ORDINARY MEETING MINUTES 16 JUNE 2022
Stormwater Drainage
42. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and the Queensland Urban Drainage Manual, and must include in
particular:
a. the detention system generally as described in Site Based Stormwater
Management Plan, prepared by ADG, dated 28th October 2021;
b. provision for the extent of inundation outside of batters of bioretention devices to
be confined to grassed areas only not to impact pathways, structures or the pool
and associated infrastructure for any event up to and including the 1%AEP at year
2100. A plan showing the extent of inundation and details of proposed signage for
grassed areas subject to inundation are to be provided with the application for
operational works;
c. extension of the site stormwater system to accommodate runoff from any external
catchment areas which drain onto the subject site at the time of the operational
works application being lodged. Any flowpath through the site which conveys
external catchment flows is to be provided with a drainage easement in favour of
the external property, with registration of the easement required prior to
commencement of use;
d. the use of gravity stormwater drainage and not surcharge pits to the maximum
extent practicable. Surcharge pits may only be used where the catchment is
composed of roof surfaces only;
e. provision of rainwater tanks for the capture and reuse of roofwater for the irrigation
of communal landscaping; and
f. accommodation for both severe storms or severe blockage of the underground
drainage network. A Severe Storm/Severe Blockage Assessment for the drainage
system proposed for the site is to be provided with the development application for
operational works, and is to demonstrate that finished floor levels will not be
inundated under either a severe blockage of the underground drainage network in
the 1%AEP event at year 2100, or for a severe storm exceeding the 1%AEP based
on design blockage.
Stormwater Quality Management
43. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and the latest
version of the Water Sensitive Urban Design Technical Design Guidelines for South East
Queensland, and must include in particular:
a. stormwater quality treatment devices of a size and location generally in accordance
with those shown in Site Based Stormwater Management Plan, prepared by ADG,
dated 28th October 2021;
b. bioretention devices which:
i. are designed generally in accordance with the Bioretention Technical Design
Guidelines (Water by Design, 2012)
ii. are designed generally in accordance with IPWEQA Standard Drawing No.
DS-073, DS-075, DS-076, and DS-078
iii. are provided with a free-draining outlet from the sub-soil drainage system
44. Permanent educational signage must be erected to educate the residents of the
development about the function of the bioretention device(s). The dimensions, standard,
presentation and location of the educational signage must be in accordance with an
Operational Works approval.
Page 37 of 43
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.