SUPERSEDED - Approved Plan - OPW23/0084
Plans and drawings: the text below has words only, no drawings.
Personnel Base Architecture are responsible for:
responsible
• Ensuring the engaged FSC possesses all required qualifications.
• Ensuring that clearing works cease immediately if dictated by the FSC, e.g. if
a Koala is identified within 100m of works, or if injured fauna requires
immediate transportation to a veterinarian/carer.
The Clearing Contractor is responsible for:
• Communicating clearly with the FSC by use of radio, hand signals or other
agreed upon methods.
• Ceasing clearing and/or dewatering while the FSC is assessing fauna,
inspecting habitat features, transporting or relocating fauna, or is otherwise
engaged.
The FSC is responsible for:
• Managing all fauna during works.
• Maintaining detailed records of all fauna interactions and habitat features and
preparing reports.
Reporting and The FSC / Ecologist is responsible for:
auditing
• Providing Base Architecture with information pertaining to fauna
management during works, as part of the Post-Clearance Report.
• Maintaining a fauna register and submitting applicable returns to DES as per
permit requirements.
Corrective action In the event that practices are inconsistent with the strategies outlined in this FMP,
the Contractor should take the corrective steps and report non-compliance to the
relevant personnel.
Timing The duration of the clearing period.
FAUNA MANAGEMENT PLAN | Summit Road, Pomona
23
Document Set ID: 22570982
Version: 1, Version Date: 05/09/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.