Rfi - C6535-25-FULL Set 2025-06-18

of 19

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                                            GENERAL NOTES:                                                                         EARTHWORKS NOTES:                                                                                          ROADWORKS NOTES:                                                                                   STORMWATER NOTES:
                                            1.   ALL WORK ON THIS CONTRACT IS TO BE CARRIED OUT IN                                 1. NOT ALL SERVICES HAVE NECESSARILY BEEN RECORDED
                                                                                                                                                                                                                                           1. THESE DRAWINGS ARE TO BE READ IN CONJUNCTION WITH IPWEAQ,                                          1. ALL STORMWATER PIPES ARE R.C.P. CLASS 3, R.R.J. U.N.O.
                                                 ACCORDANCE WITH WALSH CONSULTING ENGINEERS SPECIFICATION                             AND SHOWN ON THE DRAWINGS. THE CONTRACTOR IS
                                                                                                                                                                                                                                              NOOSA COUNCIL & MAIN ROADS STANDARD DRAWINGS.
                                                 AND TO THE SATISFACTION OF THE LOCAL AUTHORITY AND THE                               RESPONSIBLE TO LIASE WITH THE RELEVANT SERVICE
                                                 ENGINEER.                                                                            AUTHORITY PRIOR TO COMMENCEMENT OF CONSTRUCTION                                                                                                                                                            2. ALL STORMWATER MANHOLES ARE TO BE STD 1050 DIA U.N.O.
                                                                                                                                                                                                                                           2. THESE DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE
                                                                                                                                      TO DETERMINE THE LOCATION AND LEVEL OF ALL EXISTING
                                                                                                                                                                                                                                              LANDSCAPE ARCHITECT'S DESIGN DRAWINGS.                                                             3. ALL PROPOSED STORMWATER OUTLETS NOTED AS "STONE
                                            2.   THE CONTRACTOR IS TO CONTACT ERGON, TELSTRA, COUNCIL AND                             SERVICE UTILITIES.
                                                 OTHER SERVICE AUTHORITIES AND LOCATE EXISTING                                                                                                                                                                                                                                                      PITCHED HEADWALL" ARE TO BE DIMENSIONED IN ACCORDANCE
                                                                                                                                                                                                                                           3. SEDIMENTATION CONTROL DEVICES TO BE PROVIDED IN ACCORDANCE                                            WITH MAIN ROADS CONCRETE EQUIVALENT.
                                                 UNDERGROUND SERVICES PRIOR TO CONSTRUCTION.                                       2. THE CONTRACTOR SHALL IMPLEMENT THE SEDIMENT
                                                                                                                                                                                                                                              WITH THE ENVIRONMENTAL MANAGEMENT PLAN & AS DIRECTED ON
                                                                                                                                      CONTROL MEASURES TO PROTECT THE SITE FROM ALL
                                                                                                                                                                                                                                              SITE BY SUPERINTENDENT.                                                                            4. ALL WORK IS TO BE COMPLETED IN ACCORDANCE WITH WALSH
                                            3.   CONDUIT LOCATIONS IF SHOWN ON THE PLANS ARE PROVISIONAL                              CONSTRUCTION ACTIVITIES. ALL PERIMETER CONTROL
                                                 ONLY AND THE CONTRACTOR IS TO LIAISE WITH THE ENGINEER,                              MEASURES SHALL BE INSTALLED PRIOR TO DISTURBANCE OF                                                                                                                                                           CONSULTING ENGINEERS STANDARD SPECIFICATION.
                                                                                                                                                                                                                                           4. ROAD PAVEMENTS TO BE COMPACTED TO ACHIEVE A MINIMUM DRY
                                                 TELSTRA AND THE ELECTRICAL CONSULTANT FOR THEIR FINAL PLANS                          THE SITE.
                                                                                                                                                                                                                                              DENSITY RATIO (M.D.D.R.) OF 100% STD.                                                              5. ROADWORKS AND DRAINAGE SET-OUT INFORMATION IS
                                                 IMMEDIATELY PRIOR TO LAYING ROAD AND FOOTPATH CONDUITS.
                                                                                                                                   3. THE CONTRACTOR IS TO ALLOW FOR STRIPPING AND                                                                                                                                                                  AVAILABLE FOR THE CONTRACTOR VIA COMPUTER MODEL
                                                                                                                                                                                                                                           5. ALL CONDUITS TO BE IDENTIFIED BY BRASS PLAQUES ON KERB AND                                            PROVIDED BY WALSH CONSULTING ENGINEERS. HOWEVER,
                                            4.   THE ENGINEERING DESIGN IS BASED PARTLY ON A DATA TERRAIN                             STOCKPILING OF SOIL FOR FUTURE USE.
                                                                                                                                                                                                                                              CHANNEL AS PER IPWEA STANDARD DRAWING R-0160 U.N.O.                                                   WALSH CONSULTING ENGINEERS ACCEPTS NO RESPONSIBILITY
