SUPERSEDED - Negotiated Decision Notice RAL21 0009

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Officer: 	Lisa Pienaar
Direct Telephone: 	07 53296514
Our Reference:	RAL21/0009
Your Reference:	210224
20 January 2022
KAM Gould & RD Gould & M Gould
C/- Danya Cook Town Planning
PO Box 9410
PACIFIC PARADISE  QLD  4564
[email protected]
Dear Sir/Madam,
Negotiated Decision Notice
Planning Act 2016
I refer to your application and the representations you made in respect to the decision notice. On 17 January 2021, Council decided your representations. This negotiated decision notice replaces the decision notice of 24 November 2021.
Details of the negotiated decision are as follows:
APPLICATION details
Application No:	RAL21/0009
Street address:	4-6 Hay St & 51 Ward St Tewantin Qld 4565
Real property description:	Lot 2 RP 72903, Lot 4 RP 72903, Lot 4 RP 77225
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
decision details
Council on 24 November 2021, decided to issue the following type of approval:
Development Permit to Reconfigure a Lot (Boundary Realignment - 3 lots into 3 & Access Easement)
In relation to representations, Council on 17 January 2021 decided to:
Agree to an administrative amendment to Condition 8
Refuse to delete condition 19 for the following reason:
The width of the proposed easement is not substantial only encompassing the retaining wall and the footings and is not considered an unreasonable imposition, nor will impact on the future development of the site.
currency period of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
PLANNING
When Conditions Must Be Complied With
Unless otherwise stated, all works required by the conditions of this Decision Notice must be completed prior to submission of the subdivision plan to Council for compliance assessment.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
210224	B	Plan of Development, prepared by Dayna Cook Town Planning	31/03/2021
All lot numbering on the subdivision plan to be submitted to Council for compliance assessment must remain as shown on the Approved Plans.
Currency Period
This development approval lapses if the use has not happened by 24 November 2025, unless an application to extend the currency period is approved by Council.
Property Access and Driveways
A sealed access driveway must be constructed extending from the existing formation in Hay Street to Lots 401 and 402. The works must be undertaken in accordance with an Operational Works approval and be generally in accordance with drawing number 2021-1087-06 Revision 2 prepared by Blackall Range Consulting Engineers dated September 2021.
Vehicle access to Lots 401 and 402 is limited to the constructed driveway only.  A clause must be included in the contract of sale for Lots 401 and 402 which requires vehicle access to be from the constructed driveway only, and which prohibits the driveway from being relocated without Council agreement. The following property notation or similar will be added to Council’s rates records to advise owners, prospective buyers and private certifiers of the access requirements:
“To ensure that the protection of the road reserve is maintained, vehicle access to this lot must be from the constructed driveway only unless otherwise approved by Council (refer to Council Approval RAL21/0009).”
Dwelling removal
The dwelling and shed must be removed prior to the sealing of the survey plan or alternatively and in the event part of the buildings remain, the building must comply with setbacks in Noosa Plan.
Stormwater Drainage
The site must be provided with a stormwater drainage system connecting to a lawful point of discharge. The works must be undertaken in accordance with an Operational Works approval and be generally in accordance with drawing number 2021-1087-13 Revision 2 prepared by Blackall Range Consulting Engineers dated September 2021. The works must include in particular:
all private structures (headwalls, scour protection, frog flaps etc) wholly contained within the private property;
discharge to the Hay Street road reserve in a manner that does not cause scour or damage to the road reserve;
the provision of inter-allotment drainage within proposed Lot 401 to convey runoff from proposed Lot 201;
the use of gravity stormwater drainage and not surcharge pits.
Condition 8 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk infrastructure.
Services
Reticulated electricity and telecommunication services must be provided to each lot in accordance with an approval for Operational Works and the standards and requirements of the relevant service provider.
Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications.
Certification must be submitted to Council from all relevant service providers (Energex, NBN and Unitywater) which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction.
Easements
An easement for access and services purposes must be registered against the title of proposed Lot 401 in favour of proposed Lot 402. The easement must be a minimum of 4.5m wide and widened where necessary to wholly encompass the access driveway, passing bay and all services.
A private easement for drainage purposes must be registered in favour of proposed Lot 201 against the title of proposed Lot 401. The easement must be a minimum 1.5 metre wide and widened where necessary to wholly encompass the drainage infrastructure
Unless otherwise agreed in writing by the relevant service provider, any public or third party infrastructure located on the subject site must be placed within an easement registered against the title of the property.
All easements must be designed in accordance with the planning scheme and granted at no cost to the Grantee. Where the Grantee is Council or a service authority, the easement documentation must be in accordance with the Grantee’s standard easement terms. Draft easement documentation must be submitted to Council for endorsement.
All works must be kept clear of any existing or proposed easements on the subject land, unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
All earthworks and associated retaining walls/batters must be undertaken in accordance with an Operational Works approval, be generally in accordance with drawing number 2021-1087-03 Revision 2 prepared by Blackall Range Consulting Engineers dated September 2021 and be contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council.
The works must include an additional retaining wall along the common boundary between Lots 401 and 402.
An easement for support for the retaining wall must be registered against the titles of proposed Lots 401 and 402. The easement must ensure the ongoing protection of the retaining wall.
All retaining walls must be designed and constructed in accordance with the planning scheme and must be certified by an RPEQ where exceeding 1.0m in height.  All retaining walls that are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade safety fence.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
Infrastructure Charges
All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges
Building and Construction Industry (Portable Long Service Leave) Levy
The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid.
Co-ordination of Operational Works Assessment
Additional application fees apply to Operational Work applications where the different aspects of the works are lodged separately. Significant savings in application fees will result if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
A preliminary Construction Management Plan must be submitted with the Operational Works application and must address the following:
traffic management during all aspects of the construction phase including:
a Traffic Management Control Plan in accordance with the Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction.
maintenance of safe pedestrian access for the areas affected by the works during and after daily construction has ceased.
proposed fencing to the site during the construction phase of the development.
approval of the Traffic Management Control Plan by the Department of Transport and Main Roads (DTMR) for any works on State controlled roads.
provision for worker car parking.
maintenance and protection of water quality and existing drainage lines through the construction site, through the implementation of appropriate erosion and sediment control measures
works programme identifying key components of the works and their respective durations
establishment of a communication protocol with the general public, adjoining owners and emergency services to advise of construction times, impacts on traffic, services and other relevant issues
Include a post out to the local residents advising of the proposed development, the expected time frames and the site contact details.
Include signage in prominent locations on the boundaries of the site advising of the proposed development, the expected time frames and the site contact details.
identification of complaint management procedures including:
contact details for the on-site manager
dispute resolution procedures
details on the location of external fill sites/sources, the haulage route, type of vehicle to be utilised during filling operations and frequency of usage. NB any damage to the existing road system and/or the access to the property that occurs as a result of haulage operations must be fully repaired at the applicant’s expense
it is acknowledged that the preliminary Construction Management Plan will be a draft document requiring finalisation upon appointment of the Principal Contractor employed to construct the works and a final document will be required to be submitted at the Pre-Start Meeting for the project.
Private Infrastructure
All private infrastructure for the development must be designed to meet the planning scheme requirements unless otherwise agreed by the relevant authority.
property notes
The following property notes will be placed against the subject property in Council’s property record system:
RAL21/0009 - Property Access Driveway
The following notation applies to approved Lots 401 and 402:
To ensure that the protection of the road reserve is maintained, vehicle access to this lot must be from the constructed driveway only unless otherwise approved by Council (refer to Council Approval RAL21/0009).
VARIATION approval details
Not applicable.
further development permits required
Type of Development Permit Required	Subject of the required Development Permit
Development Permit for Operational Works	Stormwater, Drainage work, Earthworks, Access
Development Permit for Building Works	All building work.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

