ACT 1997 [DAS Assessment Checklist, Version 21.3, 9 May 2008
Pets LA) Dune Nena
IDAS
Assessment Checklist
DAS Development Application Form 1 is the approved form for all development applications under the Integrated Planning Act
1997 IPA). Form 1 is made up of various Parts,
Part A (Common details) of Form 1 must be completed for all applications. The relevance of other Parts of Form 1 depends on
the nature of the application.
Form 1 also includes this IDAS Assessment Checklist, which is used to assist in determining State assessment and referral
requirements, and the Parts of Form 1 relevant to the application.
Section 1 and all other relevant sections of the IDAS Assessment Checklist, as identified in the Table below, must be
completed for all development applications except those proposed on land in an urban development area, or for building work
requiring assessment against the Building Act 1975only.
For more information about development applications on land in an urban development area, refer to www.ulda.qid.gov.au.
For more advice about building applications refer to Part B of the IDAS Application Form.
Answering the following questions will assist you in determining which sections of the checklist must be completed for your application. If
unsure, phone or visit your local government or log onto the DIP website www.dip.qld.gov.au for help
For all IDAS development applications {except those for building work requiring assessment against the Building Act 1975only) - complete Section 1 of this
checklist
Does the application seek approval to materially change use of the premises?
ifyes -complete Section 2of this checklist Ces |[x)No
Does the application seek approval to reconfigure a lot? OYes No
IF yes - complete Section 3 of this checklist and PartF of (DAS Application Form 1. Assessmentis *y the local government -
Does the application seek approval to carry out operational work?
if yes - complete Section 4 of this checklist falYes |LJNo
Does the application seek approval to carry out building work requiring assessment against the Fisheries Act 1994 Ces |fsNo
ff yes - complete Section Sof this checklist
Have you received a referral agency response under section 3.3.2.0f the IPA, in relation to this development application?
if yes » complote Section 6 of this checklist ClYes |EINo
Does the application seek approval to carry out building work requiring assessment against a local government planning
scheme? C1 Yes |LINo
if yes - complete PartE of IDAS Application Form 1. Assessmentis by the local government
Does the application seek approval to carry out building work requiring assessment against the Building Act 1975?
if yes -go to Appendix 7 of this checklist for advice on building referrals, Complete PartB of IDAS Application Form 1. C1Yes |LINo
Assessmentis by a building certifier
SE CT 10 N 1 Section 4 must be completed for all applications that require completion of the IDAS Assessment Checklist.
HERITAGE ]
141A 's any part of the proposal intended to be carried out on a Queensland Heritage place under the Queensland Heritage Act 19922
[XJ No-cow178 =[_] Yes
WA achedine 4 pert? ladle eet ZIP Regileaen, schedule 2 abe J tem TT lab 2 tein PR IPA, sechan 7 Bn (Danninans tar ipinis used a develnguneay)
Page 12
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 21.3, 9 May 2008
1.1B Does the proposal involve development, other than development mentioned in the integrated Planning Act 1997 Schedule 9
{development that is exempt from assessment against a planning scheme), that is intended to be carried out on a place entered in
a Local Heritage Register under Part 11 of the Queensland Heritage Act 1992?
bs No -Go Q1.2 oO Yes - (Compiete Form 1, Part C2) This application requires assessment by the relevant local govemment against the IDAS
Code in the Queensland Hentage Regulation 2003 If the development involves building work and the local
govemmentis not the Assessment Manager for the application, the local govemmenthas jurisdiction as Concurrence
Agency.
& 1 Regulaten, schedule 2 table Fein TIA, IPA, secton
for terms used 7 dav.
ye
ie
REMOVING QUARRY MATERIAL; WILD RIVER AREA
1.2 Does the proposal involve removing quarry material from a watercourse or lake as defined under the Water Act 2000?
[LX] No-Goa13 [] Yes
hedule pat 1. sibie 5 dem 1: IP Regulation. schedule 2 ble 2 ite
BOE: Wild Rweis Act 20S section 438
77; 12 Regulation, schedule 1, table 5 item 2 (wild nvet area): Wame Act 200
ENVIRONMENTALLY RELEVANT ACTIVITY; WILD RIVER AREA 1
‘ a
1.3 Does the proposal involve an environmentally relevant activity (ERA), other than a mining activity or a petroleum activity?
BX] No-cowar4 [_] Yes
PUPA, sthedale & 6:
# LOS secooa Ate
be 2 kets Tard 23
ironeretiel Prowetion Act 14,
WITHIN THE LIMITS OF A PORT.
