Skip to the record
Noosa's #1 Council Tracker.

Original source · versioned page text

Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL

of 30

Page text shows just the words. Original shows the document exactly as it was published.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                 Traffic Management Plan
                           Lake Macdonald Drive, Cooroy




99 Sandalwood Lane, Forest Glen Q 4556 | Phone: 07 5458 3300 | Fax: 07 5458 3388 | www.shadcivil.com.au | ABN: 68 162 606 377
Log in to download the original file

Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL.pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 29 pages

Page 2

                                                                                 Traffic Management Plan


Revision Status
  Revision              Author             Received / Approved                           Description    Date

                                                                               TMP for
       A         Andrew Hussey                                                                         24/09/20
                                                                               Comment/Approval




Document Acronyms
      Acronym                                                      Description

 CLO                    Community Liaison Officer

 COP                    Code of Practice

 DTMR                   Department of Transport and Main Roads

 KPI                    Key Performance Indicator

 MUTCD                  Manual of Uniform Traffic Control Devices (March 2019)

 NTO                    Nominated Traffic Officer

 QAS                    Queensland Ambulance Service

 QFES                   Queensland Fire and Emergency Service

 QPS                    Queensland Police Service

 RPEQ                   Registered Professional Engineer of Queensland

 TGS                    Traffic Guidance Scheme

 TMD                    Traffic Management Design

 TMI                    Traffic Management Implementation

 TMP                    Traffic Management Plan

 TO                     Traffic Officer

 TRUM                   Traffic and Road User Management Manual

 TSB                    Temporary Safety Barrier




IMS-04-05_D – Reviewed May 2019                     Document Uncontrolled When Printed                    Page 2 of 30

Page 3

                                                                                                       Traffic Management Plan


Table of Contents
1.     Introduction .................................................................................................................................................4

2.     Project Description .................................................................................................................................. 11

3.     Traffic Management Resources .............................................................................................................. 14

4.     Haulage ................................................................................................................................................... 15

5.     Human Resources ................................................................................................................................... 15

6.     References .............................................................................................................................................. 17

7.     Incidents .................................................................................................................................................. 17

8.     Existing Network Details .......................................................................................................................... 18

9.     Traffic Management Implementation ....................................................................................................... 19

10.    Risk Assessment ..................................................................................................................................... 20

11.    Appendix 1 - Risk Assessment ................................................................................................................ 22

12.    Appendix 2 - Construction Program ........................................................................................................ 23

13.    Appendix 3 - Haulage Movements .......................................................................................................... 24

14.    Appendix 4 - Traffic Data ......................................................................................................................... 25

15.    Appendix 5 - Staging Diagrams ............................................................................................................... 26

16.    Appendix 6 – Traffic Guidance Schemes ................................................................................................ 27

17.    Appendix 7 - Traffic Management Options Considered .......................................................................... 28

18.    Appendix 8 - Pedestrian Options Considered ......................................................................................... 30




IMS-04-05_D - Reviewed May 2019                                    Document Uncontrolled When Printed                                                   Page 3 of 30

Page 4

                                                                             Traffic Management Plan


1. Introduction
1.1 General overview

This Traffic Management Plan (TMP) is to identify and define the requirements and processes for the
management of traffic during the construction phase of Rural Subdivision Development at Lake Macdonald
Drive, Cooroy as highlighted in figure 1.1. This TMP details the overall traffic management approach to be used
by Shadforth’s Civil Pty Ltd (Shadforth) to ensure:

▪    The movement of traffic around, through or past or the works site/s is safe and efficient
▪    The traffic carrying capacity and performance of the existing roads and local road connections are optimised
▪    Delay and disruptions to traffic are kept to an absolute minimum
▪    The safety and amenity of road users and the public are assured
▪    The safety of road workers is assured.




Figure 1.1 Site Locality

1.2 Scope

This TMP will be used as a guide for coordination of all road users, during the duration of the works as required.
Traffic control and safety measures outlined in this report are intended to assist in maintaining a safe
environment for both site workers and members of the public.

The scope of this Traffic Management Plan includes the following;

▪    Description of works
▪    Timing and delivery of project
▪    Haulage routes
▪    Impacts on the road and pedestrian networks
▪    Location of traffic control devices

1.3 Legislation and design Standards

The TMP and associated Traffic Guidance Schemes (TGS) have been developed in accordance with the
requirements of the following documents;



IMS-04-05_D - Reviewed May 2019                 Document Uncontrolled When Printed                      Page 4 of 30

Page 5

                                                                                Traffic Management Plan


▪      Department of Transport and Main Roads “Manual of Uniform Traffic Control Devices” (MUTCD):
        o    Part 3: Works on Roads ( July 2019)
        o    MUTCD Supplementary Notes to Part 3
▪      TOD Engineers & project Managers Project Specific Specification
▪      Traffic Management for Construction or Maintenance Work COP 2008
▪      Workplace Health & Safety Act 2011
▪      Workplace Health & Safety COP Notice 2011
▪      Workplace Health & Safety Regulations 2011
▪      Traffic Management Construction COP 2008
▪      Traffic Controller Accreditation Scheme Approved Procedure (December 2017)
▪      Transport and Main Roads Specifications: MRTS02, MRTS02.1



 1.4 Objective of this Plan

This TMP summarises the overall traffic management strategy and traffic safety requirements, associated with
the earthworks, shoulder widening, vehicular access/egress and Construction Stages. The overarching aim,
being to ensure a coordinated approach to traffic management and the successful delivery of the program of
works, whilst minimising disruption to road users and the surrounding community.

