2015-03-31 I&S Committee - Item 5 - Attachment 1 - Munna Pt Bridge Repairs Level 3 Bridge Report
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
Option 1) – Construct new substructure Option 2) – Repair the existing bridge.
under bridge, as designed by Arup. 50 50-year life if maintenance schedule is
year deck life & 100 year substructure life properly followed. This option makes no
(if maintenance schedule is properly special allowance for sea level rises or
followed). From our review of the design associated canal erosion
report for this option, it appears that there
is no special allowance for sea level rises
or associated canal erosion.
Project delivery cost = estimated Project delivery cost = estimated
$8,092,247 + GST. This cost would be $2,783,000 + GST. This cost will be
incurred over 1-2 financial years. spread over 3-5 financial years.
Important note: These costs DON’T deliver Cost breakdown: Access craft & scaffolding
any extra bridge width. An additional $2.5 ($175,000) + traffic control (allow $20,000)
to $3 million would be required to supply + 6 new columns ($180,000) + pilecap
and install a 3.5 metre wide shared path on beam repairs ($600,000) + cathodic
one side of the bridge protection to pilecap beams ($310,000) +
60 pile encasements ($720,000) + deck
Cost breakdown: New substructure (piles, waterproofing & scupper linings (allow
columns, headstocks & removal of existing $100,000) + replace deck joints ($75,000)
piles, pilecaps & columns) = $6,031,588 + silane coatings to pilecap beams,
(per Arup 2011 report) + waterproofing & columns, headstocks, abutments and deck
coating underside of existing bridge deck underside + sides ($130,000) + clean up
(allow $200,000) + replace deck joints and coat all stressing bar ends (allow
($75,000) + cathodic protection of pilecaps $20,000) + design & project management
and piles to ensure 100 year life (allow costs (allow $ 200,000) + contingency
$380,000) + clean up and coat all stressing (allow 10%) + GST.
bar ends (allow $20,000) + design &
project management costs (allow
$650,000) + contingency (allow 10%) +
GST.
2017 Maintenance: Recoat bridge traffic 2017 Maintenance: Recoat bridge traffic
barriers and handrailing = allow $50,000 + barriers and handrailing = allow $50,000 +
GST GST
Page 24 of 31
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.