     GENERAL NOTES                                                                                    EARTHWORKS AND PAVEMENT                                                                                                                                                            ROADWORKS NOTES
     GN1.         ALL DIMENSIONS AND SET OUT POINTS ARE TO THE KERB LINE OF THE                       CONSTRUCTION NOTES CONTINUED                                                                   SEDIMENT & EROSION CONTROL                                                          RD1.    THE CONTRACTOR SHALL ESTABLISH THE LOCATION, LINE & LEVEL OF ALL PUBLIC
                  SPECIFIED KERB TYPE. REFER LOCAL AUTHORITIES STANDARD DRAWINGS FOR
                                                                                                      EW6.          ALL FILLING SHALL BE CLEAN EXCAVATED MATERIAL FREE FROM TOPSOIL
                                                                                                                                                                                                     NOTES                                                                                       & PRIVATE UTILITY SERVICES PRIOR TO COMMENCEMENT OF ANY CONSTRUCTION.
                  KERB TYPE DETAILS.                                                                                                                                                                                                                                                             WHERE UTILITY SERVICES ARE SHOWN ON THE PLANS, THEY ARE SHOWN FOR
                                                                                                                    AND VEGETATION.
                                                                                                                                                                                                     SE1.   GENERAL:                                                                             THE INFORMATION OF THE CONTRACTOR ONLY. THE PRINCIPAL SHALL NOT BE
     GN2.         FINAL LOCATIONS OF CONDUITS SHALL BE PROVIDED WHEN AVAILABLE FROM                                                                                                                             a. TEMPORARY DRAINAGE CONTROL. FLOW SHOULD BE                                    LIABLE FOR ANY OMISSION OF SERVICES FROM THE PLANS OR THE ACCURACY OF
                                                                                                      EW7.          THE EXISTING SITE WON MATERIALS MAY CONTAIN ROCKS AND COBBLES
                  SERVICE AUTHORITIES. (IF REQUIRED).                                                                                                                                                                DIVERTED AROUND THE WORK SITE WHERE POSSIBLE.                               ANY SERVICES SHOWN ON THE PLANS.
                                                                                                                    AND THESE SHALL BE EXCLUDED OVER 100mm NOMINAL SIZE IN ANY
                                                                                                                    EXISTING MATERIAL USED AS FILLING.                                                          b.   ALL DRAINAGE, EROSION AND SEDIMENT CONTROLS TO BE
     GN3.         ALL CONSTRUCTION SHALL JOIN SMOOTHLY TO EXISTING.                                                                                                                                                  INSTALLED AND BE OPERATIONAL BEFORE COMMENCING                      RD2.    SURFACE LEVELS OVER THE SITE HAVE BEEN INTERPOLATED THROUGH
                                                                                                                                                                                                                     UP-SLOPE EARTHWORKS.                                                        COMPUTER MODELING OF FIELD SURVEY DATA. THESE CALCULATED LEVELS MAY
                                                                                                      EW8.          ANY IMPORTED FILLING MATERIAL REQUIRED TO MAKE UP SHORTFALLS IN
     GN4.         NOTIFY ALL RELEVANT AUTHORITIES PRIOR TO COMMENCEMENT OF WORK                                                                                                                                 c.   ALL SEDIMENT & EROSION CONTROL DEVICES MUST BE                              VARY FROM THE ACTUAL GROUND LEVEL.
                  WITHIN EXISTING ROAD RESERVES.                                                                    QUANTITIES SHALL BE CLEAN SOIL MATERIAL FREE FROM TOPSOIL,
                                                                                                                    VEGETABLE MATTER AND OTHER DELETERIOUS MATERIAL. THE FILLING                                     REGULARLY INSPECTED AND MAINTAINED BY THE
                                                                                                                                                                                                                     CONTRACTOR. INSPECTIONS SHOULD OCCUR ON A WEEKLY                    RD3.    ALL CONSTRUCTION LEVELS SHALL BE SET BY THE CONTRACTOR WITH
     GN5.         THE CONTRACTOR SHALL CONTACT ALL RELEVANT SERVICE AUTHORITIES FOR                                 SHALL BE FREE FROM COBBLES OR ROCKS IN EXCESS OF 100mm NOMINAL
                                                                                                                                                                                                                     BASIS (MINIMUM), ALONG WITH BEFORE AND AFTER                                REFERENCE TO SURVEYED BENCH MARKS PROVIDED BY THE PRINCIPAL'S
                  DETAILED LOCATION AND LEVEL OF SERVICES PRIOR TO COMMENCEMENT OF                                  SIZE. THE MATERIAL SHALL HAVE A MINIMUM SOAKED CBR 15 UNLESS
                                                                                                                                                                                                                     SIGNIFICANT RUNOFF PRODUCING STORMS.                                        APPOINTED SURVEYOR.
