Stormwater Management Report · MCU22/0087.01
The survey of the site has identified two 100mm diameter PVC pipes discharging into the Bottlebrush Avenue
drainage system. The internal stormwater drainage network, as well as the outlets from the roof drainage will be
discharged via this outlet as the lawful point of discharge.
An upstream catchment from the adjacent property to the northeast is expected to drain overland into the subject
site. The upstream catchment, of approximately 380m² is currently undeveloped and is expected to drain as overland
sheet flows across the property boundary. This area is shown in yellow in Figure 2.2 - Site Characteristics (Noosa
Council Intramaps, 2022).
Approx. upstream
catchment 380m²
Discharge via
2x100mm PVC
Kerb Outlet
Figure 2.2 - Site Characteristics (Noosa Council Intramaps, 2022)
P 1300 469 707 E [email protected]
Page 6 of 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Stormwater Management Report.PDFRelated documentApplication case desk ↗
About this file
- File size
- 1.8 MB (small file)
- File type
No other editions are linked here.