The TMP provides an overview of measures to manage and control movement during the works. It sets out the
responsibilities for the safe and orderly passage of vehicular and pedestrian traffic around the site at all times
from the commencement of work on site. This TMP shall be updated and approved as required.

It outlines the commitment, responsibility and strategy to be adopted to ensure compliance with the traffic
management and traffic safety requirements of the ‘Transport and Main Roads Standard Specification –
Provision for Traffic’ (MRS02) and the MUTCD Part 3 Work on Roads. This plan seeks to ensure the certainty
of delivery of the prescribed traffic management and control devices and to minimise any disruptions to traffic.



1.5 Key Personnel and Out of Hours Contact Details
       Name                 Position     Company                   Phone                               Email

    James Harris   Project Manager      Shadforth          0417 736 105                 [email protected]

    Andrew
                   Traffic Officer      Shadforth          0450 607 330                 [email protected]
    Hussey

    Mark
                   Community Liaison    Shadforth          0400 524 763                 [email protected]
    Lonergan

    Mark           Health and Safety
                                        Shadforth          0400 524 763                 [email protected]
    Lonergan       Manager

    Darryl Hart    Site Supervisor      Shadforth          0407 395 496                 [email protected]

                   Police               Police             Emergency 000


1.6 Limitations of this Traffic Management Plan




IMS-04-05_D - Reviewed May 2019                    Document Uncontrolled When Printed                                  Page 5 of 30

Page 6

                                                                           Traffic Management Plan


This TMP developed by Shadforth considers the physical traffic and transport impact of the works on all road
users (not limited to but including cars, pedestrians, cyclists and public transport). This TMP is based on the
information contained in the contract documents, construction methods, program and site visits by the Traffic
Management Designer

If any part of the program or methods changes, it may be necessary for the TMP (and TGS’s) to be amended.



1.7 Document Structure



             DTMR                                                                               Stakeholder Expectations
     Standard Specification
      Provision for Traffic

                                                                                                      Traffic Data

            MUTCD
                                             TRAFFIC MANAGEMENT
                                              PLAN FOR PROJECT




                                                                                   Aftercare Plans
            TRUM                                                                    as Required




                                                Traffic Guidance
                                                    Schemes
      Road Planning and
        Design Manual




1.8 Distribution

Shadforth will develop and submit the TMP to the Contract Superintendent or Principals Representative.

It is intended that the TMP and the site-specific Traffic Guidance Schemes (TGS’s) will be continually updated
and amended, as required, during the contract period in response to any incidents, consultation/ meetings with
work force, traffic disruptions, audits or changes in the design and construction process.

1.9 Site Specific Traffic Guidance Schemes

TGS’s will be prepared for every scenario effecting relevant stakeholders necessary to complete the works.
These documents can be located in the appendices of this document.

The TGS’s will include detailed drawings that show proposed temporary signing and other traffic control device
layouts. The TGS’s will include details of:

▪    Lane or part road closures
▪    Major traffic control devices
▪    Approach speed / speed through works / departure speed
▪    Work site barrier locations
▪    Pedestrian and cyclist provisions
▪    Public transport provisions



IMS-04-05_D - Reviewed May 2019               Document Uncontrolled When Printed                                     Page 6 of 30

Page 7

                                                                             Traffic Management Plan


▪      Construction site access
▪      Access provisions for businesses
▪      Worker safety provisions
▪      Residents / property access
▪      Parking restrictions
▪      Approximate duration of works
▪      Aftercare

1.10       Approval of Traffic Guidance Schemes

It is the Principal Contractors responsibility to gain approval for the use of this TMP and associated TGS’s and
ensure that traffic management provisions are installed and maintained, in accordance with approved TGS’s
and current MUTCD requirements.

Any changes to an approved TGS can only be approved by a person with TMD certification. Any site-based
changes should be noted on the TGS with date and time and the TMI or TMD name of whom approved the
changes.

1.11       Traffic Management Devices

Shadforth will implement a structured management reporting system in accordance with the TMP. Shadforth
will provide, maintain and monitor the infrastructure, systems, services and resources, needed to manage the
effects of the construction activities on road traffic.

Regular inspection of the traffic management systems will ensure they continue to provide safe traffic conditions
for the travelling public. Inspections will be completed in accordance with Appendices A and B of the MUTCD
Part 3:

▪      Before Works
▪      During Works (Twice Daily)
▪      Close of Works
▪      After Hours

All devices, signs, temporary infrastructure and temporary lighting will be designed, manufactured, installed and
maintained in accordance with the relevant Department of Transport and Main Roads (DTMR) Standards,
Australian Standards, technical standards, design documentation and the approved TGS. Directional,
information and regulatory signposting will accompany any changes to the existing road networks. Shadforth
will design, supply, install and maintain all directional, information and regulatory signs required for the work,
including any modifications to existing signs.

Signs, lights, barriers and barricades will be kept clean, securely fixed in position and maintained in good order
day and night. Inspections will take place prior to the morning peak period and at the beginning of the night time
period. Any corrective action will be carried out immediately.

1.12       Temporary Signage

In order to minimise driver confusion during construction, directional signage will be provided in locations where
a route has changed temporarily. Directional signage will be provided on the existing roadways, and pedestrian
and cyclist pathways. Any traffic rearrangements will be advertised to the motorist prior to the alteration by use
of static signs. Information conveyed to the motorist will include, but not be limited to, directional information,
advance warnings and speed limits.

