Avocet Pde OPW - App A Civil · OPW20/0092

of 16

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Original PDF page 3, section 1. The text section number identifies this passage in the reader.

                                          GENERAL NOTES                                                                                                                                                                                                                          11. THE CONTRACTOR SHALL MAINTAIN A WRITTEN RECORD OF DATES OF ALL INSPECTIONS INCLUDING ANY CORRECTIVE
                                          1.   DO NOT SCALE DRAWINGS.                                                                                 TOPSOIL:                                                                                                                       ACTIONS TAKEN.

                                          2.   ALL DISCREPANCIES SHALL BE REFERRED TO THE SUPERINTENDENT FOR CLARIFICATION BEFORE PROCEEDING.         7.   PRIOR TO ANY EARTHWORKS ACTIVITIES, TREE STUMPS, BUILDING DEBRIS, ORGANIC RICH TOPSOIL AND SEVERELY
                                          3.   THE CONTRACTOR SHALL NOTIFY THE SUPERINTENDENT IN WRITING OF ALL VARIATIONS ARISING FROM THE                ROOT AFFECTED AREAS MUST BE REMOVED.                                                                                  EXISTING PAVEMENT:
                                               CLARIFICATION OF THE DISCREPANCY.                                                                      8.   ORGANIC RICH TOPSOIL MUST NOT BE USED IN FILL. IT SHALL BE STOCKPILED FOR RE-USE IN LANDSCAPING OR                    6.   WHERE PAVEMENT WIDENING IS PROPOSED, THE EXISTING PAVEMENT IS TO BE SAW CUT TO FORM THE JOINT, AS PER
                                          4.   THE CONTRACTOR SHALL SUBMIT DETAILS OF ANY ADDITIONAL COST ARISING FROM A VARIATION TO THE                  DISPOSED OF. TOPSOIL STOCKPILES SHALL NOT EXCEED 2m IN HEIGHT.                                                             STANDARD DRAWING IPWEAQ RS-170. THE DEPTH OF THE EXISTING PAVEMENT IS TO BE CONFIRMED AS PART OF THIS
                                               SUPERINTENDENT FOR APPROVAL, BEFORE PROCEEDING WITH THE WORKS.                                                                                                                                                                         PROCEDURE.