1.4 Is any part of the premises within the limits of a port under the Transport Infrastucture Act 1994?
No -Go t Q1.5
(Yes
IP Raguaton, schedule 2 atic 2 lems Wand bt
DECLARED FISH HABITAT AREA oe ” eS ny
1.5 Does any part of the premises adjoin a declared fish habitat area under the Fisheries Act 1994?
(No -Go 0 a16
oO Yes - ifanswers to questions in other sections of this checklist indicate that the proposed developmentis assessable under IPA, schedule
& this application requires assessment by the Department of Primary Industries and Fisheries (DPI&F). if DPI&F is not the
Assessment Manager for the application, the agency has jurisdiction as Advice Agency.
IP Regulation, scheduie 2 table 2 item 26
‘COMMUNITY INFRASTRUCTURE |
4.6 Is any part of the premises designated for community infrastructure?
No -Go@ Q17 :
(Yes
IPR: on, Sehodule & tabie 2 iiewe 7
17 Does the proposal involve the establishment or expansion of a waste water disposal system?
No -End of Section? [—] Yes
J? Regulaten, schedule 2 tbe 3 item 5
‘WASTE WATER MANAGE NENT
S E CcTIO N 4 - Section 4 must be completed when the application seeks approval to carry out operational work.
PLANNING SCHEME
41 Is any of the proposed operational work assessable under a planning scheme?
(No - Go Q42 LJ Yes - (Complete Form 1, Part £) Answer Qs47.7 - 41.7below.
‘ASSOCIATED WITH RECONFIGURING A LOT; RESIDENTIAL, COMVERCIAL OR INDUSTRIAL DEVELOPINENT INA WILD RIVER
AREA
4.2 (s any of the proposed operational work associated with reconfiguring a lot and the reconfiguration is also assessable?
KJ No -Gowaa3 ((] Yes
Page 13
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 21.3, 9 May 2008
shedele & pert i tabie 4 em 21? Re é:
le ths cada dors nati
VEGETATION CLEARING; KOALA CONSERVATION; WILD RIVER AREA oe eee 7
4.3 Is any of the proposed operational work for the clearing of native vegetation to which the Vegetation Management Act 1999
applies?
No -Gowaa4 [_] Yes
art tabie tems VA 1b, i Rey
Requistor, schedule t part a
area) Wid Reet Avi AG
4 fe 2 tate 2 tem
ditem hegetiton clear
wns SF and 43h
46H
2uem 3 hole
1 2A frege muon
TAKING OR INTERFERING WITH WATER; WILD RIVER AREA }
44 ‘s any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000 for taking or
interfering with water from a watercourse, lake or spring (other than using a water truck to pump water; and other than under
the Water Act 200Q section 20(2), (3) or (5)), or from a dam constructed on a watercourse or lake?
[X] No -Gow 4s Ov Yes - Answer f4)and (b) below
ebay
7, Peet 4 tadle 4 iterts Sanit GA: Yeaier Ars 0) sectan SpA hed ives
45 's any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 200Q for taking or
interfering with artesian water (other than using a water tuck to pump watery?
& No Go 046 O Yes - (Complete Form 1, Part K,) This application requires assessment by the Department of Natural Resources and Water
(NRW). I NRWis notthe Assessment Manager for the application, the agency has judsdiction as Concurrence Agency.
IPA, schedule & part 1 lative 4 item 3b) 1? Regulation, de 2 table 2 item a IP Regutation, schanule 1, part 3 able 4 tem 3
Wild Rivers cade Note: the cade dors nat comendy contin applicable provisions for igkin faring with artesian water}
46 ls any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000 for taking.
overland flow water (other than using a water truck to pump water)?
XI No -Gomaz7z [_] Yes- Answer (3) and (b) below
8 yuhyrtele & part i woke 4 shan Ford) IP Regelavion, schedule 2 tebie
Witt Reery Act Tia serton LA reineant wild mer diriars goa; Wid Rive:
BP Requtavan, scheduis 1, part habe @ nem 2 Water ACL CO vention UE cand oer atta),
“nde
47 Is any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000 for taking or
interfering with subartesian water (other than using a water truck to pump watery?
IX] No -Gowa4e ((] Yes
1 table «tem
GEA wid wer rent Wd
nade (Note the code does aot currently coitain applicable provisions fer sub artesian wa
pdt d ble 4
iiteroring with subavtesian water as assessable}
48 Does any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000 for
interfering with overland flow water (other than using a water tuck to pump water?
EX] No -cowaag C)¥ Yes - Answer both @)and (0) below
file 2 tote 7 wear @ HE Reghia ton,
fe 7, Dart 3 table 4 ite JA, Warer Ag? 7000 seca
EOE taetid
49 ls the proposed operational work for the following?
