Delegated Report - Code - MCU22 0139 CHANGED FROM COUNCIL REPORT [As Published] · MCU22/0139
Very large file (12.8 MB): the original may take a few minutes to open or download. The page text below is quick to read.
DA07 7 Section A prepared by The Drafty 12/03/24
DA08 7 Section B prepared by The Drafty 12/03/24
DA09 7 Section C prepared by The Drafty 12/03/24
DA10 7 Section F, G, H, I and J prepared by The 12/03/24
Drafty
Amendments • Delete the rooftop terraces and associated structures.
• Comply with the side (northern) setback requirements.
• Comply with the Plot Ratio requirements of the Noosa Plan
2020.
*(Refer to Advisory Note)
Nature and Extent of Approved Use
4. The premises must be used as a Dual Occupancy, it is not approved to be used as Multiple
Housing and/or Visitor Accommodation or any other residential use as defined by The Noosa
Plan.
5. The communal swimming pool must not be used in a manner that affects the amenity of
neighbouring premises through emission of noise, light, fumes or smoke.
Building Height
6. Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) before
the issue of a building permit and at completion of works which certifies the proposal will not
exceed the maximum height requirement of this Decision Notice.
7. The maximum height of the development must not exceed 59 AHD or 8 metres (whichever
is lesser) above the ground level including where excavation is undertaken.
8. The ground level must be reinstated around any basement level to ensure no part of which
is more than 1 metre above ground level, apart from the driveway entrance.
Performance Bond
9. Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of a Development Permit for Operational Works. The cash bond or trading bank
guarantee will be returned on performance of the conditions of approval less any costs
incurred by Council in respect of enforcing performance of this permit. Council reserves the
right to call upon the bond or guaranteed sum to effect compliance with conditions.
Water & Sewer Connections
10. An underground connection to reticulated water and sewerage must be provided to the
premises in accordance with the standards and requirements of Northern SEQ Distributor–
Retailer Authority (Unitywater).
11. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to the premises.
Sunset Clause for Completion of Approved Development
12. Pursuant to s88(1) of the Planning Act 2016, the uncompleted aspects of this development
approval lapses if the whole of the approved use has not happened by 17 November 2029.
Building Appearance
13. External design features, materials and finishes must be as shown on the Approved Plans,
with no inclusions or alterations made without approval in writing by Council.
Document Set ID: 22625793
Version: 14, Version Date: 03/04/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - MCU22 0139 CHANGED FROM COUNCIL REPORT [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 12.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.