EROSION AND SEDIMENT MANAGEMENT STRATEGY

ENVIRONMENTAL ISSUE MANAGEMENT STRATEGY Erosion and Sediment Control

Objective/Target Comply with the erosion and sediment control plan as shown,
to control erosion and sediment flows. Sediment trap (sandbags or fence)
Ensure that all erosion and sediment control devices are
operational at all times = Direction of minor flow

Management Strategy Site foreman to identify and check direction of stormwater ri =p Direction of major flow
land flows as shown on plan. Provide barriers and other

measures shown on the plan to prevent stormwater flows
over embankments, and sediments into gully pits eat Construction Entry/Exit

Tasks/Actions Erect sedimentation barriers at perimeter of construction
areas as shown on this drawing

Frequency/Deadline Site foreman to monitor performance after every heavy
rainfall

Responsible Person/ Site foreman to be responsible for

Organisation inspections.

Reporting/Review Site workmen to advise foreman if they notice any barrier
needing repair.

Corrective Actions Site foreman to report and order through supervisor, extra
barriers as required.

EROSION & SEDIMENT CONTROL NOTES:
This site has low erosion risk potential
Refer IPWEAQ Standard Drawings D-0040 and D-0041 for
details of sediment traps
All gullies shall be provided with on grade kerb inlet
sediment trap refer IPWEAQ Standard Drawing D-0041.
The Contractor shall construct Entry/Exit Sediment Trap
Alternative 2, refer IPWEAG Standard Drawing D-0040
Grass filter strips 600mm wide shall be placed along back
of kerb and channel, pathways and other impervious
areas. Locations shall be confirmed by contractor
All allotments shall be revegetated with mulch or grass
seeding as specified in Section AS-B2 of Soil Erosion and
Sediment Control Guidelines for Queensland Construction
Sites, June 1996, IEAQ

20 0 20 40 60 80 10.0m

————
4200-A1 1400 - AB ;
rpea’ ) 84+ sicnatuREC. 3: /fbwereA . For Cardno (Ald) Pty Lid

pean COMISKEY GROUP

SUNSHINE BEACH CHILDCARE CENTRE
LOT 31 RP149005

EROSION AND SEDIMENT CONTROL PLAN 2384-01 -008

 

 

 

 

DRAWING No.

 

 

 

 

 

 

 

Used in these records

About this file

File size
11.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

08_1056 - Operational Works - Roadworks, Stormwater & Earthworks [As Published].pdf · 11.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.