002 ECM_22091773_v3_Decision Notice - Approved by Delegation of Authority MCU21 0231 · OPW22/0299

of 10

Text shows just the words. Original shows the document exactly as it was published.

               6.     For the purpose of preparing an Arborist Report, a qualified person is considered to be a
                      person with either:
                      a.      ISA certification; or
                      b.      a Diploma of Arboriculture in addition to a minimum of 3 years current experience in
                              the field of arboriculture.
                      Co-ordination of Operational Works Assessment
               7.     Additional application fees apply to Operational Work applications where the different
                      aspects of the works are lodged separately. Significant savings in application fees will result
                      if all works are lodged in a single application.
                      Preparation of a Preliminary Construction Management Plan
               8.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      traffic management during all aspects of the construction phase including:
                              i.       a Traffic Management Control Plan in accordance with the Manual of Uniform
                                       Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
                                       control measures prior to construction;
                              ii.      maintenance of safe pedestrian access for the areas affected by the works during
                                       and after daily construction has ceased;
                              iii.     proposed fencing to the site during the construction phase of the development;
                              iv.      provision for worker car parking;
                      b.      maintenance and protection of water quality and existing drainage lines through the
                              construction site, through the implementation of appropriate erosion and sediment
                              control measures;
                      c.      works programme identifying key components of the works and their respective
                              durations;
                      d.      establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic, services and other relevant issues;
                      e.      Include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details;
                      f.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager
                              ii.      dispute resolution procedures
                      It is acknowledged that the preliminary Construction Management Plan will be a draft
                      document requiring finalisation upon appointment of the Principal Contractor employed to
                      construct the works and a final document will be required to be submitted at the Pre-Start
                      Meeting for the project.
                      Infrastructure Charges
               9.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges




                                                                                                         Page 8 of 10
Document Set ID: 22091773
Version: 3, Version Date: 05/09/2022

Used in these records

About this file

File size
204 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

002 ECM_22091773_v3_Decision Notice - Approved by Delegation of Authority MCU21 0231.pdf · 204 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.