132007.786.04 Request to Change Exsisting Approval
NOTES: For question 7
Under section 371 of the Sustainable Planning Act 2009, If the person making the request Is not the owner of the land to which the
approval relates, the request must be accompanied by the owner's consent.
However, owner's consent Is not required If the approval:
- relates to land the was acquisition land to which section 263(2)(d) of the Sustainable Planning Act 2C09 applied when the
application for the approval was made; or
is for building work or operational work for the supply of oomrmx*y'infrastructure on land designated for the community
Infrastructure; or
- the consent of the owner would rot be recuired under section 263(1) of the Sustainable Planning Act 2009 If a development
application were made.for the requested change.
Also, owners consent is not required if the Assessment Manager is satisfied that
- the number of owners of the land make it impractical to obtain owners' consent, and the requested change does not materially
affect the owners' land; or
- having regard to the nature of the proposed change, the owner has unreasonably withheld consent andthe requested change
does not materially affect the owner's land.
8. Does the request involve a Stir resource flt>!edttutderthe 3 i+9 Re8 !
Schedule 147
/111 D-Nn 0 Yes - complete below details
re of State owned resource:
Nature of Evidence required:
O Evidence of allocation of] entitlement to, the resource q Evidence the chief executive has agreed to the request
Attach a copy of the evidence required above
NOTES: For question 8
Section 370(3).and (4) of the Sustainable Planning Act 2009 requires that N an application for the development approval were made at
the time of making this request and evidence under section 284(1) of the Sustainable Planning AC, 2009 would be required to support
the application, this, request must be accompanied by the written agreement of the chief executive from whom-evidence would be
required under section 264(1).
Section 264 of the Sustainable Planning Art 2009 provides that If a development involves a State resource, a regulation may require
the application to be supported by certain evidence prescribed under regulation. Schedule 14 of the Sustainable Planning Regulation
2009 prescribes the State resources for which evidence is required to be given, and the evidence required, to support the application.
I/We, the applicant, declare that the above information is correct in all respects, at the time of lodgement of this
application with the Sunshine Coast Regional Counctl. Should any of the details given in relation to this application be
changed in the future, the applicant shall advise the Sunshine Coast Regional Council In writing prior to any such change
being implemented.
Signaturels MiC#► AEL- 2oA%r2S i!A2(".1 241et;0- $ Date 0S 02 201 L
3 of 4 2011112 Regional Strategy and Planning Request to Change Existing Approval and/or Extension to Relevant Period FM401
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
132007.786.04 Request to Change Exsisting ApprovalRelated documentApplication case desk ↗
About this file
- File size
- 3.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.