Yours faithfully,

Lisa Pienaar
Development Planner

Enc:	Appeal Rights
Approved Plans/Documents

DECISION NOTICE HISTORY
Original Decision Notice – 24 November 2021.
Negotiated Decision Notice – 17 January 2022, with an amendment to conditions 8 and refuse to amend condition 19

	Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1)	Schedule 1 of the Planning Act 2016 states –
(a)	Matters that may be appealed to –
(i)	either a tribunal or the P&E Court; or
(ii)	only a tribunal; or
(iii)	only the P&E Court; and
(b)	The person-
(i)	who may appeal a matter (the appellant); and
(ii)	who is a respondent in an appeal of the matter; and
(iii)	who is a co-respondent in an appeal of the matter; and
(iv)	who may elect to be a co-respondent in an appeal of the matter.
(2)	An appellant may start an appeal within the appeal period.
(3)	The appeal period is –
(a)	for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or
(b)	for an appeal against a deemed refusal – at any time after the deemed refusal happens; or
(c)	for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or
(d)	for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or
(e)	for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or
(f)	for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person.
Note –
See the P&E Court Act for the court’s power to extend the appeal period.
(4)	Each respondent and co-respondent for an appeal may be heard in the appeal.
(5)	If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal.
(6)	To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about-
(a)	the adopted charge itself; or
(b)	for a decision about an offset or refund-
(i)	the establishment cost of trunk infrastructure identified in a LGIP; or
(ii)	the cost of infrastructure decided using the method included in the local government’s charges resolution.
230 Notice of appeal
(1)	An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that-
(a)	is in the approved form; and
(b)	succinctly states the grounds of the appeal.
(2)	The notice of appeal must be accompanied by the required fee.
(3)	The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to –
(a)	the respondent for the appeal; and
(b)	each co-respondent for the appeal; and
(c)	for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and
(d)	for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and
(e)	each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and
(f)	for an appeal to the P&E Court – the chief executive; and
(g)	for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate.
(4)	The service period is –
(a)	if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or
(b)	otherwise – 10 business days after the appeal is started.
(5)	A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6).
(6)	A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person.
231 Other appeals
(1)	Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable.
(2)	The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error.
(3)	A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter.
(4)	In this section –
decision includes-
(a)	conduct engaged in for the purpose of making a decision; and
(b)	other conduct that relates to the making of a decision; and
(c)	the making of a decision or failure to make a decision; and
(d)	a purported decision; and
(e)	a deemed refusal.
non-appealable, for a decision or matter, means the decision or matter-
(a)	is final and conclusive; and
(b)	may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and
(c)	is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground.
232 Rules of the P&E Court
(1)	A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal.
(2)	However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court

[word/footer1.xml]
Page 2 of 2

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 2

[word/footer3.xml]
Page 6 of 6

[word/footer4.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 6

[Attachment: image2.png (image text)]
ee) NOOSA COUNCIL
Log in to download the original file

SUPERSEDED - Negotiated Decision Notice RAL21 0009.docx · 336 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.