                  WORKS AND THE SITE. ANY DAMAGE TO EXISTING SERVICES SHALL BE                                      OTHERWISE APPROVED BY THE SUPERINTENDENT.
                                                                                                                                                                                                                d. ALL DISTURBED LAND MUST BE RENDERED EROSION-PROOF
                  RECTIFIED AT THE CONTRACTORS EXPENSE.                                                                                                                                                              BY THE ESTABLISHMENT OF 80% EFFECTIVE GROUND                        RD4.    SUBGRADE EVALUATION IS TO BE UNDERTAKEN IN ACCORDANCE WITH THE
                                                                                                      EW9.          ALL FILLING SHALL BE PLACED IN MAXIMUM 200mm LOOSE LAYER
                                                                                                                                                                                                                     COVER WITHIN 28 DAYS OF FINAL EARTHWORKS TRIM.                              PROCEDURES OUTLINED IN ARRB SR41 - A STRUCTURAL DESIGN GUIDE FOR
     GN6.         ALL WORK SHALL CONFORM WITH THE RELEVANT LOCAL AUTHORITY'S                                        THICKNESS WITH EACH LAYER COMPACTED TO AT LEAST 98% COMPACTING
                                                                                                                                                                                                                e. IN AREAS WHERE RUNOFF TURBIDITY IS TO BE                                      FLEXIBLE RESIDENTIAL STREET PAVEMENTS.
                  SPECIFICATIONS AND REQUIREMENTS.                                                                  AS MEASURED BY THE STANDARD METHOD DESCRIBED IN AS 1289.
                                                                                                                                                                                                                     CONTROLLED, EXPOSED SURFACES TO BE EITHER
                                                                                                                                                                                                                     MULCHED, COVERED WITH EROSION CONTROL BLANKETS                      RD5.    ALL KERBING SHALL CONFORM TO LOCAL AUTHORITY COUNCIL'S RELEVANT
                                                                                                      EW10.         REFER TO THE GEOTECHNICAL REPORT REGARDING REMOVAL AND
                                                                                                                                                                                                                     OR TURFED IF EARTHWORKS ARE EXPECTED TO BE                                  STANDARD DRAWINGS.
                                                                                                                    REPLACEMENT OF EXISTING FILLING MATERIAL. THIS NOTE SHALL APPLY TO
                                                                                                                    THE SUBGRADE UNDER ALL ROADS, DRIVEWAYS AND FILL BATTERS.                                        DELAYED FOR MORE THAN 14 DAYS.
                                                                                                                                                                                                                f.   STRAW BALE SEDIMENT TRAPS ARE A SECONDARY OPTION                    RD6.    ALL ROADSIDE VERGE AREAS AND BATTERS SHALL BE TOP S OILED TO A
                                                                                                                    FOLLOWING THE SITE STRIP AND DRIVEWAY SET OUT THE ENGINEER SHALL
                                                                                                                                                                                                                     WHICH GENERALLY SHOULD NOT BE USED IF OTHER                                 MINIMUM DEPTH OF 100mm (LIGHTLY COMPACTED) AND TURFED.
                                                                                                                    BE CALLED TO SITE TO DETERMINE THE PRESENCE OF ANY EXISTING FILL
                                                                                                                    UNDER DRIVEWAYS AND ASSOCIATED BATTERS. PROVIDE A BACKHOE FOR                                    OPTIONS ARE AVAILABLE.
