Detailed engineering design of Option 2 will be required, before commencing
construction. An RPEQ Engineer experienced in bridge design can design the columns.
The impressed-current cathodic-protection system will need to be designed by a
specialist engineer: it is common for these to be designed and constructed by specialist
contractors with their own engineers.
Construction work should be carried out by a specialist contractor, or by an experienced
bridge contractor with a specialist subcontractor. Conventional building or civil
contractors are not suitable for this type of work.
References
AS5100.5 Australian Standard – Bridge design—Concrete, 2004, Standards Australia
AS5100.7 Australian Standard – Bridge design—Rating of existing bridges, 2004,
Standards Australia
Bertolini, Elsener, Pedeferri, Polder, Corrosion of Steel in Concrete – Prevention,
Diagnosis, Repair, 2004, Wiley-VCH
Humphreys, Setunge, Fenwick, Alwi, Strategies for Minimising the Whole of
Life Cycle Cost of Reinforced Concrete Bridges Exposed to Aggressive Environments,
2007, QUT
Islam, Akhtar, A Critical Assessment to the Performance of Alkali-Silca Reaction (ASR) in
Concrete, 2013, Canadian Chemical Transactions
Page 28 of 31
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.