Skip to the record
Trusted by locals. Built for Noosa.

Original source · versioned page text

Part C - Attachments E to G

Attached to the e-mail Other Change Application – 132002.220285.5.

of 69

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (15.1 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 18, section 1. The text section number identifies this passage in the reader.

311


[OCR of page images]
NOOSA COUNCIL IDAS Development Application Decision Notice 17

94.

95.

96.

97.

98.

99,

100.

101.

102.

103.

104.

105.

106.

107.

108.

The design of the evaporative cooling system shall seek to optimise energy efficiency by identifying
and maximising the advantage of the prevailing winds at the site.

Spectrally selective and/or low emissivity glass shall be incorporated where appropriate in the detailed
design, so as to reduce heat transmission to and from buildings.

Hot water requirements of the site are to be provided by solar powered hot water systems, heat
pumps, or heat recovered from refrigeration or air-conditioning systems subject to compliance with
relevant health regulations. Where it is demonstrated to be satisfactory. by the Manager —
Environmental Services that such technology is impracticable, five star solar gas hot water will be
accepted as an alternative.

The developer shall seek to apply the energy efficiency strategies listed at Table 5.1 of the Energy
Efficiency Assessment report where appropriate in the detailed design of buildings.

Use the Australian Greenhouse Building Rating System (AGBR) scheme to rate the greenhouse and
energy performance for commercial/business precinct of the NSBC.

The developer shall prepare and implement a Building Energy Performance Management and
Monitoring Plan (“BEPMMP") to the reasonable satisfaction of the Manager Land Use, dealing with
programmed time controlled scheduling for all areas capable of separable operation, demand
management, trend logging, energy usage monitoring and reporting and exception events reporting.
The developer shall report to the Council in writing the results of the monitoring of performance
against the BEPMMP on the first, second and third anniversaries of the commencement of use Stage
1 of the NSBC. The report shall note the strategies and recommendations of the Parsons Brinckerhoff
report (April 2003) that have been carried through to the development.

Deleted.

The proposed wind catcher ventilation shafts shall be designed to achieve optimal internal ventilation
of buildings consistent with acceptable standards of comfort.

The developer will design tenancy agreements to ensure that any self-contained commercial
refrigeration used on site will meet any mandatory minimum energy performance standards for self-
contained commercial refrigeration to be introduced from July 2005. The developer will also design
tenancy agreements to ensure that in general all appliances used on site are as energy efficient as
possible.

Waste Management & Recycling

The applicant must provide a suitably screened imperviously paved area large enough for all refuse
and recycling containers for each building complex. A wash down area is required with a cold-water
tap, hose and drain outlet connected to sewer. The drain outlet is to be designed to prevent
stormwater entry to the sewerage system.

Refuse containers must be provided in accordance with the requirements of the Environmental
Protection (Interim Waste) Regulations 1996 and (Waste Management) Regulation 2000, for the
storage and collection of refuse.

The development must allow refuse-loading areas to be located off street. All vehicles associated with
the collection of waste/recyclables, shall enter and leave the site in a forward direction. ©

The applicant is to ensure that operational procedures are in place for the prevention of wind blown
litter on the site during both the construction and operational phases of the development.

Street litterbins and recycling bins to a design approved by Council, shall be supplied and installed at
the applicants expense at agreed locations.

The applicant shall submit a Waste Management Plan (WMP) for the construction phase of the
development prior to the issue of a development permit for operational works. The WMP shall be to
the reasonable satisfaction of the Manager Environmental Services, and shall contain information
generally in accordance with the following:-

A o\databaselonestop\decision.doc

311

 
Log in to download the original file

Part C - Attachments E to G.PDF · 15.1 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.