(i) For the construction of a referable dam as defined under the Water Act 2000 (] No OO Yes
(ii) To increase the storage capacity of a referable dam by more than 10% 0 No O Yes
If yes to either or both (i) or (ii) above - (Complete Form 7, Part Ks) This application requires assessment by the Department of Naural Resources and
Water (NRW). if NRWis not the Assessment Minager for the application, the agency has jurisdiction as
Concurrence Agency.
IPA schedule G part) ote 4 tem 4 IP Regulator, schedule 2 ible 2 tem 10
TAL WORK; WILD RIVER AREA Zz — |
4,10 ls any of the proposed operational work tidal work, other than excluded work defined under the IPA?
Xx No -Gow Qa C} Yes - Answer (a) and @) below
tibie ftom & IP chedule 2 table 2 items 2 Mane ie i
ad Kanegement Act oi TOAA diye near grea)
non schedule | part 4 bible 4 tems 4A and &
Page 14
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 21.3, 9 May 2008
COASTAL MANAG EM MEN NT DISTRICT; WILD f RIVE R AREA
TAL MANS —_- Woe j
4.11 Is any of the operational work proposed to be carried out within a coastal management district?
[X] No -cowaa12 (_] Yes
IPA scheduie & pe:
Coastal Propertion snd
WATERWAY BARRIER WORKS; WILD RIVER
YF HED
genes
1. Schedele 1. part 3 table 4 items Hand $
ct 2008 sechon 43
4.12 ts any of the proposed operational work for constructing or raising waterway barrier works under the Fisheries Act 1999?
BX] No -Go 9473 O Yes
s$abhe (goes RP §
en 4A
6. schedus %
qulain
DECLARED FISH HABITAT AREA; WILD RIVER AREA |
4.13 Is any of the operational work proposed to be carried out completely or partly within a declared fish habitat area under the
Fisheries Act 1994?
{X} No -Goma4r4
C1 Yes
4swin 7 IPA, »
tabie 4 den) 7,
B pari 2 wie 1 item 3
Ait XA seetans
IPA, schudule & pa
Reguiaton, sched
assessable codush 1? Regulavod. athedule « table é Hea Zi iP
REMOVAL, DESTRUCTION OR DAMAGE OF A MARINE | PLANT; WILD RIVER AREA }
4.14 ls any of the proposed operational work removing, destroying or damaging marine plants under the Fisheries Act 1994?
DX} No -Go to a 15 oO Yes
IPA gene:
Reyultha
vs mae = . arm “ <n = 2 ste tate
‘wito RIVER AREA a f
4.15 ts any of the operational work proposed to be carried out in a wild river area declared under the Wild River Act 2005?
(XJ No -Gowa4i6 (] Yes
IPA, schedule & part) abla 4 tein 12 IP Regulation schedule 2 table 2 ile 37% Wild Rivers Act 2004 secnons 42 4%
STATE CONTROLLED ROAD . 4d
4.16 Is any part of the premises located in part of a future State-controlled road, or within 100m of a State-controlled road?
DX] No -Endofsection¢ [_] Yes
IF Regqulatun, she
lable a item
Disclaimer:
While the Department of Infrastructure and Planning (DIP) believes that this information contained on this form and provided as part of
this process will be of assistance to you, itis provided on the basis that you will not rely on the information without first making your own
enquiries regarding the interpretation and application of the applicable legislation to your circumstances.
To the full extent permitted by law DIP expressly disclaims all liability (including but not limited to liability for negligence) for errors or
omissions of any kind or for any loss {including direct and indirect losses), damage or other consequence which may arise from your
reliance on this process and the information contained on this form.