                                          5.   ALL WORK AND MATERIALS SHALL BE IN ACCORDANCE WITH THE DRAWINGS, SPECIFICATIONS, CURRENT RELEVANT      SUBSOILS:                                                                                                                  7.   ALL EXISTING PAVEMENT SURFACES ARE TO BE SWEPT CLEAN OF ALL LOOSE DEBRIS/FOREIGN MATTER PRIOR TO
                                               AUSTRALIAN STANDARDS, OTHER STATUTORY REQUIREMENTS AND TO THE SATISFACTION OF THE LOCAL AUTHORITY                                                                                                                                      APPLICATION OF SEAL.
                                                                                                                                                      9.   ENSURE SUITABLE GROUND COVER IS PROVIDED TO ALL EXPOSED SUBSOILS AS SOON AS PRACTICAL, TO MINIMISE
                                               AND THE SUPERINTENDENT.                                                                                     THE RISK OF SOIL EROSION, ESPECIALLY IF THE SOILS ARE DISPERSIVE.                                                     8.   AREAS OF EXISTING PAVEMENT CONTAINING POTHOLES, TO BE SAW CUT AND REPLACED WITH DEEP LIFT ASPHALT
                                          6.   NO WORK IS TO COMMENCE ON SITE UNTIL THE APPROVAL OF THE COUNCIL HAS BEEN RECEIVED IN WRITING AND AN                                                                                                                                   WITH A MINIMUM THICKNESS OF 100mm.
                                               OFFICIAL PRE-START MEETING WITH A REPRESENTATIVE OF COUNCIL AND THE ENGINEER HAVE BEEN HELD. THE                                                                                                                                  9.   IF UNDERLYING GRAVEL IS EXPOSED DURING MILLING OPERATIONS A PRIMER SEAL SHALL BE PLACED OVER THE
                                               CONTRACTOR IS TO OBTAIN A COPY OF THE MINUTES OF THE PRE-START MEETING AND SHALL COMPLY WITH THE       SUBGRADES:                                                                                                                      AFFECTED AREA.
                                               REQUIREMENTS THEREOF.                                                                                  10. SUBGRADES IN PAVEMENT AREAS SHALL BE PROOF ROLLED USING A MINIMUM FULLY LADEN WATER TRUCK (MIN. 20
                                          7.   ALL CONSTRUCTION SHALL COMPLY WITH THE RELEVANT WORK PLACE HEALTH AND SAFETY LEGISLATION.                  TONNE) AND ANY SOFT SPOTS OR UNSUITABLE MATERIALS SHALL BE EXCAVATED AND REPLACED WITH SELECT FILL.
                                                                                                                                                          THE SUBGRADE IS TO BE INSPECTED BY THE SUPERINTENDENT BY MEANS OF A PROOF ROLL, BY A MINIMUM FULLY                    STORMWATER DRAINAGE
                                          8.   A MINIMUM OF 24 HOURS NOTICE IS REQUIRED FOR ALL ENGINEERING INSPECTIONS, WHERE POSSIBLE.                  LADEN WATER TRUCK (MIN. 20 TONNE), PRIOR TO PLACEMENT OF ANY PAVEMENT LAYERS. THE SUBGRADE SHALL                      GENERAL
                                          9.   THE WORK AREA WILL BE MINIMISED TO FACILITATE CONSTRUCTION WHILST ENABLING CONTINUAL OPERATIONS OF         EXHIBIT NO VISIBLE SIGNS OF DEFORMATION UNDER PROOF ROLLING.                                                           1.   EXCAVATION, BEDDING AND BACKFILLING OF STORMWATER DRAINAGE PIPES TO BE IN ACCORDANCE WITH STANDARD
                                               THE NEIGHBOURING AREA, TO THE SATISFACTION OF THE PRINCIPAL AND SUPERINTENDENT.                        11. SUBGRADE TESTS SHALL BE UNDERTAKEN AND RESULTS SUPPLIED TO THE ENGINEER, TO DETERMINE THE                                   DRAWING IPWEAQ DS-0030 (TYPE 2).
                                          10. WORKING HOURS, COMMUNICATIONS PROTOCOLS, SITE ACCESS, AREA FOR CONTRACTORS FACILITIES/STORAGE AND           ADEQUACY OF THE PAVEMENT DEPTH DETAILED ON THE DRAWINGS.                                                               2.   ALL MANHOLES TO BE 1050mm DIAMETER IN ACCORDANCE WITH STANDARD DRAWING IPWEAQ DS-010.
                                              SITE SECURITY TO BE AGREED WITH THE PRINCIPAL AND SUPERINTENDENT.                                       12. THE SUPERINTENDENT MAY REQUEST ADDITIONAL SUBGRADE TESTING OR SUBGRADE REPLACEMENT FOLLOWING                           3.   ALL MANHOLE COVERS LOCATED WITHIN ROADWAY TO BE SOLID DUCTILE CAST IRON CLASS D IN ACCORDANCE WITH
                                          11. THE FOLLOWING HOLD POINT INSPECTIONS WILL BE REQUIRED;                                                      THIS INSPECTION.                                                                                                            STANDARD DRAWING IPWEAQ DS-019.
                                                 ● CONSTRUCTION PRE-START MEETING
                                                                                                                                                                                                                                                                                 4.   ALL MANHOLE COVERS LOCATED NOT WITHIN ROADWAY TO BE SOLID DUCTILE CAST IRON CLASS B IN ACCORDANCE
                                                 ● SET OUT
                                                                                                                                                      STOCKPILE MANAGEMENT:                                                                                                           WITH STANDARD DRAWING IPWEAQ DS-020.
                                                 ● DEMOLITION
                                                 ● SUBGRADE PROOF-ROLLS                                                                               14. CONTRACTOR TO ENSURE STOCKPILES ARE NOT LOCATED IN A POSITION WHERE THEY COULD BE WASHED INTO A                        5.   THE CONTRACTOR IS TO CONSIDER CONSTRUCTION LOADING ON EXISTING AND NEW STORMWATER PIPES AND
                                                 ● PRE-SEAL PROOF-ROLLS                                                                                   GUTTER, DRAIN OR WATER BODY, SUCH AS:                                                                                       STRUCTURES.
                                                 ● CONCRETE PRE-POURS                                                                                        ● ON A ROAD PAVEMENT;                                                                                               6.   ALL PIPE PENETRATIONS WILL BE FLUSH AND NEATLY MORTARED ON THE INSIDE FACE OF MANHOLES AND / OR PITS.
