GENERAL COMMITTEE MEETING AGENDA 13 FEBRUARY 2017
Recurrent Expenditure (YTD Benchmark 58%)
Operating expenditure is currently 55% of the full year budget forecast. Detailed commentary for
each expenditure category appears below:
Employee Costs – Actuals of $16.0m against the YTD budget of $16.4m and equates to 56%
of the full year budget. This is represented by an under-expenditure of the training allocation
($119k), a rebate for Work Cover premiums ($37k), and recovery from labour allocations to
capital projects exceeding budget.
Materials and Services – $20.8m (51% of the full year budget) has been expended compared
to the YTD budget of $21.6m. Year to date variances primarily relate to contract services
budgets, specifically under expenditure in electricity costs ($79k); insurance costs ($24k);
Waste operations ($135k); ICT Operations ($116k); Fleet & Plant operations ($64k); Library
Services ($47k); and Property & Facilities ($70k). Civil Works is below budget ($369k); and
Planning costs are currently ahead of budget by $234k due to ongoing appeal defence costs.
Levy related expenses also shows under-expenditure of $72k against YTD budget forecasts.
All significant variances will be investigated for possible adjustment with the current budget
review.
Finance Costs – bank merchant fees ($16k) and interest on loans ($35k) are currently below
the YTD budget.
Depreciation expenses – actual depreciation exceeds the YTD budget by $323k. A revised
forecast will be done as part of the current budget review to account for a higher than
anticipated impact of asset revaluations undertaken as at 30 June 2016.
Other Expenses – in accordance with YTD budget.
Figure 3: Recurrent Expenditure Position by Type
$25
YTD Budget ($m)
$20
YTD Actual ($m)
$15
$10
$5
$0
Materials
Finance Costs
Depreciation
Employees
Other
Capital Revenue
YTD capital revenue of $3.7m received includes $2.4m of cash contributions from developers,
together with $1.3m received as grant funding towards capital projects, including $200k (TIDS);
$153k (Natural Disaster Relief and Recovery); $303k (Rufous Street Project); $75k (Natural
Disaster Resilience Program – Flood studies and flood gauges); $275k (Bus Shelter Disability
Upgrade program); $288k (Cycle Network Program); and $11k Road Safety Grant. Adjustments
will be made as part of the budget review currently underway to account for annual trend and
grant revenue not originally included in the budget.
Page 56 of 61
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.