Page 15
%. ww INTEGRATED PLANNING ACT 1997 Part B, Version 3.1, 3 March 2008 6 Development Applicatio ore Building work requiring assessment against the Building Act 1975 Nature of the building work 1. Nature of the proposed building work: [D4] New building or structure - Complew Table A J Removal - Complete Table B [J Alterations / additions - Complete Table A [[] Demolition - complete Tabie 8 [1 Change of building classification - Complete Table C Table A Description of new buildings, structures, alterations or additions Building Maximum No|Existing floor area) Proposed new classifications | of storeys | to be retained floor area @ [1 [childcare 1 440 Sqm 2. Are there any current approvals associated with this proposed building work? [] No ( Yes- Compiete Table 0 3. Whatis the dollar value of this proposed building work? ¢. the total value including GST, materials and labour) | $500,000.00 [Builder's detalls ¢fknon et the Sve of lodges ib | Name fndividuat or company name in full) Comiskey Management Services Postal address PO Box 46 Lawnton Telephone number |07 3882 2533 Mobile number |0407 522 298 _ Facsimile number |07 3882 5255 e-mail address [email protected] e BSA Licence Number or Owner-builder Number |1106895 her's details (Ine app:cantis respotiab:s fe ensui ay he Owners cubits ve comect / QOTE sf neve tere thon one Gain and tere’ore vate Den sate pp-cads 7 fr ap eddtess you tay need pro" de the toe. nt deat. s ud an atch ont ths form) Name/s éndividual or company name in full) }Marcoola Custodians Postal address PO Box 46 Lawnton Qld 4501 Telephone number |07 3882 2533 Mobile number |0407 522 298 Facsimile number 07 3882 5255 e-mail address [email protected]
Page 16
INTEGRATED PLANNING ACT 1997
{Construction details
4. Proposed construction materials
Part B, Version 3.1, 3 March 2008
CJ Double brick (41) OU Steel (60) LJ Curtain glass (50) LJ Stone / concrete (20)
External walls 1D Brick veneer (12) © Aluminium (70) C1 Timber (40) & Fibre cement (3)
C Other (80)
Frame (X) Timber (40) CJ Steel (60) L) Aluminium (70) LJ Other (80)
Floor () Timber (40) &] Concrete (20) LJ Other (80)
. 0 Tiles (10) {J Slate / concrete (20) CL) Fibre cement (30) CL) Steel (60)
Roofeoverings 15 Aluminium (70) (1 Other (80)
[Details of proposed new residential building work compiste only If app':cable) |
5. Dwelling type? (Tick applicable box és)
po -_4. | No of dwelling | No of new additional
Type of building work poe units tobe | self-contained
9 demolished | dwelling units |
(1 (i) Single detached house fncludes a new house /alterations to an existing house)
(ii) Relocated single detached house
OD iii) Kit house
(1 (iv) Existing transportable / relocatable house N/A N/A N/A
(J ()_ New transportable / relocatable house NIA NIA N/A
C1 Wi) Semi-attached house (e.g. duplex, duat occupancy)
C1 wii) Apartment, unit or flat attached to an existing house
C1 (iii) Apartment building / unit where units are layered one above the other
CO (ix) Attached housing (including row /terrace /townhouse)
Release of owner's details and availability of information
6. Does the owner of the land agree to release their name and the premises address for marketing purposes?
LlYes [No
7. Does the applicant have reasons why certain development information (e.g. private information about the applicant plans, drawings and specifications
for plans) should not be made available for inspection and purchase under IPA, sections 5.7.2 and §.7.4?
[IKI No
LJ Yes - Complew Table E
OFFICE USE ONLY
Date received |
FOR COMPLETION BY THE BUILDING CERTIFIER
Building classification/s of
‘approved building work
Building Services Authority (BSA) Insurance
receipt number
BSA Certification licence number
Page 17
INTEGRATED PLANNING ACT 1997 Part B, Version 3,1, 3 March 2008 Advice for completing Part B General advice : Part A must also be completed for all IDAS development applications. The applicant is responsible for answering all questions fully and correctly, unless following a response there is a statement to go directly to another question. For further information about completing this form go to IDAS Guide 9 (Building work documentation). (Q1_ indudes information required by the Australian Bureau of Statistics. (Q3_ Value of the building work is information required by the Austrafian Bureau of Statistics Builder's details: More than one builder may be involved in a proposal, e.g. one for construction of the hause, and another for the pool. Details are required for each builder and whether the builder is an owner-builder. BSA insurance is not required if the builder is an owner-builder. Owner's details: Owner's details are required to deliver various documents to the owner in accordance with the Building Act 1975 Q4 This information is required by the Australian Bureau of Statistics (ABS). The numbers in brackets are for use by the ABS only. (Q& This information is required by the Australian Bureau of Statistics and applicable for residential work only. A ‘dwelling unit’ is a self-contained abode of permanent residence (e.g. house, flat, unit, townhouse). Q@ The owner may choose whether they wish to receive marketing material. 7: IPA, sections 5.7.2 and 5.7.4 require the local government to make development information about building applications avaitable for inspection and purchase. However, this obligation does not apply to the extent the tocal government is reasonably satisfied a document contains sensitive security information, or information of a purely private nature about an individual, including, for example, someone's residential address.