                                                 ● FINAL INSPECTION                                                                                          ● WITHIN AN OVERLAND FLOW PATH;
                                                                                                                                                                                                                                                                                 7.   THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ALL TRENCH EXCAVATION AND CONSTRUCTION IS IN
                                                 ● ADDITIONAL HOLD POINT INSPECTIONS MAY BE REQUIRED (TO BE DETERMINED)                                      ● ADJACENT TO STREAM BANKS.
                                                                                                                                                                                                                                                                                      ACCORDANCE WITH CURRENT CONSTRUCTION SAFETY ACT AND WORKPLACE HEALTH AND SAFETY LEGISLATION.
                                          12. THE CONTRACTOR SHALL PROVIDE ALL MANAGEMENT PLANS, INCLUDING TRAFFIC MANAGEMENT PLAN,                   13. CONTRACTOR TO ENSURE STOCKPILES ARE ADEQUATELY STABILISED. LONG TERM STOCKPILES CAN BE COVERED
                                                                                                                                                                                                                                                                                 8.   THE CONTRACTOR IS TO TAKE ALL POSSIBLE MEASURES TO ENSURE PROPER COMPACTION TO BACKFILLING OF
                                              ENVIRONMENTAL MANAGEMENT PLAN AND WORK PLACE HEALTH AND SAFETY PLAN FOR REVIEW AND APPROVAL OF              WITH MULCH OR TEMPORARY VEGETATION (GRASS).
                                                                                                                                                                                                                                                                                      TRENCHES AND STRUCTURES.
                                              PRINCIPAL AND SUPERINTENDENT, PRIOR TO CONSTRUCTION.                                                    14. ENSURE APPROPRIATE DUST CONTROL MEASURES EXIST FOR ALL STOCKPILES. ENSURE AN APPROPRIATE SEDIMENT
                                                                                                                                                                                                                                                                                 9.   THE CONTRACTOR IS TO PROVIDE A CCTV SURVEY OF ALL NEWLY CONSTRUCTED STORMWATER DRAINAGE ASSETS
                                          13. FOLLOWING COMPLETION OF THE WORKS THE CONTRACTOR SHALL CLEAN UP THE SITE AND DEMOBILISE TO THE              CONTROL SYSTEM IS LOCATED DOWN-SLOPE OF ALL STOCKPILES.
                                                                                                                                                                                                                                                                                      FOR APPROVAL BY THE ENGINEER AND / OR LOCAL AUTHORITY.
                                              SATISFACTION OF THE PRINCIPAL AND SUPERINTENDENT.
                                                                                                                                                                                                                                                                                 10. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO DEMONSTRATE HE HAS CAUSED NO DAMAGE TO EXISTING
                                                                                                                                                      SITE REHABILITATION:                                                                                                           STORMWATER INFRASTRUCTURE DURING THE CONSTRUCTION OF THESE WORKS.
                                          SURVEY                                                                                                      15. ENSURE THE SOIL SURFACE IS SCARIFIED PRIOR TO THE PLACEMENT OF TOPSOIL TO BREAK UP ANY EXCESSIVE                       11. ALL DEFECTS IDENTIFIED BY THE CCTV SURVEY WILL BE REPAIRED TO A SATISFACTORY STANDARD BY THE
                                          1.   THIS DESIGN IS BASED ON SURVEY PROVIDED BY SKYLINE SURVEYS.                                                COMPACTION, AND ENABLE THE APPROPRIATE KEYING OF THE SOIL LAYERS.                                                          CONTRACTOR. PAYMENT FOR THESE REPAIRS WILL BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR, UNLESS IT
                                                                                                                                                      16. SCARIFY LIGHTLY COMPACTED SOILS TO A MINIMUM DEPTH OF 100mm AND HEAVILY COMPACTED SUBSOILS TO A                            CAN BE DEMONSTRATED THAT THE IDENTIFIED DAMAGE WAS PRE-EXISTING AND THE RESPONSIBILITY OF OTHER
                                          2.   ALL LEVELS ARE TO AUSTRALIAN HEIGHT DATUM (AHD).
                                                                                                                                                          MINIMUM DEPTH OF 300mm.                                                                                                    PARTIES.
                                          3.   THE CONTRACTOR SHALL CONFIRM EXISTING LEVELS, FEATURES AND UTILITIES PRIOR TO CONSTRUCTION.
                                                                                                                                                      17. TURF MUST NOT BE PLACED ON EXCESSIVELY COMPACTED SOILS.                                                                12. UPON COMPLETION ALL STORMWATER DRAINAGE INFRASTRUCTURE WILL BE CLEAR OF DEBRIS AND OTHER
                                          4.   ALL ELEMENTS OF PROPOSED WORK TO BE SETOUT AND CHECKED BY THE CONTRACTOR'S LICENSED SURVEYOR AND                                                                                                                                      BLOCKAGES.
                                               ANY DISCREPANCIES ARE TO BE REPORTED TO THE SUPERINTENDENT.                                            18. ALL SITE REHABILITATION MEASURES SHOULD BE MONITORED, PARTICULARLY AFTER RAINFALL.