                                                 MODEL COMPUTER GENERATED FROM THE SITE SURVEY AND SOME
                                                 ELEMENTS OF THE SURVEY DATA ARE INTERPOLATED AND MAY VARY                         4. FILL IS TO BE PLACED IN ACCORDANCE WITH THE                                                                                                                                                                   FOR INCORRECT SETOUT FROM THE DATA PROVIDED.
                                                                                                                                                                                                                                           6. WHERE CONCRETE DRIVEWAYS ABUT KERB & CHANNEL, THE                                                     CONTRACTOR SHOULD CONFIRM THE CORRECT COORDINATES
                                                 FROM THE ACTUAL SITE CONDITIONS. THE CONTRACTOR SHALL                                REQUIREMENTS OF AS 3798-1996 "GUIDELINES ON
                                                                                                                                                                                                                                              CONTRACTOR IS TO CONSTRUCT A CROSS-OVER IN ACCORDANCE                                                 WITH THE MANHOLE SETOUT DATA PROVIDED ON THESE
                                                 LIAISE WITH THE ENGINEER AND SURVEYOR AND SET OUT THE                                EARTHWORKS FOR COMMERCIAL AND RESIDENTIAL
                                                                                                                                                                                                                                              WITH IPWEA STANDARD DRAWING R-0050.                                                                   DRAWINGS.
                                                 WORKS ONLY FROM APPROVED REFERENCE PEGS AND LEVEL                                    DEVELOPMENTS" - LEVEL ONE SUPERVISION AND TESTING.
                                                 BENCH MARKS.                                                                                                                                                                              7. PROVIDE ENERGEX AND TELSTRA CONDUITS UNDER DRIVEWAYS &
                                                                                                                                   5. MINIMUM RELATIVE COMPACTION:
                                                                                                                                                                                                                                              FOOTPATHS (IF REQUIRED).
                                            5.   THE CONTRACTOR IS TO ORGANISE HIS WORKS SO THAT EROSION,                              - RESIDENTIAL LOTS = 95% STANDARD AS1289.S.1.1
                                                 DEPOSITION OF SILT AND STORMWATER RUNOFF FROM THE JOB                                 - ROAD SUBGRADE = 98% STANDARD AS1289.S.1.1
                                                                                                                                                                                                                                           8. ALL WORK IS TO BE COMPLETED IN ACCORDANCE WITH WALSH
                                                 SITE DOES NOT EXCEED THE PRE CONSTRUCTION RATES AT ANY                                                                                                                                       CONSULTING ENGINEERS STANDARD SPECIFICATION.
                                                 POINT AS A RESULT OF HIS ACTIONS.                                                 6. THE FINISHED SURFACE SHALL BE FREE DRAINING
                                                                                                                                      (1:200 ON LOTS MIN).
                                                                                                                                                                                                                                           9. ROADWORKS AND DRAINAGE SET-OUT INFORMATION IS AVAILABLE
                                            6.   CLEAR ALL VEGETATION FROM THOSE AREAS TO BE EXCAVATED OR                                                                                                                                     FOR THE CONTRACTOR VIA COMPUTER MODEL PROVIDED BY WALSH
                                                 FILLED. IN OTHER AREAS WHERE CLEARING IS SPECIFIED. SELECTED                      7. MAXIMUM ALLOTMENT GRADE = 1:25 (EXISTING NATURAL
                                                                                                                                                                                                                                              CONSULTING ENGINEERS. HOWEVER, WALSH CONSULTING ENGINEERS
                                                 CLEARING ONLY IS TO BE CARRIED OUT BY RETAINING THOSE TREES                          SURFACE EXCLUDED), MINIMUM ALLOTMENT GRADE = 1:200
                                                                                                                                                                                                                                              ACCEPTS NO RESPONSIBILITY FOR INCORRECT SETOUT FROM THE
                                                 MARKED BY THE ENGINEER AND LEAVING THE AREA IN A CONDITION                           (UNLESS NOTED OTHERWISE).
                                                                                                                                                                                                                                              DATA PROVIDED. CONTRACTOR SHOULD CONFIRM THE CORRECT
                                                 SUITABLE FOR SLASHING.                                                                                                                                                                       COORDINATES WITH THE HORIZONTAL CURVE DATA PROVIDED ON
                                                                                                                                   8. THE CONTRACTOR IS TO STAGE EARTHWORKS WHEREVER
                                                                                                                                                                                                                                              THESE DRAWINGS.
                                            7.   THE CONTRACTOR IS TO PRESENT UP THE JOB FOR                                          POSSIBLE TO MINIMISE AREA OF 'OPEN' EXCAVATED AREAS.
                                                 ON-MAINTENANCE AND OFF-MAINTENANCE INSPECTIONS WHEN
                                                 DIRECTED BY THE ENGINEER WITH ALL PIPES, ROADS AND                                9. ALL WORK IS TO BE COMPLETED IN ACCORDANCE WITH
                                                 ALLOTMENTS FREE OF RUBBISH OR SILT AND WITH FOOTPATHS AND                            WALSH CONSULTING ENGINEERS TECHNICAL SPECIFICATION.
                                                 PARK AREAS SLASHED OR MOWN AND UNDERGROUND SERVICES
                                                 OPENED FOR INSPECTION.