     EARTHWORKS AND PAVEMENT                                                                                        THE TEST PIT EXPLORATION. THE ENGINEER MAY DIRECT EXISTING LOOSE
                                                                                                                                                                                                                                                                                         RD7.    PAVEMENT MARKINGS AND SIGNS SHALL BE PROVIDED IN ACCORDANCE WITH THE
                                                                                                                                                                                                                                                                                                 QUEENSLAND MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES.
                                                                                                                                                                                                     SE2.   SEDIMENT CONTROL FENCE:
     CONSTRUCTION NOTES                                                                                             FILL TO BE REMOVED AND RE-COMPACTED.
                                                                                                                                                                                                                g. NOT TO BE LOCATED IN AREAS OF CONCENTRATED FLOW.
                                                                                                                                                                                                                h. NORMALLY LOCATED ALONG THE CONTOUR WITH A                             RD8.    PROVIDE TELSTRA AND ENERGEX CONDUITS UNDER CONCRETE DRIVE-WAYS,
                                                                                                      EW11.         ALL DRAINAGE, EROSION AND SEDIMENT CONTROLS TO BE INSTALLED AND                                                                                                              WHERE DIRECTED.
     EW1.         THE CONTRACTOR SHALL PROVIDE CERTIFICATION FROM A RPEQ QUALIFIED                                                                                                                                  MAXIMUM CATCHMENT AREA 0.6 HA PER 100M LENGTH OF
                                                                                                                    FULLY OPERATIONAL BEFORE COMMENCING UP-SLOPE EARTHWORKS.
                  ENGINEER THAT THE WHOLE OF THE EARTHWORKS AND GEOTECHNICAL                                                                                                                                        FENCE.
                  SUPERVISION COMPLIES WITH AS3798.                                                                                                                                                             i.  WOVEN FABRICS ARE PREFERRED, NON-WOVEN FABRICS
                                                                                                      EW12.         ALL EXISTING UNDERGROUND SERVICES TO BE LOCATED AND MARKED
                                                                                                                    PRIOR TO COMMENCING EARTHWORKS.                                                                 MAY BE USED ON SMALL WORK SITES, I.E. OPERATIONAL                    DRAINAGE NOTES
     EW2.         THE CONTRACTOR SHALL REFER TO GEOTECHNICAL INVESTIGATION                                                                                                                                          PERIOD LESS THAN 6 MONTHS OR ON SITES WHERE                          DN1.    1.5m WIDE EASEMENTS SHALL BE CREATED OVER ALL INTER-ALLOTMENT
                  REPORT - (IF AVAILABLE)                                                                                                                                                                           SIGNIFICANT SEDIMENT RUNOFF IS NOT EXPECTED.
                                                                                                      EW13.         FILL DENSITY TESTING SHALL CONFORM TO THE FOLLOWING:                                                                                                                         DRAINAGE LINES UNO.
     EW3.         ALL EXISTING UNDERGROUND SERVICES TO BE LOCATED AND MARKED PRIOR                                                                                                                              j.  WHERE FENCES NEED TO BE LOCATED ACROSS THE
                                                                                                                          a. 1 TEST PER 500 cu.m - GENERALLY
                  TO COMMENCING EARTHWORKS.                                                                                                                                                                         CONTOUR - REFER IPEAW STANDARD DRAWING D-0040 FOR
                                                                                                                         b. 1 TEST PER 2 LAYERS PER 40m - TRENCH BACKFILL                                                                                                                DN2.    PIPE BEDDING AND BACKFILL ARE IN ACCORDANCE WITH LOCAL AUTHORITIES
                                                                                                                                                                                                                    DETAILS.                                                                     REFERENCED SPECIFICATION AND/OR STANDARD DRAWINGS.