                                                                                                                                                                                                                                                                                 SUBSOIL DRAINAGE
                                          EXISTING SERVICES                                                                                           EROSION & SEDIMENT CONTROL
                                                                                                                                                                                                                                                                                 13. SUBSOIL DRAINS SHALL BE SUPPLIED AND CONSTRUCTED IN ACCORDANCE WITH MRTS03.
                                          1.   THE LOCATION OF ALL IN-GROUND AND OVERHEAD SERVICES HAS BEEN DETERMINED FROM FIELD SURVEY, DIAL        OBJECTIVES:
                                                                                                                                                                                                                                                                                 14. SUBSOIL DRAINS ARE TO BE GRADED AT 1% MINIMUM (DESIRABLE) AND 0.5% (MINIMUM).
                                               BEFORE YOU DIG ENQUIRIES AND INFORMATION PROVIDED BY THE SERVICE PROVIDERS / AUTHORITIES.              1.   THESE DRAWINGS ARE PROVIDED FOR GUIDANCE ONLY. THE CONTRACTOR SHALL ASSESS WHAT MEASURES ARE
                                                                                                                                                           REQUIRED TO SUIT THE PROPOSED CONSTRUCTION METHODOLOGY AND STAGING. SITE SPECIFIC CONSTRUCTION ESC                    15. SUBSOIL FLUSHING POINTS ARE TO BE PLACED AT A MAXIMUM DISTANCE OF 50m.
                                          2.   THE SERVICES ARE SHOWN ON THESE DRAWINGS FOR INFORMATION ONLY AND NO RESPONSIBILITY IS TAKEN FOR
                                               THE ACCURACY OR COMPLETENESS OF THE INFORMATION SUPPLIED.                                                   DRAWINGS TO BE UNDERTAKEN BY CPESC IN ACCORDANCE WITH ACEA REQUIREMENTS.                                              16. THE MAXIMUM LENGTH OF ANY SUBSOIL DRAINAGE LINE SHALL BE 100m.