1.13       Temporary Road Safety Barriers




IMS-04-05_D - Reviewed May 2019                 Document Uncontrolled When Printed                       Page 7 of 30

Page 8

                                                                               Traffic Management Plan


Temporary Safety Barriers (TSBs) may be used to contain and redirect wayward vehicles and prevent them
from entering the worksite in constrained situations. In such instances, installation of safety barriers will cater
for the dynamic deflection of the barrier type.

Types of Traffic Safety Barriers that may be used are:

▪      Rigid barriers (temporary concrete / TL2 barriers or temporary corrugated steel beam guardrail)

Where temporary barriers and delineation bollards are used for the separation of traffic from road works and
hazards, they will be installed to achieve compliance with DTMR specifications and manufacturers
specifications. The minimum distance from the face of the TSB to the lane edge will be as per clause 4.13.4 (c)
of the MUTCD Part 3.

As appropriate, the area immediately behind the temporary safety barrier will be kept clear of materials and
hazards. The workforce will be directed to keep clear of this area and a containment fence may be erected, if
required.

All barriers will be installed so that both the likelihood and extent of deflection of the barrier in the event of impact
are minimised.

These will be typically used between traffic and a severe hazard such as a deep excavation, bridge pier or a
hazardous stockpile and for the protection of workers and non-vehicular road users in vulnerable situations
where lateral clearance to moving traffic would otherwise be insufficient for safety.

1.14       Containment Fences other than Road Safety Barriers

Containment fences comprising tapes, plastic mesh fencing or longitudinal channelising devices may be used
to provide visible containment in situations where physical protection by use of a road safety barrier system is
not warranted.

In accordance with MRTS02 CL 5.4, where work activities are being undertaken within 3.5m of the lane edge,
and where such activities are likely to cause traffic delays, anti gawking screens are to be installed on barriers
within 100m of: any intersection, an entry; or an exit ramp.

All excavations shall be protected in accordance with Shadforth SWMS and the relevant codes of practise: use
of temporary fencing and shade cloth where conditions permit.

1.15       Temporary Lighting

Temporary lighting may also be required to supplement existing lighting where the path through the site could
be difficult to follow. Lighting from other sources, especially glare sources, should be considered. Lighting for
pedestrians shall be provided

1.16 Construction Access

Construction access will vary on throughout the project. Specific Vehicle Movement plans and TGS’ will be
issued prior to mobilising into an area.

1.17       Detours

Not applicable within this project Scope of Works.

1.18       Access Requirements

Whilst there are limited numbers of businesses or residential properties, which will require access through or
across the work site; any existing access to businesses and residential properties shall always be maintained
including out of hours operations. During the work shift, a designated spotter shall be present to direct and spot
any accessing vehicles through the work site. If access across worksite is required, suitable control methods
shall be employed through utilising spotters, backfilling trenches as works proceed, trenchless technology and



IMS-04-05_D - Reviewed May 2019                   Document Uncontrolled When Printed                           Page 8 of 30

Page 9

                                                                                Traffic Management Plan


or provide alternative access routes for the affected area. Shadforth will make prior contact with the affected
business and or land owner to discuss and agree on access routes and the scope of works.

1.19       Pedestrian and Bicycle Routes

There are no dedicated pedestrian and bicycle routes contained within the works. It is estimated that the public
interfaces / impacts / disruption will be minor within this scope of works.

1.20       Emergency Services

The project will have appropriate emergency response equipment and first aid provisions for site use. Equipment
shall be maintained and checked at regular intervals, with appropriately trained personnel on site to respond to
incidents. The Queensland Ambulance Service (QAS) shall be called and given right of way for any medical
incidents or emergencies. The Queensland Fire and Emergency Service (QFES) shall be called for all fire
emergencies.

1.21       Public Transport

There are no bus stops or public transport pick up points currently identified within the project boundaries.

1.22       Environmental

Environmental considerations that should be considered:

▪      Dust Control (should be assessed and eliminated from work site using appropriate control measures).
▪      Inclement Weather (checks to be made to ensure traffic control devices do not hinder the natural flow of
       rain water getting to gullies).
▪      Spoil mounds should be maintained with silt fence / silt socks to avoid silt run off.
▪      After rain events ensure that all control devices are clean and visible.

1.23       Key Performance Indicators

The following Key Performance Indicators (KPIs) are a selection which may be used by Shadforth to measure
effectiveness.

▪      Number of complaints on traffic related issues.
▪      Number of Traffic incidents reported from site
▪      Response time to traffic incidents

Progress on these KPIs may be included in monthly reports and corrective actions noted. The Project Engineer
will report monthly on these indicators.

1.24       Dissemination of Information / Consultation

Shadforth will undertake a cooperative and coordinated approach to ensure the public receive timely, accurate
and credible traffic information. Letter box drops and door knocks to directly affected residents will be undertaken
prior to commence construction activities.

1.25       Post TMP and TGS Evaluation

Evaluation of TMP and TGS’s will occur at regular meetings and consultation with the implementers will occur
after the job is completed. Such items for discussion will include but not limited to:

▪      Risk Assessment outcomes
▪      TGS modifications at implementation




IMS-04-05_D - Reviewed May 2019                    Document Uncontrolled When Printed                     Page 9 of 30

Page 10

                                                                       Traffic Management Plan


▪    TGS modifications during operation
▪    Contractor feedback
▪    Performance reports
▪    Complaints
▪    Traffic operations issues
▪    Incident logs
▪    Safety outcomes




IMS-04-05_D - Reviewed May 2019           Document Uncontrolled When Printed            Page 10 of 30

Page 11

                                                                             Traffic Management Plan


1.26       Private Property

There are a number of private residences that will be directly affected by this scope of works:

       1. 21 Wilgee Court

       2. 166 Lake MacDonald Dr, Lake MacDonald QLD 4563

       3. 156 Lake MacDonald Dr, Lake MacDonald QLD 4563

       4. 152 Lake MacDonald Dr, Lake MacDonald QLD 4563

       5. 171 166 Lake MacDonald Dr, Lake MacDonald QLD 4563

       6. Houses 4-13 Pine Tree Drive W



Prior to construction commencing a letter box drop will be provided advising the residents of the upcoming
works.