                                            8.   NO WORK IS TO COMMENCE ON THE SITE UNTIL THE APPROVAL OF
                                                 THE COUNCIL HAS BEEN RECEIVED IN WRITING AND AN OFFICIAL
                                                 PRE-START MEETING WITH A REPRESENTATIVE OF COUNCIL AND THE
                                                 ENGINEER HAVE BEEN HELD. THE CONTRACTOR IS TO OBTAIN A
                                                 COPY OF THE MINUTES OF THE PRE-START MEETING AND SHALL
                                                 COMPLY WITH ALL REQUIREMENTS THEREOF.

                                            9.   ALL CONSTRUCTION IS TO BE SET OUT BY THE CONTRACTOR FROM
                                                 PEGGING OF ROAD CENTRELINE, MANHOLE POSITIONS, LOT STAKING
                                                 AND TBM'S PROVIDED BY THE PRINCIPAL'S LICENSED SURVEYOR

                                            10. THE CONTRACTOR IS TO MAINTAIN THE SITE DURING CONSTRUCTION
                                                FREE OF RUBBISH TO THE SATISFACTION OF THE SUPERINTENDENT.




                                                        REV        DATE                                        DESCRIPTION    BY     CHKD                                                    PROJECT:                                                                                                                           DRAWING TITLE:

             P 07 5443 4443
                                                                                                                                                                                              PROPOSED RESIDENTIAL SUBDIVISION                                                                                                  NOTES PAGE
             E [email protected]                                                                                                      ................         ................       at HOY ROAD, LAKE MACDONALD                                                                                                                                                                          CONSULTING
             W walsheng.net.au                                                                                                                       CHECKED            DIRECTOR APPROVAL
                                                                                                                                                                                              for INDIGO GROUP                                                                                                                                                                                     ENGINEERS
                                                                                                                                                                                  4665
CONSULTING   A 15/72 Wises Road, Maroochydore Q 4558
               PO Box 5512, Maroochydore BC Q 4558
                                                                                                                                                                        RPEQ -


ENGINEERS      A.B.N. 39 611 482 716                                                                                                                       FOR APPROVAL                       C This plan is Copyright. Other than for the purposes of and subject to the conditions prescribed under the Copyright Act, no
                                                                                                                                                                                              GARRRRRR!!!! THE PIRATE HAS LEFT HIS MARK!




                                                                                                                                                                                             part of it may in any form or by any means (electronic, mechanical, micro copying, photo-copying, recording or otherwise) be
                                                                                                                                                                                                                                                                                                                                DRAWING No:   C6535/25/L02                                   REVISION:
                                                                                                                                                           NOT FOR CONSTRUCTION              reproduced, stored in a retrieval system or transmitted without the prior written permission of Walsh Consulting Engineers. All
                                                                                                                                             Design: ILF       Drawn: EPW    Date:JUN 2025   intellectual property remains within Walsh Consulting Engineers. All enquiries should be directed to Walsh Consulting Engineers.   COUNCIL REFERENCE: RAL25/0001                                SHEET:      of
                                                       FILENAME : C6535-25-L02.dwg - DATE : 18/6/25 - 1:31pm                 A1 Sheet Size
Log in to download the original file

RFI - C6535-25-FULL SET 2025-06-18.pdf · 8.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.