                                          3.   NOT ALL EXISTING SERVICES HAVE NECESSARILY BEEN IDENTIFIED AND SHOWN ON THE DRAWINGS.                  2.   THE CONTRACTOR SHALL COMPLY WITH ALL STATUTORY REGULATIONS DURING THE CONSTRUCTION PHASE AND                          17. THE CONTRACTOR SHALL ENSURE THAT ANY EXISTING SUBSOIL DRAINS HAVE AN APPROPRIATE OUTLET.
                                                                                                                                                           MAINTENANCE PERIOD.
                                          4.   THE CONTRACTOR SHALL VERIFY THE LOCATION OF ALL EXISTING SERVICES ON THE SITE PRIOR TO COMMENCING
                                               WORKS.                                                                                                 3.   EROSION AND SEDIMENTATION CONTROL MAY BE AIDED BY MINIMISING THE AREA OF DISTURBANCE.

                                          5.   NO WORK IS TO BE UNDERTAKEN OVER OR WITHIN 3m OF EXISTING SERVICES PRIOR TO NOTIFICATION TO THE
                                               APPROPRIATE AUTHORITIES.                                                                               MANAGEMENT PRINCIPLES:
                                          6.   EXISTING VALVES, HYDRANTS, PITS, ACCESS CHAMBERS AND OTHER UTILITIES SHALL BE MODIFIED WHERE           4. THE MANAGEMENT PRINCIPLES EMPLOYED IN THESE DRAWINGS ARE IN ACCORDANCE WITH THE 'BEST PRACTICE
                                               NECESSARY TO SUIT FINAL FINISHED SURFACE LEVELS.                                                       EROSION AND SEDIMENT CONTROL' MANUAL, PUBLISHED BY THE INTERNATIONAL EROSION CONTROL ASSOCIATION (IECA).
                                                                                                                                                      THE BASIC PRINCIPLES ARE TO:
                                                                                                                                                           ●    MINIMISE THE AREA OF DISTURBANCE;
                                          CLEARING, GRUBBING AND DISPOSAL                                                                                  ●    CONTROL DRAINAGE PATHS UPSTREAM OF SITE AND AT OUTLETS FROM SITE;
                                          1.   CLEARING SHALL NOT OCCUR UNLESS PRECEDED BY THE INSTALLATION OF ALL NECESSARY EROSION AND SEDIMENT          ●    MINIMISE EROSION;
                                               CONTROL MEASURES. THE EXCEPTION WOULD BE ANY CLEARING NECESSARY TO ALLOW INSTALLATION OF THESE              ●    MINIMISE SEDIMENTATION;
                                               CONTROL MEASURES.                                                                                           ●    PROGRESSIVELY REVEGETATE AND REHABILITATE THE SITE.
                                          2.   CLEARING SHALL BE STAGED TO MINIMISE THE EXTENT AND DURATION OF SOIL EXPOSURE.                              ·    RELEVANT DECISION NOTICE CONDITIONS.
                                          3.   ESTABLISH ANY NON-DISTURBANCE OR EXCLUSION AREAS IDENTIFIED.
                                          4.   WHERE APPROPRIATE, IDENTIFY, ISOLATE AND/OR PROTECT RETAINED VEGETATION.                               CONSTRUCTION PRE-START MEETING:
                                          5.   CLEARING SHALL BE MINIMISED TO ONLY THE TREES AND VEGETATION NECESSARY TO UNDERTAKE THESE WORKS.       5.   THE CONSTRUCTION PRE-START MEETING IS AN OPPORTUNITY FOR ALL PARTIES TO DISCUSS CRITICAL ISSUES, SUCH
                                                                                                                                                           AS:
                                          6.   A SPOTTER-CATCHER SHALL BE PRESENT DURING ALL CLEARING OPERATIONS.
                                                                                                                                                               ● KEY OBJECTIVES OF THE EROSION AND SEDIMENT CONTROL PLAN;
                                          7.   CLEARING AND GRUBBING INCLUDES REMOVAL OF THE MAIN TREE ROOTS TO A MINIMUM DEPTH OF 1.0m AND THE                ● REQUIRED WATER QUALITY OBJECTIVES;
                                               REMOVAL OF SURFACE ROOTS AND VEGETABLE MATTER FROM THE TOP 0.3m BELOW THE NATURAL SURFACE LEVEL.                ● PERFORMANCE MONITORING AND INSPECTION PROCEDURES;
                                          8.   DISPOSAL OF ALL CLEARED VEGETATION AND RUBBISH SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THE              ● IDENTIFICATION OF THE RESPONSIBLE SITE OFFICERS;
                                               LOCAL AUTHORITY.                                                                                                ● IDENTIFICATION OF CRITICAL ENVIRONMENTAL CONCERNS;
                                                                                                                                                               ● REPORTING PROCEDURES FOR NON-COMPLIANCE ACTIVITIES AND EVENTS.
                                          9.   CLEARED VEGETATION CAN BE PROCESSED THROUGH WOOD CHIPPING AND THE MULCH PRODUCED PLACED IN
                                               INTERIM STOCKPILES FOR LATER USE IN EROSION AND SEDIMENT CONTROL OR LANDSCAPING PURPOSES.              ●    RELEVANT DECISION NOTICE CONDITIONS.


