RFI - RECOR Preliminary Stormwater Management Report - 20220078
Original PDF page 9, section 1. The text section number identifies this passage in the reader.
Figure 3.2 – DRAINS Pre-development catchment
Figure 3.3 – DRAINS Post-development catchments
Figure 3.4 – DRAINS Split Post-development catchments
The results of the modelling against the range of design storms for the development under the existing and
proposed development conditions are shown in Table 3.1 Existing and proposed unmitigated site peak discharge
rates.
Table 3.1 Existing and proposed unmitigated site peak discharge rates
Wyandra Street
Qchange
A.E.P Qexisting Qproposed Qchange (%)
(m³/s) (m³/s) (m³/s)
1EY 0.016 0.018 0.002 13%
50% 0.019 0.02 0.001 5%
0.2 EY 0.028 0.03 0.002 7%
10% 0.036 0.036 0 0%
5% 0.041 0.041 0 0%
2% 0.047 0.047 0 0%
1% 0.051 0.052 0.001 2%
Project number 20220078
File RECOR Preliminary Stormwater Management Report - 20220078, 2022-11-11 Page 9 of 16
Revision 2
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.