Minor Change Existing Approval - MCU25 0136 01 (As Published)
h. details on the location of external fill sites/sources, the haulage route, type of vehicle
to be utilised during filling operations and frequency of usage. NB any damage to the
existing road system as a result of haulage operations shall be fully repaired at the
applicant’s expense
i. it is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed
to construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.
Community Title Scheme - Private Infrastructure
5. All private infrastructure for the development must be designed to meet the planning scheme
requirements unless otherwise agreed by the relevant authority
Plan Sealing
6. All works required by this permit must be completed and accepted by Council prior to
submitting an application for plan sealing.
Biosecurity Act 2014 – Fire Ant Control
7. Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
individuals and businesses are responsible for ensuring that they follow the movement
controls for specific organic materials to help prevent the spread of fire ants within South
East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
ant biosecurity zone may need a biosecurity instrument permit. More information is available
on https://www.fireants.org.au/treat/business-andindustry/movement-controls
Qualified Person
8. For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
current experience in the field of landscape design.
9. For the purpose of preparing an Arborist Report, a qualified person is considered to be a
person with either:
a. ISA certification; or
b. a Diploma of Arboriculture in addition to a minimum of 3 years current experience in
the field of arboriculture.
10. For the purpose of preparing a Fauna Management Plan, a qualified person is considered to
be an ecologist with a minimum of 3 years current experience in the field of fauna assessment
property notes
8. PROPERTY NOTES
Not applicable.
9. VARIATION APPROVAL DETAILS
Not applicable.
10. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Operational Works Road work, Stormwater, Drainage work,
Earthworks, Landscaping.
Development Permit for Building Works All building work.
Page 8 of 10
Document Set ID: 25046953
Version: 4, Version Date: 17/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Minor Change Existing Approval - MCU25 0136 01 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.