                                          EARTHWORKS / EXCAVATION                                                                                     SITE INSPECTION AND MONITORING:
                                          GENERAL:                                                                                                    6.   CONTRACTOR SHALL NOMINATE A PERSON RESPONSIBLE FOR INSTALLATION, MONITORING AND MAINTENANCE OF
                                                                                                                                                           CONTROL MEASURES (E.G. SITE FOREMAN).
                                          1.   ALL EXISTING UNDERGROUND SERVICES TO BE LOCATED AND MARKED PRIOR TO COMMENCEMENT OF EXCAVATION.
                                                                                                                                                      7.   ALL EROSION AND SEDIMENT CONTROL MEASURES SHOULD BE INSPECTED:
                                          2.   ALL EARTHWORKS ACTIVITIES INCLUDING STRIPPING, EXCAVATION, FILLING, COMPACTION AND TESTING, IS TO BE
                                                                                                                                                               ● AT LEAST DAILY WHEN RAIN IS OCCURRING;
                                               UNDERTAKEN IN ACCORDANCE WITH MRTS04, THE DRAWINGS, SPECIFICATIONS, CURRENT RELEVANT AUSTRALIAN
                                                                                                                                                               ● AT LEAST WEEKLY (EVEN IF WORK IS NOT OCCURRING ON-SITE);
                                               STANDARDS, OTHER STATUTORY REQUIREMENTS AND TO THE SATISFACTION OF THE LOCAL AUTHORITY AND THE
                                                                                                                                                               ● WITHIN 24 HOURS PRIOR TO EXPECTED RAINFALL;
                                               ENGINEER.
                                                                                                                                                               ● WITHIN 18 HOURS OF A RAINFALL EVENT.
                                          3.   STOCKPILES SHALL BE PROPERLY STABILISED.
                                                                                                                                                      8.   CONTRACTOR TO CHECK AFTER RAINFALL FOR PERFORMANCE INDICATORS SUCH AS EVIDENCE OF EXCESSIVE FLOW
                                          4.   EARTHWORKS SHALL AVOID THE EROSION OR SILTATION OF ADJOINING LANDS, STREAMS OR WATERCOURSES.                CONCENTRATIONS, EROSION PATHS DEVELOPING, SILT AND SEDIMENT ACCUMULATION.
                                          5.   ALL EROSION AND SEDIMENT CONTROLS TO BE INSTALLED AND FULLY OPERATIONAL PRIOR TO COMMENCEMENT OF       9.   CONTRACTOR TO CHECK DURING RAIN THAT FLOWS ARE NOT BYPASSING CONTROL MEASURES.
                                               EARTHWORKS.
                                                                                                                                                      10. WHEN A SITE INSPECTION DETECTS A NOTABLE FAILURE IN THE ADOPTED MEASURES, THE SOURCE OF THIS FAILURE
                                          6.   EARTHWORKS SHALL BE STAGED TO MINIMISE THE EXTENT AND DURATION OF SOIL EXPOSURE.                           MUST BE INVESTIGATED AND THE APPROPRIATE AMENDMENTS MADE TO THE SITE CONTROLS.