1.27       Provisions for Special Events

NA

1.28       Specific Seasonal Activities

School holiday periods may increase traffic volumes

2. Project Description
2.1 Project Overview

The project includes the following:

▪      Clearing and grubbing to various locations
▪      Shoulder widening
▪      Construction of pavements and drainage

Due to the various work locations, all construction activity and deliveries will be contained and minimised to within
the immediate site boundary/area. Where works are to take place next to live traffic lanes, shoulder closures,
lane closures using temporary traffic signals and or controllers may be required.

2.2 Works Staging and Methodology

Works on Lake Macdonald Drive shall be completed in 1 mobilisation implementation of several TGS’ that
enable the construction of the 2 new access points to the development and also the shoulder widenings. Works
are planned to be completed in a sequential manner whilst maintaining continuity of work for work crews and
subcontractors. Similarly, Wilgee Court will be completed in a similar manner but with its own operation under
a separate set of TGS’.

Works will proceed with boundary demarcation followed by clearing of vegetation, earthworks and then
pavement construction.

The program for the works are currently anticipated as follows:

▪      Site Establishment - October 2020




IMS-04-05_D - Reviewed May 2019                 Document Uncontrolled When Printed                        Page 11 of 30

Page 12

                                                                                    Traffic Management Plan


▪      Construction Commences                    October 2020
▪      Construction Completion                   December 2020

Refer to Appendix 2 for a more detailed copy of the construction program provided by Shadforth.

2.3 Key Personnel and Contact Details
     Contact Name            Position              Company               Phone                         Email

                                                Mark Bain
    Mark Bain           Client                                                          [email protected]
                                                Constructions

                                                                      0488 383
    Doug Reynolds       Administrator           TOD Consulting                          [email protected]
                                                                      370

                        Out of Hours                                  0407 395
    Darryl Hart                                 Shadforth                               [email protected]
                        Contact                                       496

                                                                      0417 736
    James Harris        Project Manager         Shadforth                               [email protected]
                                                                      105

                                                                      0407 395
    Darryl Hart         Site Supervisor         Shadforth                               [email protected]
                                                                      496

                        Health and Safety                             0400 524
    Mark Lonergan                               Shadforth                               [email protected]
                        Manager                                       763

                                                                      0450 607
    Andrew Hussey       Traffic Officer         Shadforth                               [email protected]
                                                                      330

Table 2.3 Key Personnel and Contact Details

2.4 Stakeholder Details

During all construction phases, the project team will communicate to the Administrator the planned construction
activities and any impacts these activities may pose on the public / community; including changed traffic
conditions or disruption to services. The community and all mode user groups will be informed of changes via
a variety of means: Examples being letter box drops and or Variable Message Sign (VMS) and construction
signage

Key stakeholders include, but are not limited to:

▪      Noosa Council
▪     Local residents and businesses
▪     General public

Engagement with the community will be ongoing throughout the works and consultation with local stakeholders
will be conducted by Shadforth personel.



2.5 Working Hours

The normal hours of onsite work will be:

▪      Monday to Saturday                 6:30am - 6:00pm - excluding public holidays
▪      No Work                            Sundays and Public Holidays




IMS-04-05_D - Reviewed May 2019                        Document Uncontrolled When Printed                              Page 12 of 30

Page 13

                                                                              Traffic Management Plan


All out of hours works will be subject to appropriate approvals from the relevant authorities. The relevant
council is to provide written approval of the submitted this TMP and associated TGS’ prior to Shadforth
mobilising to site.

2.6 Complaints Management

A development information board will be provided at the site entry in a clear and appropriate location. This will
provide the necessary contact details of the onsite manager.

Complaints procedures will be handled as follows:

Complaints directly to the Site Manager - Shadforth will maintain a complaints register that will record all public
complaints made to them directly. The register will record dates, details and actions taken for future reference.
The complainant will be notified by phone or email of the outcome. The Administrator may be notified of any
complaints received and a copy of the register will be made available upon request.

Complaints made to Noosa Council, Shadforth will work with the department to resolve the issues in a timely
manner and appoint expert consultants to assist if necessary. E.g. Civil and Traffic Engineers.

2.7 Asset Management

All road line markings and traffic signs within the vicinity of the site, will not be affected during the construction
phase. There may be a need for temporary removal or modification to existing kerbs and landscaping for
crossovers.

Any changes, damage or deterioration of road pavement, kerbs, traffic signs and line markings that have
occurred as a result of development works will be replaced and reinstated accordingly. Shadforth will ensure that
pre and post records of the affected area will be recorded for future reference. It is noted during the pre-
construction condition assessment of the existing infrastructure shows signs of fatigue and pavement failure /
cracking throughout.




IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                        Page 13 of 30

Page 14

                                                                            Traffic Management Plan


3. Traffic Management Resources
3.1 Public and Worker Safety

The key criteria at all stages of construction is to maintain a safe site, safe access to and from the site for
workers, and to ensure the necessary safety measures and notifications are provided for the local community for
the duration of works.

Nearby Access Points

Access to the works areas typically involve works on the side of the carriageways.

