Reference Document - OPW23 0189
ADG Consulting Pty Ltd
excavation footprint based on area and depth, but does not take account of the method of perimeter
piling i.e. sheet pile/concrete secant wall, which will inhibit lateral inflows. Also note that the cone of
depression radius measure includes water table depressions of 1 mm depth or more, so any significant
depression of the water table is limited to much closer to the spear point dewatering spears (generally
within 3 to 10 m from the pile shoring wall in fine‐medium grained sands, depending on density of the
strata).
5.4 Dewatering duration
Dewatering will be necessary throughout the basement construction phase, which is expected to require
dewatering for approximately 8 to 12 weeks. To minimise the potential impacts during construction of
short‐term dewatering, periods of active dewatering will be minimised as much as possible. However,
ADG notes that once active dewatering has commenced, dewatering will not be able to be ceased until
both: a) the basement hydrostatic uplift forces have been compensated to the satisfaction of the
consulting RPEQ engineer; and b) potential hydraulic loading on the external face of the piled shoring
system has been compensated to the satisfaction of the consulting RPEQ engineer and shoring
contractor.
5.5 Groundwater drawdown
Groundwater drawdown caused by dewatering has the potential to create settlement in unconsolidated
sediments and loose sands. It is noted that dilapidation reports for surrounding structures and services
are proposed to be undertaken, which were not available or supplied to ADG for the purposes of
preparing this DMP, and are to be provided to Council separately from this DMP.
Groundwater drawdown may also oxidise potential acid sulfate soils within the cone of depression,
subsequently producing acidic groundwater conditions and mobilising heavy metals. Monitoring of the
extracted untreated groundwater will be undertaken to detect potential in‐situ oxidation, as required
and at the frequencies stated in Section 6.5.2. Groundwater monitoring bores for groundwater level
gauging external to the excavation footprint are unable to be established and monitored prior to and
during construction on the site, due to limited space (SCG Consulting Engineers).
A plan showing the proposed basement extent is provided at Appendix C.
5.6 Groundwater treatment
All extracted groundwater will be treated on‐site using available technologies prior to discharge to the
stormwater network. The following treatment measures will be adopted, and will be installed and
operational prior to the commencement of dewatering:
1. A groundwater pH buffering treatment system (primary treatment)
2. A sedimentation tank to provide additional residence time and sedimentation (secondary
treatment).
3. Installation of fine media filtration to retain suspended sediments and/or heavy metals (tertiary
treatment), if required.
Details of the treatment systems and methodologies are provided in Section 6 of this report.
Note: Consideration should be taken, regarding placement of treatment gear on site to enable easy
cleaning and maintenance throughout the dewatering phase for the project. Consider the potential
requirement for regular de‐sludging of sedimentation tank/s to suitable area onsite, if available (cost
minimisation).
5.7 Nominated Hold Points
In accordance with anticipated DA Conditions, nominated hold points to be enacted during construction
have been proposed to facilitate for certification by the suitably qualified person experienced with Acid
Sulfate Soils, as well as Council Development Engineer to ensure all possible avenues for continual
dewatering below permanent groundwater level, including around pipework bedding that outlet to
ADG1580.23 Dewatering Management Plan_Rev0_28.09.23 Page 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.