     EW4.         THE LIMITS OF CUTTING AND FILLING SHALL BE GENERALLY AS SHOWN ON THE                                                                                                                          k. FENCES ARE REQUIRED 2m MIN FROM TOE OF CUT OR FILL
                                                                                                      EW14.         PLACEMENT OF FILL SHALL CONFORM TO THE FOLLOWING MINIMUM DRY
                  DRAWINGS. THE CONTRACTOR SHALL SET OUT THESE LIMITS FOR INSPECTION                                                                                                                                BATTERS, WHERE NOT PRACTICAL ONE FENCE CAN BE AT
                                                                                                                    DENSITY RATIO (M.D.D.R.) COMPACTION STANDARDS:                                                                                                                       DN3.    PIPE MATERIALS ARE UPVC SEWER PIPE MINIMUM CLASS SN4; UPVC DRAINAGE
                  BY THE ENGINEER PRIOR TO CONSTRUCTION. AMENDMENTS TO EARTHWORKS                                                                                                                                   THE TOE WITH A SECOND FENCE 1M MIN AWAY. FENCE
                                                                                                                        c.   ALLOTMENTS = 98% STD                                                                                                                                                PIPE PLASCOR OR EQUIVALENT OF EQUIVALENT CLASS TO UPVC SEWER CLASS
                  AND FINISHED SURFACE CONTOURS MAY BE ADJUSTED BY THE WRITTEN                                                                                                                                      SHOULD NOT BE LOCATED PARALLEL WITH TOE IF
                                                                                                                        d. ROAD VERGES/EMBANKMENTS = 98% STD                                                                                                                                     SN4; R.C.P. CLASS "2" RUBBER RING JOINTED OR F.R.C. PIPE CLASS "X" RUBBER
                  DIRECTION OF THE ENGINEER DURING CONSTRUCTION.                                                                                                                                                    CONCENTRATION OF FLOW WILL OCCUR BEHIND THE FENCE.
                                                                                                                        e. PAVEMENT SUBGRADE = 100% STD FOR NON-COHESIVE                                                                                                                         RING JOINTED.
                                                                                                                             MATERIALS, M.D.D.R. = 80%
     EW5.         SITE PREPARATION:                                                                                                                                                                  SE3.   TEMPORARY CONSTRUCTION ENTRY/EXIT SEDIMENT TRAP:                             DN4.    UPVC PIPES ARE EITHER RUBBER RING JOINTED OR SOLVENT WELD JOINTED.
                  a. STRIP TOPSOIL MIN 150 OR MORE AS REQUIRED TO REMOVE ALL                                                                                                                                    l. ADJACENT STORMWATER RUNOFF TO BE DIVERTED AWAY                                STANDARD MANUFACTURER'S FITTINGS ARE USED IN BOTH CASES.
                       VEGETABLE MATTER TO THE BASE OF THE SUB GRADE.                                                                                                                                              FROM ENTRY/EXIT.
                                                                                                                                                                                                                m. WHEEL - WASH OR SPRAY UNIT MAY BE REQUIRED DURING                     DN5.    FRC AND RCP SYSTEMS ARE CONSTRUCTED BY EMBEDDING THE LOWER PRECAST
                  b.   FURTHER EXCAVATE IF REQUIRED TO BOX OUT TO MINIMUM PAVEMENT                                                                                                                                 WET WEATHER.                                                                  SECTION INTO A WET CAST-INSITU CONCRETE BASE. CUT OUTS FOR PIPE
                       THICKNESS. REMOVE AND RE-COMPACT FILL AS PER GEOTECHNICAL
                                                                                                                                                                                                                                                                                                 PENETRATIONS ARE MADE USING CONCRETE SAWS/DRILLS WHILE MINIMIZING
                       REPORT NOTE ON THIS DRAWING.                                                                                                                                                  SE4.   SAFETY ISSUES MUST BE CONSIDERED AT ALL TIMES, INCORPORATE                           DAMAGE TO THE ADJACENT PIPE MATERIALS.
                                                                                                                                                                                                            TRAFFIC CONTROL DEVICES .
                  c.   COMPACT SUBGRADE TO A MIN RELATIVE DENSITY RATIO OF 98%
                                                                                                                                                                                                                                                                                         DN6.    LIDS TO CAST-IN-SITU MANHOLES ARE LIGHT DUTY, CLOSE FITTING BOLT DOWN
                       STANDARD COMPACTION AS DEFINED IN AS 1289 IN THE TOP 200.                                                                                                                     SE5.   IT IS THE CONTRACTOR'S RESPONSIBILITY TO ENSURE THAT ALL
                                                                                                    ASSOCIATED CONSULTANTS DETAILS                                                                          SEDIMENT AND EROSION CONTROL MEASURES HAVE BEEN
                                                                                                                                                                                                                                                                                                 CAST IRON OR GALVANISED STEEL, CONCRETE INFILL TYPE (GATIC LIGHT DUTY,
                                                                                                                                                                                                                                                                                                 POLYCRETE BROADSTEL OR SIMILAR) OF APPROXIMATELY THE SAME INTERNAL
                  d.   COMPACT AND PROOF ROLL ALL PREPARED SUBGRADE AREAS PRIOR TO                                                                                                                          ADDRESSED AS STIPULATED IN THE ENVIRONMENTAL MANAGEMENT
                                                                                                      AC1. REFER ARCHITECTURAL CONSULTANT FOR:                                                                                                                                                   DIMENSIONS AS THE MANHOLE.