Access to properties and any affected businesses is to be maintained at all times as agreed with the affected
stakeholder.

3.2 Traffic Guidance Scheme Summary

It should be noted that this TMP has been developed on the basis that all activities associated with this project
will be undertaken within the approved areas of the project.

The traffic management devices will be in place as required by the TGS and scope of works. This will be prior
to commencement of activities on site.

For reference to site wide traffic management TGS, refer to the Appendix of this document.




IMS-04-05_D - Reviewed May 2019                Document Uncontrolled When Printed                     Page 14 of 30

Page 15

                                                                              Traffic Management Plan


3.3 Special Requests (Signage)

Not applicable to this Project.



4. Haulage
4.1 Staff Parking

Construction personnel may access the main site office off Lake Macdonald Drive. Car parking for for all
vehicles, plant and equipment shall not park nor obstruct Lake Macdonald Drive. Subcontractors and other
construction workers operating at the various locations on site will need to mitigate excess vehicles due to restricted
working widths. With work site locations varying across the different areas of the project, private vehicles will be
restricted access, car pooling will be encouraged, with only subcontractor vehicles permitted unless agreed
otherwise. Workers will be made aware of particular areas where parking will be prohibited such as:

▪    Lake Macdonald Drive
▪    Outside of Traffic Management when operating on road shoulders
▪    Privat Land / Driveways
▪    Wilgee Court

4.2 Site Access and Egress

The installation of an industry standard rumble grid will be located at the site entry to reduce the likelihood of
excess gravel and soil being spread onto the nearby road network. The work site boundary will be established
by fencing to maintain separation from the public where required.

All long-term crossovers will be provided as per Council standards, while temporary crossover will be removed,
and the kerb and verge being reinstated accordingly.


5. Human Resources
5.1 Training / Induction

The competency needs of all personnel performing activities affecting traffic management and construction will
be identified by the Supervisor in consultation with members of the project team. Personnel performing assigned
tasks will be qualified on the basis of appropriate education, training, skills and experience, as required.

Prior to work beginning onsite, all project personnel will undergo a site induction. This will cover the traffic
management system and include requirements for safety, environment, site rules, administration and other
issues relating to traffic management.

Traffic Controllers will have an identification card showing that the person is a qualified Traffic Controller. The
card will be issued by a training provider accredited by DTMR. The card will be carried by the Traffic Controller
at all times whilst undertaking the duties of traffic control.

5.2 Nominated Traffic Officer

The Nominated Traffic Officer (NTO) role will be fulfilled by:

Andrew Hussey from Shadforth

DTMR Traffic Management Design Card No. 651

Certification Type: Open




IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                         Page 15 of 30

Page 16

                                                                              Traffic Management Plan


The traffic management for different areas will be organised under the NTOs direction by the Project Manager
responsible for that section of work and will involve the following:

▪    Familiar with the requirements of the TMP and TGS’s.
▪    Maintain an updated listing of personnel and subcontractors, both on and offsite who are suitably trained to
     provide traffic management and emergency incident callout service.
▪    Maintain an updated listing of equipment available both on and offsite which would be available and
     appropriate for traffic management and varying incidents.
▪    Develop and maintain a personal contact with emergency services representatives, Queensland Police
     Service (QPS), DTMR and other relevant authorities if applicable.
▪    Liaise with the Administrator to ensure the relevant parties are continually updated as to the progress of the
     work and any changes to either the TMP or the TGS’s.
▪    Be party to regular meetings with the management and construction staff for the purpose of obtaining
     program forecasts and ensuring the requirements of the TMP will be implemented.
▪    Establish a program for suitable training of personnel in traffic management and emergency procedures, as
     well as ensuring these issues are addressed at site inductions and toolbox meetings.
▪    Be responsible for the establishment and operation of the organisation charged with implementation of the
     traffic management.
▪    Maintained a register of all incidents and complaints received, recording action taken to address each. A
     similar register is to be maintained outlining requests for information from the public.
▪    Maintain a register of all devices used for traffic control, including the times and dates that they were erected
     and dismantled.
▪    Coordinate all the reporting functions relating to traffic management.
▪    Be available to receive regular briefings on the implementation of the TMP, TGS’s and incident response
     plans, attend inductions and toolbox meetings.
▪    Participate in the development of work procedures relating to traffic management and incident response
     plans.
▪    Implement the work procedures in the field, in a manner that recognises the importance of safety of
     employee, road users and members of the public in general.
▪    In conjunction with the Project Engineer ensure adequate resources are available and used to carry out
     works in accordance with program and construction constraints.
▪    Ensure that all resources necessary to deal with traffic management and incident response issues, are on
     hand or are readily available.
▪    Traffic controllers will be accredited traffic management implementers.
▪    Consultation of all traffic management operatives shall be sought at Pre-Start meetings for ideas for
     improvements or safer implementation of the traffic management, an open and honest approach will be
     maintained throughout the project to ensure all communication and consultation is recorded and discussed
     for post traffic evaluation.

5.3 Out of Hours Representative

The name, address and contact details of three out of hours traffic management representatives will be supplied
to the Administrator during the construction period. The nominated persons will have the authority and
experience to organise immediate repairs, maintenance or replacement of the traffic control devices. The traffic
management representative will ensure that all repairs are carried out to the satisfaction of the Administrator
representative.

5.4 Principal Convened Traffic Coordination Committee




IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                        Page 16 of 30

Page 17

                                                                              Traffic Management Plan


The Contractor will make available a member of the senior management team for any requests made by the
Client/ Administrator / Principal to coordinated a traffic coordination committee.