Page 18
LANDSCAPE
SPECIFICATION
Proposed Childcare Centre - 71 Pacific Ave, Sunshine Beach
EXTENT OF WORKS
Contractor should take full account of documentation of Civil
Engineering, Hydraulic Engineering and Electrical Engineering
Works. Landscape works are to include the following:
4. Edging to planting areas / Gravel Installation
2. Topsoil - Supply and incorporation
3. Turf Supply & Lay
4. Containerised Plant Material - Supply and installation
5. Garden Mulch - Supply and Spread
6. Irrigation & Drainage
a Shaping of garden areas
8. Maintenance of landscape works (90days)
1. EDGING TO PLANTING
Concrete/timber edging is to be installed for all garden areas
as required to the detail shown on sheet LAQ2.
= TOPSOIL - SUPPLY AND INCORPORATION
Planting areas are to be progressively filled with premium
grade blended organic garden soil mix (sandy loam).
Soil supplier as well as intended mix is to be nominated.
Soil is to be mounded to facilitate good drainage to
hardstand areas (max. 1:3 grade) and is to finish 50mm
below edging after settlement. Organic additive
“dynamic lifter" or similar is to be incorporated throughout the
soil mix at the recommended rate.
A slow release fertiliser such as "osmocote” or its equivalent is
also to be incorporated with individual plantings in accordance
with the manufacturers recommendations.
2. TURF - SUPPLY AND LAY
a. “A” Grade Couch Species (or similar approved)
minimum sod depth - 25 mm.
b. Turf to be laid within 24 hours of being cut.
c. Allow for ground preparation and deposition of 50 mm
imported garden loam topsoil. Apply Dynamic Lifter or
equivalent as per manufacturers recommendations.
d. Turf to be close butted and rolled in accordance with
accepted practice to ensure a smooth even surface.
4. CONTAINERISED PLANT MATERIAL
Plant material is to be approved by superintendent prior to
planting. Planting is to be carried out in a manner consistent
with good horticultural practice. All >45 It. pot plant material
is to be guyed and staked as per Planting Detail — Advanced
Stock (Refer LAQ2). Smaller plant stock is to be staked as
necessary. Stakes shall not pass through rootball of plant at
time of planting or any time thereafter.
PLANT STOCK NOTES
Container sizes are noted with Pots in millimetres & Bags in litres.
Stock may be rejected if plants are:
a) Undersized proportional to specified container size or
if the root system is underdeveloped
b) Oversized proportional to specified container size or
severely root bound
c) Unbalanced or unchara cteristic of normal or specified
growth pattern for the species
d) Not suitably acclimatised for the specific environment
e) Diseased, infested with pests or suffering from other
form of significant stress
&: GARDEN MULCH
Organic Mulch: = Mulch shall be one inch hoop pine mulch to
all garden areas to a predominant depth of 100mm after settlement.
Mulch is to be graded to avoid placement against green plant
stems and overflow from purpose formed edges, kerbs and pathways.
6. IRRIGATION & DRAINAGE
(Irrigation for the project shall be carried out b y an experienced and
reputable irrigation contractor - Tenderers intending to handle the
irrigation themselves will be required to demonstrate proficiency in
this area). A fully automated and programmable irrigation system,
with rainswitch, is to be provided to all planting areas. All fittings
are to be fully effective and inconspicuously placed. Irrigation is to
serve all garden and turf areas of the site with lines placed through
conduits provided. The system should provide re gulated
application to all areas. Irrigation systems is to be guaranteed for a
period of 12 months against faulty materials and workmanship.
Ensure all gardens and Sand Pits have adequate drainage through
Ag. Pipes and direct drainage away from the building at all times.
ch SHAPING OF GARDEN AREAS
Planting areas are to be fin ished in a gently mounded fashion
to facilitate drainage of excess water and to show planting to
best advantage. Contractor is to seek confirmation of finished
levels prior to final plantings and application of mulch.
All garden beds to be well drained. Drainage shall be provided
for in areas that stay saturated for extended periods to the
potential detriment of plantings.
8. MAINTENANCE OF LANDSCAPE WORKS
a. Monitor plant performance and st ress constantly and take
appropriate remedial action. Soil moisture levels are
critical during early establishment.
b. | Prune and shape all shrubs and trees as required
ie. Clear trunk to 1200mm & damaged branches
Remove all stakes at 90 day inspection
Fertilise all garden beds at 3 months (low phosphorus type)
e. Contractor shall maintain an up to date written log book
to record inspection observations and actions.
a9
did¥lS NVIG3SW
AUS-dul x 2
GRE-ban x2
BAN-rob x 4
AUS-dul x 1
CAL-MF x2 ay :
AUS-dul x 1
CAL-sal x 2
LEP-pet x 1
AUS-dul x 2
CAL-sal x 1
CAL-LJ x 4
CAL-sal x 1
AUS-dul x4
PUL-WG x3
CAL-LJ x3
BAN-rob x 5
PUL-WG x3
AUS-dul x 4
BAN-rob x 5
CAL-LJ x 5
PUL-WG x3
ACR-impx 2
Softfall
GRE-ban x2 |
BAN-rob x 2.
