Council archive · source document
Request for Further Information - 010.2008.00000200.001 [As Published] · 142008.200
Daniel Smith, 5449 5106
Email: [email protected]
Application Ref: 2008/200
22 February 2008
Middap Ditchfield Architects
Cnr Mary & Thomas Streets
NOOSAVILLE QLD 4566
Dear Sir or Madam:,
Re: Application for a Development Permit for 08/0200 Operational Works -
Landscaping, Carparking & Access, Frontage Works, Stormwater Drainage,
Site Civil Works and Erosion & Sediment Control situated at 15 Duke Street
SUNSHINE BEACH described as LOT: 201 RP: 48113
I refer to the above application and wish to advise that following preliminary
examination of the plans, the following information is required to be submitted:-
1. An amended landscaping plan with the following changes:
1.1 Replace Casuarina littoralis with another suitable species, chosen from
Planning Scheme Policy 3 (Landscaping Plants & Guidelines).
1.2 Replace Syzygium ‘Bush Christmas’ species with another suitable species,
chosen from Planning Scheme Policy 3 (Landscaping Plants &
Guidelines), that would achieve a minimum mature height of 4-5 metres.
1.3 Remove all landscaping plants and works (i.e. dry creek bed) from road
reserve and replace with 3 suitable street trees and grass. The street tree
species shall be of a suitable mature height to comply with Outcome 7
(services and utilities) of the Landscaping Code.
2. Plans by SCG Consulting Engineers indicate that there is an existing footpath
across the frontage, when in fact no footpath exists – please amend these plans.
3. The location of the visitor car park does not comply with condition 28 (MCU
2007/1045). The visitor car park is located in the manoeuvring path to unit 1
garage. Vehicles cannot enter or exit this garage if a vehicle is occupying the
visitor bay. The assess/driveway layout needs to be revised to comply with
condition 28.
Please provide four (4) copies of all information that you are providing. In addition, it
would assist Council if you could also provide an electronic copy of your response.
Pursuant to the conditions of the Development Permit for a Material Change of Use
please note that all bonds and contributions are required to be paid prior to the issue of
the Operational Works approval.
Award Winner - Australian Clean Beach
Challenge 2004 Litter Prevention
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 1 page
Page 2
Please be aware that under Section 3.2.12 of the Integrated Planning Act, the applicant
is to respond to any information request within 12 months of the request or otherwise,
the application lapses.
Under the provisions of the Integrated Planning Act 1997, you as the applicant, have
three options available in response to this Information Request. You may give the
assessment manager (in this instance Council) and each referral agency (if any):-
1. all of the information requested; or
2. part of the information requested together with a letter asking the assessment
manager and each referral agency to proceed with the assessment of the
application; or
3. a letter:-
stating that you do not intend to supply any of the information requested; and
asking the assessment manager and each referral agency to proceed with the
assessment of the application.
The above information is required to be submitted, prior to assessment of the
application. If any further matters arise as part of assessment of this application, you
will be advised accordingly.
Should you have any further queries in relation to the above, please do not hesitate to
contact me on the above number.
Yours faithfully,
Daniel Smith
ASSISTANT PLANNING OFFICER
Award Winner - Australian Clean Beach
Challenge 2004 Litter Prevention
Used in these records
Request for Further Information - 010.2008.00000200.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 10 KB (small file)
- File type
No other editions are linked here.