Contact details are provided in section 1.5.

6. References
▪    Queensland MUTCD Part 3: Traffic Control for Works on Roads July 2019
▪    Traffic and Road Use Management Manual (TRUM) - Supplements to the Austroads Guides
▪    Workplace Health and Safety Queensland - Code of Practice for Construction Work or Maintenance
     Activities on, or Adjacent to a Road
▪    Austroads Guide to Traffic Management and Austroads Guide to Road Safety
▪    Traffic Management for Construction or Maintenance Work - Code of Practice 2008

7. Incidents
Types of possible incidents could include but not limited to:

▪    Motor vehicle crashes
▪    Fires
▪    Environmental spills
▪    Inclement weather conditions (flooding, hail, high winds)
▪    Terrorist activity

The occurrence of unforeseeable incidents can temporary restrict project activities and smooth operation of the
road network. Although the management and response of incidents on the local road is not the responsibility of
the project, if there was an incident within the confines of the site boundaries the following would apply under
our duty of care:

▪    Make available resources to provide a first response to the incident with the aim to make the area safe and
     to prevent any further harm, bearing in mind that no-one is to risk injury to themselves or others in doing so.
▪    Inform emergency services, local authority, DTMR, of any incident and aid any emergency services
     especially if there are traffic controllers on site.
▪    Follow any emergency response plans, from the Administrator, as is fit to the incident.
▪    Make notes, take records of any witnesses, regos, times, dates that could be needed for an incident review
     at a later date.
▪    Schedule review and update of TMP or TGS in response to any incidents and outcome of investigation.

In the event of a traffic incident within the boundaries of our traffic devices, the Engineer and NTO shall complete
a traffic accident report within 24 hrs of any incident. A full report should include but is not limited to:

▪    Photos and / or videos of traffic control devices in place
▪    Date and time
▪    Details of incident
▪    Possible causes of incident or contributing factors
▪    Witnesses
▪    Injuries / fatalities / damage
▪    Environmental harm cause
▪    Contractors response


IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                      Page 17 of 30

Page 18

                                                                                Traffic Management Plan


▪     Suggestions on avoidance of similar incidents (corrective actions)
▪     Temperature and weather

8. Existing Network Details
8.1 Existing Conditions and Operations

8.1.1      Local Road Network

All roads in the immediate vicinity of the site are administered by Noosa Council. The hierarchy and
characteristics of these roads in the immediate vicinity of the site that may be impacted are shown in Table 8.1.
Table 8.1: Local Road Hierarchy

                                       40km / hr
                            Speed
      Road / Street                     School                Lanes                     Classification   Road Authority
                            Limit
                                         Zone

    Wilgee Court           50km / hr      No       2 Lanes                         Local Access Rd       Council Rd

    Lake Macdonald         60km / hr
                                          No       2 Lanes                         Local Access Rd       Council Rd
    Drive                  80km / hr

    Pine Tree Drive W       50km/hr       No       Track                           Local Access Rd       Council Rd




Note: All haulage routes will be compliant with state mass requirements and dimension limits.

8.1.2     Pedestrians and Cyclists

There is no designated pedestrian and or cyclists routes

8.1.3     On-Street Parking

Throughout the nearby traffic road network there is no on-street parking availability

No on-street parking for construction vehicle will be provided and all plant, vehicles and equipment will be parked
within the extents of the works or within approved Traffic Management extents.

8.1.4     Schools and Community Precincts

The intersection of Lake MacDonald Drive and Elm Street is a designated school zone where by Tadpoles
Early Learning Centre is located. All personnel associated with the works are to adhered to road rules .




IMS-04-05_D - Reviewed May 2019                    Document Uncontrolled When Printed                           Page 18 of 30

Page 19

                                                                               Traffic Management Plan


9. Traffic Management Implementation
9.1     Existing Conditions and Operations

Refer to Section 1.5 for project personnel details.

9.2     Implementation Details
▪     All TGS implementations are subject to the Risk Assessment process and requirements
▪     All TGS must be implemented as per the “Optimal Treatment” set out in the MUTCD, with modifications to
      “Optimal Treatments” restricted as per Clause 4.1.6 - Tolerances and Positioning, unless Risk Assessed
      and signed off by a RPEQ.
▪     QLD MUTCD Work on Roads 9th Edition. “Optimal Treatment” requirements are:
       o   Risk Management as per Clause 2.2.3
       o   Variation to Optimal Treatment as per Clause2.2.5
       o   Long Term signage as per Clause 2.5.2
       o   Short Term signage as per Clause 3.3 and Appendix D
       o   Traffic Cone and Bollard spacing as per Table 3.7
       o   Temporary RRPM use as per Clause 3.9.4 and 3.9.5
       o   Safety Buffer as per Clause 4.1.4(c)
       o   Value of “D” as per Table 4.2
       o   Tolerances and Positioning as per Clause 4.1.6
       o   Static work sites as per Clause 4.2
       o   Mobile works as per clause 4.6 and Table 4.5
       o   Advance Warning Signage as per Clause 4.7
       o   Taper lengths as per Table 4.6 and Clause 4.8
       o   Speed zones as per Table 4.7 and Clause 4.9
       o   Reversible Flow (single lane lengths) as per Table 4.9, Clause 4.13.1 (previously TRUM Note 7.9)
       o   Number of lanes as per Table 4.10 and Clause 4.13.2
       o   Minimum lane widths as per Table 4.11, Clause 4.13.3 & 4.13.4
       o   Local Traffic Access as per Clause 4.14.5
       o   Reversed traffic direction considerations as per Clause 4.14.8
       o   Roadwork at Intersections as per MUTCD - Appendix F
       o   Emergency and Unplanned works as per MUTCD - Appendix H
▪     Traffic Delays guidelines to be within Project Annexure MRTS02.1: No greater than 5mins.in low traffic
      volume times. Nil in high flow volumes
▪     Traffic Controllers to be positioned according to TCASAP and MUTCD requirements.
▪     Worker and Flagman Symbolics to be covered when workers / Traffic Controllers not working or not visible
      to traffic