ACR-imp x 1)
Sandpit
Y --SYZ-leu x3
BAN-rob x 8
o
HAR-pen x 1
DiA-cae x 12
ALE-cor x 2
RE-banx2
LEP-petx2
SYZ-leux3 ||
——
ACR-imp x 3
f Sandpit
CAL-sal x 1
LEP-pet x 2
4 GRE-ban x 2 PUL-WG
CAL-sal x4
lon x 2
All existing trees
are to be removed.
COR-rub x 3
LOM-lon x 5
DiA-cae x 50
LOM-lon x 18
AUS-dul x 1
GRE-ban x 2
BAN-rob x 3
R.L 54.25
“4
COR-rub x 4
LOM-lon x 6
PUL-WG x2
ACR-imp x 1
GRE-ban x 1
CAL-LJ x3
COR-rub x6
COR-rub x 10
LOM-lon x6
COR-rub x 5
Proposed Childcare Centre
71 Pacific Avenue, Sunshine Beach
aoe:
SYZ-leu x 16
(300mm pots
@1000crs)
NEIGHBOURING
BUILDING at
800mm wide garden
bed planted with
Syzygium leuhmannii
with court order.
1m spacings in acc.
Mel-thy x 29
AUS-dul A3
WAT-flo x 1
(200L)
All existing trees
are to be removed.
AT-flo x 1
CAL-LJ x3
AUS-dul x 6
HAR-pen x 1
ACM-hem x 1
ACM-hem x 1
NEIGHBOURING
BUILDING
VEGETATION SCREENING:
Waterhousea floribunda to be provided
as mature specimens in 200L containers
where noted on Landscape Plan.
LEGEND
EXISTING TREES TO BE REMOVED
Species as noted on plan
: ‘SEWER LINE
Refer Engineering Plans for details
EXTERNAL HARD PAVEMENT
| Refer Engineering Documentation
RUBBERISED SOFTFALL SURFACE
Colour, patiern to be confirmed
CONCRETE EDGE
Extruded Concrete Garden Edging
LARGE AND SMALL TREE PLANTING
\Refer Planting Schedule
SCREENING AND SHRUB PLANTING
Refer Planting Schedule
NEW TURF
(| Refer Specification
AMENDMENTS
18-03-08 | ORIGINAL ISSUE FOR OPW APPROVAL
29-04-08
AMENDMENTS TO LAYOUT BCJ
21-05-08 | AMENDMENTS TO LAYOUT ALP
c a d
LANDGRAPHICS
LANDSCAPE ARCHITECTS
Principal: Robert J. Burrell
2nd Floor, Esplanade & Second Bung, Caton Tree
email: andgraphik .
P.O. Box 18 Maroochydore 4558
Telephone: (07) 5443 4044
Facsimile: (07) 54434534
COPYRIGHT : No reprocuction of all or part of this crawing may be unccnaken without
‘The xpress wiitcn pomission of the author.
Project
Proposed Childcare Centre
71 Pacific Ave, Sunshine Beach
Clent / Project Managers
Tadpoles Early Learning Centre
Architects
Tabletop Architects
Drawing Tie
LANDSCAPE PLAN for
Operational Works Approval
NORTH ae
WINTER ‘PATH
W: £
‘
Nis ca Date: Morch 2008
1:125@ Al
2 Seam 1:250 @ AS
Job No: Drawing: Sheet Issue:
LGTP 1240 | LAO 01 OF c
Page 19
PLANT SCHEDULE
Childcare Centre Sunshine Beach
CODE BOTANICAL NAME COMMON NAME | MATURE | MATURE | POTSIZE | QUANTITY
HEIGHT | SPREAD | U.N.O.
