1 ACCESS & MANAGEMENT PLAN

 

Refer to Architect and Engineering documentation for access and management plan.

 

 

2 ENVIRONMENTAL PROTECTION

 

NOISE CONTROL

The Contractor is required to take all practical precautions to minimise noise resulting
from work under the Contract. Fit all motorised construction equipment with noise
suppressors and use so that noise is minimised. Do not use loud hailers. Wet saws are
to be used to cut pavers, within a suitable enclosure to the approval of the
Superintendent. Wet cutting to be in accordance with Engineering Guidelines for
Queensland Construction Sites: Soil Erosion & Sediment Control (1996).

SOIL EROSION CONTROL

Minimise erosion of soil from any lands used or occupied in the performance of the work
under the contract. Soil erosion controls and measures to be in accordance with
Engineering Guidelines for Queensland Construction Sites: Soi! Erosion & Sediment
.Control (1996), Environmental Protection Act (1994), and Environmental Protection
(Water) Policy (1994)

PESTS

Do not introduce weeds, phytophthora, insect or animal pests to the property. As in
accordance with Engineering Guidelines for Queensland Construction Sites: Soil Erosion
& Sediment Control (1996).

 

 

3 WEED ERADICATION

 

Eradicate weeds by environmentally acceptable methods using a non-residual
glyphosphate herbicide in any of its registered formulae, at the recommended maximum
rate. Regularly remove, by hand, rubbish and weed growth that may occur or recur
throughout planted and mulched areas. Continue eradication throughout the course of
the Works and during the Planting Establishment Period.

‘

 

 

4 GENERAL

 

Refer Civil Engineer for Bulk Earthworks and Excavation.

Do not disturb services. Locate all services before commencing any excavation and
cultivation. Refer to Civil Engineer for service locations. Excavate / cultivate areas within
500mm of services by hand.

 

 

5 LOCALISED EXCAVATION

 

Excavate and dispose all surplus material to allow for depths required for all landscape
elements below:

General Planting areas: 300mm

 

 

 

 

Used in these records

About this file

File size
3.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_0604 - Response to Information Request [As Published].pdf · 3.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.