IMS-04-05_D - Reviewed May 2019                   Document Uncontrolled When Printed                Page 19 of 30

Page 20

                                                                              Traffic Management Plan


9.3 Traffic Controllers General Duties (if required)

A Traffic Controller is defined as:

A person who holds an appointment as an accredited person under Section 21 of the Transport Operations
(Road Use Management) Act 1995 to perform the functions of a traffic controller as prescribed by the Transport
Operations (Road Use Management - Accreditation and Other Provisions) Regulation.

All Traffic Controllers are to be trained and accredited with the QLD Traffic Controller Accreditation
Scheme and hold a QLD Construction White / Blue Card.

Traffic Controllers will set out and maintain signage as per the relevant TGS in accordance with MUTCD, and
traffic control shall be conducted as per the Approved Procedure for Controlling Traffic. Any personnel to
implement signage will be appropriately qualified as prescribed by the MUTCD. All Traffic Controllers will be
relieved of their duty after not more than 2 hours for a period of rest or other duties of at least 15 minutes.

It is the responsibility of the and onsite foreman / supervisor to monitor queue lengths and delay times caused
to the public. The maximum time any direction of traffic that will be held is <5mins, this will be communicated to
the work force at daily pre starts. This scope of works will plan to mitigate the impact on the road user by
choosing to select a preferable shoulder closure where possible, therefore still maintaining existing traffic lanes
configurations.



9.4 Traffic Control Devices

Certain traffic control signs are only to be displayed for specific work activities, this includes:

The Traffic Controller’s responsibility to ensure that signs are erected at the start of each day, and removed (or
covered) at the end of the day. It is not acceptable to keep these signs displayed if there are no works and
especially not overnight or outside work hours.

Traffic control and advance warning signs will be placed upon all approaches to the work site. Refer to Appendix
6 for details of placement of traffic management devices and after care signage.



9.5 Unplanned Oversize Vehicle Access

Although considered low risk for this project, Should oversized vehicles require access through the work zone
the following protocols will be followed. Traffic Controllers will may obtain positive communication over the UHF
channel 40 prior to the oversized vehicle approaching the area: Width and vertical clearance will be
communicate by any pilot vehicles. Based on the advanced warning, should the works site contain a single lane
closure that is restricting the required clearance for the oversized vehicle to pass through then this will be
communicated to the onsite foreman. Depending on the traffic control devices in place [likely single lane closure
/ hats/bollards] then all personnel, plant and equipment will be removed from the work site to a safe distance off
the carriageway. Traffic controllers will still remain in position controlling 2 way traffic under stop go conditions.
Upon the oversized vehicle manoeuvring through the work site, the bollards/hats will be removed by the traffic
controllers and reinstated following its passing – all other public vehicles will remain on stop until the traffic
control devices are reinstated (<5mins).




10. Risk Assessment
Risk management entails the identification and analysis of risks likely to arise during works on road including
the setting up, operating, changing and ultimate dismantling of a traffic guidance scheme, followed by the



IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                        Page 20 of 30

Page 21

                                                                              Traffic Management Plan


determination of appropriate measures to mitigate those risks. The process is appropriate at all levels of planning
and operation.

The process is carried out by first identifying all hazards likely to arise, evaluating them in terms of likelihood of
occurrence and adverse consequences using historical data, experience or other means. The proposed
procedural statement or traffic guidance scheme should ensure that adequate means of controlling or reducing
those risks found to be significant, are in place.

All traffic control guidance schemes will be designed, developed and implemented in accordance with the
MUTCD. Whilst it is considered that speeding through the traffic controlled work site posing a safety risk to the
controllers and or workers a speed management plan will be developed if such issues occur. This plan will
implement additions to the traffic guidance schemes through implementation of additional signage, advanced
warning signs and speed activated radars.

A Project Risk Register will be maintained by Shadforth and will be updated throughout the duration of the
construction activities or when works change. Additional risks will be assessed, and control measures
implemented as they are identified.

It is expected that the Engineer will provide a project Risk Assessment of the construction activities.




IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                        Page 21 of 30

Page 22

                                                               Traffic Management Plan


11. Appendix 1 - Risk Assessment




IMS-04-05_D - Reviewed May 2019   Document Uncontrolled When Printed            Page 22 of 30

Page 23

                                                               Traffic Management Plan


12. Appendix 2 - Construction Program




IMS-04-05_D - Reviewed May 2019   Document Uncontrolled When Printed            Page 23 of 30

Page 24

                                                               Traffic Management Plan


13. Appendix 3 - Haulage Movements
Not applicable to this Project




IMS-04-05_D - Reviewed May 2019   Document Uncontrolled When Printed            Page 24 of 30

Page 25

                                                                     Traffic Management Plan


14. Appendix 4 - Traffic Data
Not applicable to this scope of works




IMS-04-05_D - Reviewed May 2019         Document Uncontrolled When Printed            Page 25 of 30

Page 26

                                                                     Traffic Management Plan


15. Appendix 5 - Staging Diagrams
     Staging Plan                          Stage                              Corresponding TGS #




Not applicable to this scope of works




IMS-04-05_D - Reviewed May 2019         Document Uncontrolled When Printed                 Page 26 of 30

Page 27

                                                                          Traffic Management Plan


16. Appendix 6 – Traffic Guidance Schemes
List to be generated on issue of IFC plans

    TGS Name                                                   Stage




IMS-04-05_D - Reviewed May 2019              Document Uncontrolled When Printed            Page 27 of 30

Page 28

                                                                                     Traffic Management Plan


17. Appendix 7 - Traffic Management Options Considered
Below is a sample of the traffic management options to be considered.