TREES
ACM-hem Acmena hemilampra Bush Satinash 6m
CAL-sal Callistemon salignus Bottlebrush 4m : oe
CUP-ana Cupaniopsis anacardioides Tuckaroo 7m SPECIFIED
HAR-pen Harpullia pendula Tulipwood 6m
SYZ4eu Syzygium leuhmannii Small leafed Lilly Pilly 6m
WAT-flo Waterhousia floribunda Weeping Lilly Pilly 8m
>
Oo
LARGE SHRUBS =
ACR-imp Acronychia imperforata Fraser Island Apple 3m 1.5m 200mL 7
ALE-cor Alectryon coriaceus Beach Bird's Eye 4m 2m 200mL 2 =
CAL-MF Callistemon ‘Mr Foster Mr Foster Bottlebrush 2.5m 1.5m 200mL 2 a
GRE-ban Grevillea banksii Red Silky Oak 3m 2m 200mL 1 g —
LEP-pet Leptospermum petersonii Lemon Scented Tea Tree | 4m 2m 200mL 6 x oO
5 >
SMALL SHRUBS TUSSOCKS & GROUNDCOVERS a
AUS-dul Austromyrtus dulcis Midyim Berry 1m 2m 150mL 43
BAN-rob Banksia robur Swamp Banksia 1.5m im 150mL 27
CAL-LJ Callistemon ‘Little John’ Little John Bottlebrush 1m 1m 200mL 31 CONCRETE EDGE
COR-rub Cordyline rubra Red Berry Palm Lily 2m 0.5m | 200mL | 40 a. |
-~ DIA-cae Dianella caerulea Flax Lily 0.5m 0.3m 140mL 67
LOM-lon Lomandra longifolia Mat Rush 1m 1m 140mL 55
MEL-thy Melaleuca thymifolia Dwarf Melaleuca 1m 1m 140mL 55
PUL-WG Pultenea ‘Wallum Gold' Pea Flower 2m 1.5m 150mL 15
PHE-woo Phebalium Woombye Prostrate Phebalium 0.3m 1m 140mL 4
NOTE:
Advanced tree stock planting
street trees to have min. 1.2m
clear trunk
1800 x 50 x 50 Hwd stakes. All
pointed & driven vertically into
the ground outside the rootball
Approved securing material
such as Rubber tree ties or
50mm jutemat/hessian ties
in figure 8 loops secured
loosely to tree & fixed to stake
with flathead galv. nails
SPADE EDGE:
Ensure neat spade
edge is maintained
to all street trees
| pee i Mound at pit edge
Turf to 100mm deep friable
specified Z imported topsoil with
edge 20% organic content, light
compaction only.
900 depth and backfilled with
friable soil with max.
2% organic content, light
=
I
3 A r
<|< XA compaction only.
2 >8 RAR
2 RARE
&\5 ‘ Re Slow release fertiliser to
Ss 1 AS j i
8 : ive s manufacturers specifications
g
O¢ Tae
3 Fe Backfill original subgrade
o SAAAB mater. IGP COMPOON ony
Tes re Cultivate subgrade
SS to 150mm depth
oo (Generally 2x width of rootball) "
PLANTING DETAIL - ADVANCED STOCK 1:25@A1
selection to council approval. All
stakes to be chamfered, centrally
100mm nom. composted organic
mulch or council approved. Form
shallow dish drain to base of tree.
Tree pit to be excavated to min.
Select Garden Bed Mulch
Planting Area
Turf
100
We pyy yey
25
yf 100
MIN
ee
Topsoil
EXTRUDED CONCRETE EDGE DETAIL NTS
25 MPa concrete, pressure washed to expose aggregate.
A 0.5m2 finished sample must be provided to the site
superintendent prior to commencement for approval. The
sample may form part of the final product. Amendments to the
aggregate mix ratios, depth of aggregate exposure or CCS
saturation, may be made at this stage.
F62 Reinforcement located
central to the concrete width.
120
{ “a Compacted sub-base and
oo | SUb-grade Supply proof of
compaction to site
superintendant.
JOINTS
+ Contraction joints to be at minimum 2.0m centres. Joints to be 25mm depth saw cut or
approved equivalent.
+ Expansion joints to be at minimum 12m centres. To be located at edges of tile bands where
possible. 10mm thick closed cell cross linked polyethylene foam or approved equivalent.
FOOTPATH PAVEMENT - DETAIL
AMUIO
CONCRETE
FOOTPATH
FORT PLAY EQUIPMENT TO
AUST. STDS. SPEC. BY BTHERS.