                       PLACING ANY FILLING. COMPACTION SHALL BE 100% COMPACTION AS                                                                                                                          PLAN. ADDITIONAL OR DIFFERENT SEDIMENT & EROSION CONTROL
                       MEASURED BY THE STANDARD METHOD DESCRIBED IN AS1289 UNO.                               a. BUILDING AND CARPARK LAYOUT AND SETOUT
                                                                                                                                                                                                            DEVICES MAY BE REQUIRED DURING CONSTRUCTION PHASE TO                         DN7.    ALL STEEL GRATES AND FRAMES TO BE HOT DIPPED GALVANIZED AND SHALL BE
                                                                                                              b. BUILDING SET DOWNS EXTERNALLY
                                                                                                                                                                                                            COMPLY WITH THE ABOVE.                                                               CYCLE PROOF IN ACCORDANCE WITH AS 3996.
                  e.   EXCAVATE AND REPLACE WITH STRUCTURAL FILL ANY SOFT SPOTS OR
                       HEAVING SUBGRADE AREAS. STRUCTURAL FILL SHALL BE APPROVED                      AC2. REFER LANDSCAPE ARCHITECTS FOR:
                                                                                                                                                                                                     SE6.   TEMPORARY STOCKPILES TO HAVE 1:6 SIDE BATTERS (MAXIMUM) AND                  DN8.    LIDS MATCH FINISHED SURFACE GROUND SLOPE AND SIT PROUD AS SHOWN ON
                       GRANULAR FILL (100mm MAXIMUM PARTICLE SIZE, MINIMUM SOAKED CBR                         c.  ALL CONCRETE HARDSCAPE FINISHES INCLUDING ROADS,
                                                                                                                                                                                                            BE SHAPED TO ENSURE RUN-OFF IS TREATED AND MANAGED TO THE                            THE LOCAL AUTHORITIES STANDARD AND ARE MARKED "STORMWATER"
                       15 PLACED IN LAYERS NOT EXCEEDING 200mm AND COMPACTED TO                                   CARPARKS, FOOTPATHS AND FOOTPATH BANDS
                                                                                                                                                                                                            SATISFACTION OF THE SUPERINTENDENT. ALL EXPOSED STOCKPILE                            IMPRESSED INTO THE CONCRETE INFILL. INFILL CONCRETE IS CLASS N25.
                       ACHIEVE NOT LESS THAN 98 % MAXIMUM RELATIVE DRY DENSITY                                d. ALL EXTERNAL CONCRETE HARDSCAPE FINISHES FOR
                                                                                                                                                                                                            SURFACES TO BE GRASS SEEDED. SEDIMENT FENCES AND CUT-OFF
                       (STANDARD), OR 75 % DRY DENSITY INDEX IN ACCORDANCE WITH AS 1289.                          PEDESTRIAN / CYCLE PATHWAY LINKS.
                                                                                                                                                                                                            DRAINS MAY BE REQUIRED.                                                      DN9.    MATERIALS AND CONSTRUCTION ARE IN ACCORDANCE WITH COUNCIL'S
                       SITE FILLING MATERIAL AND COMPACTION UNDER THE PAVING AND
                                                                                                      AC3. HYDRAULIC CONSULTANTS                                                                                                                                                                 STANDARD SPECIFICATION FOR STORMWATER DRAINAGE.
                       BUILDING SHALL BE AS ABOVE.
                                                                                                              e. INTERNAL SEWERAGE LAYOUT
                                                                                                              f. INTERNAL DRAINAGE FOR ROOFWATER AND RAINWATER                                                                                                                           DN10.   THE CONTRACTOR SHALL CONFIRM ALL LEVELS BEFORE COMMENCING WORK.