 Option                      Features                                                                       Comment

 Vehicle Traffic             Sidetrack      Construct a side-track full width to allow two lanes of         Not Adopted
 around the worksite                        traffic past the works and not affect the construction.
                                            Disadvantages:
                                            ▪    Not practical as cost of construction and timeframe
                                                 are not feasible.
                                            ▪    It would take months to construct and remove a side-
                                                 track which would delay the works program.
                                            ▪    Two bridges along section of works which require
                                                 additional detour works through creeks.
                                            Advantages:
                                            ▪    This will allow access to unimpeded access to the
                                                 work area for resealing works to be completed.
                                            ▪    Less delays for road users.
                                            ▪    Positive customer experience.

                             Detour         Close Lake Macdonald Drive and detour all through traffic       Not Practical. But
                                            around                                                          will be utilised for
                                                                                                            Emergency /
                                            Disadvantages:                                                  Alternative Route
                                            ▪    This detour would add an additional excess km of           for road users
                                                 travel to road users.
                                            ▪    Would still have to allow for full traffic management to
                                                 deal with local traffic.
                                            ▪    Harvest time would create additional traffic on road to
                                                 deal with.
                                            Advantages:
                                            ▪    Would remove most road users from the road and
                                                 minimise traffic interaction with construction.
                                            ▪    Allow smoother construction of the sealing works.

                             Contraflow     Not possible as road is not a multi lane road.                  Not Adopted




 Traffic through the         Allow road users to traverse through the works, but only possible after        Not Adopted
 worksite                    placement of initial rolling of stone.
                             Disadvantages:
                             ▪    Higher risk of incident or collision.
                             ▪    Higher risk of injury to workers and road users.
                             ▪    Possible stone chips to vehicles due to accessing the sealing works
                                  to early.
                             ▪    Possibly reduced customer satisfaction.
                             ▪    Possibly require pilot vehicle.




IMS-04-05_D - Reviewed May 2019                         Document Uncontrolled When Printed                             Page 28 of 30

Page 29

                                                                                   Traffic Management Plan


                             ▪    Greater difficulty to manage road users through works.


                             Advantages:
                             ▪    Reduced delays at these sections of works.

 Traffic past the            Close one lane of traffic and operate under shuttle flow via the use of      Option Adopted
 worksite                    portable traffic signals.
                             Disadvantages:
                             ▪    Impact to road users.
                             ▪    Delays to road users
                             ▪    Traffic controllers having to stop heavy vehicles
                             Advantages:
                             ▪    Allows for road users to pass the works safely without risk of injury
                                  or damage.
                             ▪    Speed reduced to 40km/hr due to lane proximity to workers and
                                  plant, thus reducing rick of workers being struck by vehicles.



 Lateral Shift               Lateral shift both lanes of traffic onto one lane and use unsealed           Not Practical
                             shoulder as second lane.
                             Disadvantages:
                             ▪    Insufficient space to allow for 2 x 3.5m lanes of sealed pavement
                             Advantages:
                             ▪    This will allow access to unimpeded access to the work area for
                                  resealing works to be completed.
                             ▪    Less delays for road users.
                             ▪    Positive customer experience.




IMS-04-05_D - Reviewed May 2019                       Document Uncontrolled When Printed                            Page 29 of 30

Page 30

                                                                                    Traffic Management Plan


18. Appendix 8 - Pedestrian Options Considered

   Option                    Features                                                                    Comment

   Close footpath            There is currently no footpath facilities to close but there is currently   Not adopted
                             approximately 1m of grass shoulder able to be traversed.
                             Disadvantages:
                             ▪    Reduced customer experience
                             ▪    Possible undulating surface and risk of pedestrians injuring
                                  themselves.
                             Advantages:
                             ▪    Less impact on through traffic
                             ▪    Removed pedestrians from work area

   Retain Open               The is currently no footpath facilities so pedestrians will walk on the     Not Adopted
   Footpath                  existing shoulder.
                             Disadvantages:
                             ▪    Reduced customer experience
                             ▪    Possible undulating surface and risk of pedestrians injuring
                                  themselves.
                             ▪    Risk of contact with works and machinery in work area
                             Advantages:
                             ▪    Less impact on through traffic
                             ▪    Removed pedestrians from work area
                             ▪    No change to current pedestrian movements

   Detour                    Pedestrian detour not practical                                             Not Practical

   Escort                    Escort Pedestrians through works area by spotter.                           Not Practical – there
                                                                                                         are no designated
                             Disadvantages:                                                              routes in its current
                             ▪    Having to supply pedestrians with appropriate PPE to traverse          condition
                                  works area.                                                            Pedestrians to
                             ▪    Additional cost in resources to provide this service.                  comply with common
                                                                                                         road rules and
                             Advantages:                                                                 regulations
                             ▪    Reduced risk of pedestrian injury.
                             ▪    Positive outcome for pedestrians.




IMS-04-05_D - Reviewed May 2019                        Document Uncontrolled When Printed                                Page 30 of 30

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.