°
C,
x
\— 100x100HWD “QO
TO AQ TIMBER EDGE
D4 Pa SO 100 x 100 HWD
4 a \V TIMBER EDGE
RUBBERISED SOFT
EDGE TO ALL SANDPITS
R.L 54.25
Sandpit
CHILDRENS
PLAY EQUIPMENT
AND SHADE
STRUCTURE
DESIGN BY OTHERS
ALL EXISTING TREES
ARE TO BE REMOVED
NEIGHBOURING
BUILDING
—. 800mm EDGED
GARDEN BED
NEIGHBOURING
BUILDING
100mm MULCH
LAYER
PROVIDE 90 DIA SLOTTED
PROVIDE IMPERVIOUS PIPE WITH GEOTEXTILE
MEMBRANE COATING TO SURROUND AND CAPPED TO
INSIDE OF PLANTER TO TOP FOR MAINTENACE ACCESS
MANUFACT. SPECIFICATIONS ns
PROVIDE GEOTEXTILE SURROUND
TO DRAINAGE CELL & AGGREGATE
LAYER
PROVIDE TOPPING LAYER
TO OBTAIN FALLS TO DRAINAGE
POINTS
PROVIDE AGGREGATE LAYER oa
TO TOP OF DRAINAGE CELL WITH
GEOTEXTILE SURROUND.
100mm Radius curve to
corner of planters
PODIUM PLANTER DETAIL
MATCH BUILDING
PROVIDE IMPORTED
PODIUM MIX
PROVIDE DRAINAGE CELL
TO BOTTOM & SIDES.
CUT TOFIT (5mm TOLERANCE)
DRAINAGE LINE TO
CONNECT TO STORMWATER
DRAINAGE SYSTEM
LEGEND
EXISTING TREES TO BE REMOVED
Species as noted on plan
SEWER LINE
Refer Engineering Plans for details
EXTERNAL HARD PAVEMENT
Refer Engineering Documeniation
CONCRETE EDGE
Extruded Concreie Garden Edging
* “+ RUBBERISED SOFTFALL SURFACE
‘| Colour, pattern to be confirmed
ge! LARGE AND SMALL TREE PLANTING
Refer Planting Schedule
¢ | SCREENING AND SHRUB PLANTING
"| Refer Planting Schedule
SSS
><| NEW TURF
Refer Specification
ULCHED AREA
Refer Specification
AMENDMENTS
issue | date
ORIGINAL ISSUE FOR OPW APPROVAL
AMENDMENTS TO LAYOUT
AMENDMENTS TO LAYOUT
c a d
LANDGRAPHICS
LANDSCAPE ARCHITECTS
Principal: Robert J. Burrell
2nd Floor, Esplunude & Second Bulking, Cotton Tree
Facsimile: (07)5443 4534
COPYRIGHT: No mprocuction of all or pan of this crawing may be uneertaken wahout
the xpress waitin permission of the author.
Project
Proposed Childcare Centre
71 Pacific Ave, Sunshine Beach
Clent / Project Managers
Tadpoles Early Learning Centre
Architects
Tabletop Architects
Drawing Title
LANDSCAPE DETAILS for
Operational Works Approval
LGTP 1240 | LA02
Page 20
Sunshine Coast. LAND USE SECTION FEES
Regional Council
RECEIPT TYPE
SALE OF DOCUMENTS
Superseded Planning Scheme Documentation - 520
Copy of Permit/Approval Letter 110
The Noosa Plan Documentation 111
APPLICATION FEES .
Material Change of Use - Code/Impact an
Consistent §21
Inconsistent : 521
Assessment under Superseded Planning Scheme 521
Modification to a Development Permit 521
Extension of a Currency Period. 521
Operational Works - Landscaping {42 S : 521
. e@ Bidg Work assessable against the Planning Scheme. . : 521
PRE LODGEMENT REVIEW :
Half Hour 522
One Hour §22°
ADVERTISING .
Purchase Advertised Applications 5 523
JETTIES : :
Jetty Application Fee - 524
Jetty Bond ‘ Lo ce 51
. : : (Category 4)
BONDS
” Performance Bond 51
, , , (Category 9) .
SIGNS . , :
Registration Fee : . 222
seu FEE : . .
: Search of Land Use Section file. 112
Liquor Licensing Request oo : 113
TOTAL § [o2g
NAME: ( us nek io : Gro.
ADDRESS: —_f>_ Bere |
, LAR Te st | .
FILENO: o&/ 40S --paATE: [e/g
RECEIPT NO: ' “UoY¥s(o Ye. Signature of TP Officer: PD frrives. i.
AUTHORITY NO:
Is 1228/[49/
Page 21
CALCULATION OF FEES . APPLICATION FEE TOTAL FEES MCU - CODE ASSESSMENT Details of Development Consistent 1.0 Inconsistent 3.0 FEE CALCULATION MCU - IMPACT ASSESSMENT Details of Development Consistent 1.0 Inconsistent 3.0 FEE CALCULATION OPERATIONAL WORKS Details of Development FEE CALCULATION TOTAL FEES
Used in these records
08/0975 - Operational Works - Landscaping [As Published]Related documentApplication case desk ↗
About this file
- File size
- 8.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.