                                                                                                                 TANKS
                                                                                                              g. INTERNAL RETICULATION WATER MAINS                                                                                                                                       DN11.   THE CONTRACTOR SHALL CONTACT ALL RELEVANT AUTHORITIES AND LOCATE
                                                                                                                                                                                                            NOTE:
                                                                                                                                                                                                                                                                                                 ALL SERVICES BEFORE COMMENCING WORK.THE CONTRACTOR SHALL BE
                                                                                                                                                                                                            EROSION AND SEDIMENT CONTROL MEASURES ARE TO BE DESIGNED
                                                                                                                                                                                                                                                                                                 RESPONSIBLE FOR ANY DAMAGE CAUSED TO SERVICES BY THE WORKS
      UNDERGROUND SERVICES                                                                            AC4. REFER SURVEYOR FOR:
                                                                                                              h. PSM TO AHD
                                                                                                                                                                                                            AND PROVIDED IN ACCORDANCE WITH THE INTERNATIONAL EROSION
                                                                                                                                                                                                                                                                                                 IRRESPECTIVE OF WHETHER THE SERVICES ARE SHOWN ON THE DRAWINGS OR
                                                                                                                                                                                                            CONTROL ASSOCIATION (AUSTRALASIA) 2018's "BEST PRACTICE
                                                                                                              i.  EXISTING CONTOURS, SPOT LEVELS, SERVICES,                                                                                                                                      NOT.
      UNDERGROUND SERVICES HAVE BEEN LOCATED ONLY WHERE OBVIOUS. SOME SERVICES                                                                                                                              EROSION AND SEDIMENT CONTROL FOR BUILDING AND
      THAT WERE NOT OBVIOUS AND ARE NOT SHOWN ON THE PLAN MAY STILL BE PRESENT. IT                                BUILDINGS, FENCES, ETC.                                                                   CONSTRUCTION SITE.
      IS THE RESPONSIBILITY OF ANY PERSON EXCAVATING / BUILDING, ON OR ADJACENT TO
      THE SITE TO CONFIRM WITH THE RELEVANT AUTHORITY THE LOCATION OF SERVICES.
      THE AUTHOR OF THIS PLAN ACCEPTS NO RESPONSIBILITY FOR DAMAGE TO SERVICES
      SHOWN OR NOT SHOWN ON THIS PLAN.




                                                                                                                                                                                                                                                                        PROJECT:                                                                             JOB NUMBER
REV DATE DESCRIPTION                                   BY     CHKD DRAWN
                                                                       I GDETAL
                                                                              IS                                                 SCALE                                            APPROVED                                                                              PROPOSED CULVERT CONSTRUCTION                                                            1443
 A   14/07/2020   FOR APPROVAL                          LN      DK                                                                                                                                                                                                      20 MITTI STREET, NOOSA HEADS
 B   23/07/2020   MINOR CHANGES                         LN      DK    DATUM                AHD                                                                                                                                                                                                                                                          SHEET:    2   OF     6
                                                                                                                                                                                                                                                                        FOR P LOXTON & S TRITTON
                                                                      DESIGN               LN
                                                                                                                           NOT TO SCALE                                          .................                                                                                                                                                      DRAWING NUMBER           REV
                                                                                                                                                                                                                                                                        DRAWING TITLE:
                                                                      DRAWN                LN                                                                                      DANIEL KENNA
                                                                                                                                                                                                             p 07 5443 8285                                             GENERAL NOTES                                                                                            B
                                                                      DESIGN CHECK         DK                                                                                      (RPEQ 15522)
                                                                                                                                                                                                             e [email protected] w www.barlowshelley.com.au
                                                                                                                                                                                                                                                                                                                                                             R02
                                                                                                   This drawing is not to be copied or amended without written permission from
                                                                      DATE            14/07/2020   Barlow Shelley Consulting Engineers                                                                       a PO Box 899, Maroochydore,4558 ABN 89 215 591 077

Used in these records

About this file

File size
1.2 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

1443-Civil Rev D 2020-09-07.pdf · 1.2 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.