Decision Notice Owner's Consent - 25 Wyuna Drive, Noosaville
Notice
Planning Act 2016
Land Act 1994
Decision – owner’s consent
This notice is issued by the Administering Authority pursuant to section 51 of the Planning Act 2016 to provided owner’s
consent as delegated under the Land Act (Ministerial) Delegation.
Our reference : Zendesk192830
BY EMAIL
Attn: Director
Wyuna Drive Pty Ltd A.C.N. 672 438 514 Trustee Under Instrument 723296136
C/- Marine Structures
18 Ron Parkinson Crescent
Corbould Park QLD 4551
[email protected]
Dear Sir/Madam,
Re: Request for granting of owner’s consent for proposed application for tidal works on State land
below high water mark
The Department of the Environment, Tourism, Science and Innovation, under the Land Act (Ministerial)
Delegation has assessed your application received on 28 January 2025 and wishes to advise you of the
decision as specified below:
Wyuna Drive Pty Ltd A.C.N. 672 438 514 Trustee Under Instrument
Property owner:
723296136
Activity: Prescribed Tidal Works and Material Change of Use
The construction of pontoon and gangway, and removal of existing
Activity description:
pontoon and two (2) piles.
LAYOUT PLAN prepared by Marine Structures, reference TJS-05028-
Plan / Drawing number: 02, revision B, dated 17/02/2025.
ELEVATION prepared by Marine Structures, reference TJS-05028-03,
reivision A, dated 02/12/2024.
Lot 12 on Plan N10576
Description of subject land: 25 Wyuna Drive
Nooseville QLD 4566
Owner’s consent has been granted. The application may proceed.
Decision
Standard conditions may apply
Page 1 of 2 • ESR/2015/1607 • Version 5.03 • Effective: 9 FEB 2024 ABN 46 640 294 485
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 1 page
Page 2
Notice
Decision – owner’s consent
Decision Number OC010003405
Owner’s consent can be used to support a development application
THIS DECISION IS CURRENT FOR until 4 April 2026. Should the development application not be lodged
12 MONTHS with the assessment manager prior to this date, you will be required
to lodge a further request for owner’s consent.
Although owner’s consent to the development application has been provided and no tenure under the Land Act
1994 is required, works can only commence when the development application has been approved by the
assessment manager, and in accordance with the conditions of that approval.
The provision of owner’s consent over State land means that the State has no objection to the lodgement of the
application for a development approval. It does not:
• imply approval of the development application; or
• authorise a right to use and occupy land.
The State may act at a later date as assessment manager, concurrence/referral agency, or technical agency in
the assessment of the development application – providing owner’s consent will not influence any statutory role
the State may have in this assessment.
If the development application involves a State resource in addition to State land, then the allocation or
entitlement to use the State resource is a separate process and should be obtained prior to development
commencing.
You will also need to comply with all other legislative and regulatory requirements which may include approvals
that are not part of the assessment of the development application under the Planning Act 2016 e.g. a marine
park permit if in a marine park.
A copy of this notice is to be attached to your Development application Form 1 as the required evidence of
owner’s consent.
If you require more information please contact Bronwyn Bell on the telephone number listed below.
Yours sincerely
4 April 2025
Signature Date
Delegate Enquiries:
Bronwyn Bell Bronwyn Bell
Team Leader Team Leader
Coastal & Marine Assessment Coastal & Marine Assessment
Department of the Environment, Tourism, Science Department of the Environment, Tourism,
and Innovation Science and Innovation
GPO Box 2454 BRISBANE QLD 4001
Phone: 07 3330 6231
Email: [email protected]
Page 2 of 2 • ESR/2015/1607 • Version 5.03 • Effective: 9 FEB 2024 Department of the Environment, Tourism, Science and Innovation