GENERAL COMMITTEE MEETING AGENDA 16 MAY 2022
Page 81 of 96
GENERAL COMMITTEE MEETING AGENDA 16 MAY 2022
Corporate Plan Key Operational Initiatives Outcomes Responsible Update Status Q2 ek)
Focus Areas Areas/Officers
Noosa Hinterland recreation | Increased recreational Environmental | Trail S Detailed Audit and negotiations with On track | On track
trails upgrade/implement opportunities and improved | Services, QPWS regarding realignment opportunities have
Noosa Trails Master Plan, multi use trails and linkages | Infrastructure | been completed. Initial Environmental and
Audit of the trail network within the trails network Planning, Cultural Heritage Field Assessments completed.
Design & Preparation of tender documents for design and
Delivery. construct contract underway.
Infrastructure | Planning and design work has commenced on
Planning trail head and trail node facilities including an
Design & update of the Noosa Trail Signage Manual.
eee Contract awarded for the Cooran Horse Yards
upgrade 27 March 2022.
Council have approved the Noosa Biosphere Trail
Concept. This is the basis for a series of audits to
identify preferred alignments and the
development of an implementation plan.
Display maps and design work for the Noosa
Biosphere Trail and Trail 5 are currently being
prepared for display at the Pomona Markets along
with draft signage manual & guidelines. The
Noosa Trail Masterplan Stakeholder Group will be
invited to attend the display.
connectivity within the shire | Planning, Design | shared pathway at Noosa Drive, Halse Lane to
& Delivery Sunshine Beach Rd.
Infrastructure
Planning Design| Extension of time granted with revised completion
& Delivery date of Design December 2022.
Manager
4.3 Implement the Undertake non powered water] Delivery of land use Community Contractor appointed, consultation to commence | Ontrack | On track
Noosaville Foreshore} sports feasibility study outcomes identified in the Development, | early 2022.
Land Use Noosa Foreshore Land Use | Property/
Management Plan Master Plan Community
Development
Manager
4.4 Ensure effective | Develop the new Corporate Progress towards achieving Development of new Corporate Plan to be Not Not started
service planning Plan Council's long term vision undertaken and finalized by the CEO by the end | started
processes are in and to provide strategic of 2022.
place direction to council over the
next 5 years
Page 81 of 96See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.