     COPYRIGHT ©                                                                               Associated Consultants           Client                                                                                                Drawn       Verified      Project                                                                      Drawing Title                                             Scale            Sheet Size
This drawing is subject to                                                                                                                                                                                                            M.K.P.      B.D.
copyright in accordance with the                                                              SKYLINE SURVEYORS                 RG STRATEGIC                                                                                          Designed    Verified
                                                                                                                                                                                                                                                                38 AVOCET PARADE                                                             GENERAL NOTES                                             AS SHOWN A1
agreement between Tod                                                                         SUITE 11C
Consulting pty ltd (tc) and tc's
client. This drawing shall only be                                                            BRIGHTWATER CORPORATE                                                                                                                   M.K.P.      B.D.          PEREGIAN BEACH                                                                                                                         Drawing Number
used for this specific project.                                                               CENTRE                                                                                                                                  Approved
                                                                                                                                                                                                                                      B. DOWNES
                                                                                                                                                                                                                                                  RPEQ No
                                                                                                                                                                                                                                                  14873
                                                                                                                                                                                                                                                             RDP:                                             PARISH:
                                                                                                                                                                                                                                                                                                              COUNTY:
                                                                                                                                                                                                                                                                                                                                                                                                       20538 - C02
                                                                                                                                                                                               Noosa: 07 5449 9600
This drawing shall not be used        B    22.05.20 ISSUED FOR OPW APPROVAL            M.K.P. 69 ATTENUATA DRIVE                                                               Sunshine Coast: 07 5329 3190 Mackay: 07 4840 2337
                                                                                                                                                                                                                                                             LOCAL AUTHORITY: NOOSA SHIRE COUNCIL
                                                                                                                                                                                                                                                                                                              PSM: 44279                                0      10     20    30     40    50       60   Sheet             Revision
for construction until marked as                                                                                                                                                                                                      Signed      Date       MCU APPROVAL:
                                      A    21.05.20 ISSUED FOR CLIENT COMMENT          M.K.P. MOUNTAIN CREEK, QLD 4557                                                                  PO Box 61, Noosaville, QLD 4566                                                                                       VERT DATUM: AHD
'issued for construction' in the
revision description.                Rev Date Revision Description                    Drawn PH. 07 5493 4877
                                                                                                                                                                             [email protected]      www.todconsulting.com
                                                                                                                                                                                               ABN 39 128 805 336                                 22.05.20
                                                                                                                                                                                                                                                             ROL APPROVAL: 51901.4274.02
                                                                                                                                                                                                                                                             OPW APPROVAL: TBC                                                                               MEASUREMENT BAR - INCREMENTS IN mm
                                                                                                                                                                                                                                                                                                                                                                                                       2 of 11              B

Used in these records

About this file

File size
4.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Avocet Pde OPW - App A Civil.pdf · 4.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