ORDINARY MEETING AGENDA 21 JUNE 2018
Capital Revenue
YTD capital revenue of $6.9 million received comprises cash contributions from developers
($1.7m), contributed assets from developers ($1.0m) and capital grants ($4.1m). Note that the
timing of capital grant receipts are generally dependent on the timing of grant conditions and also
capital delivery performance, and that the timing of the receipt of developer contributions (both
cash and contributed) is unpredictable.
Figure 4: Capital Revenue by Type
$4.5
YTD Budget ($m)
$4.0
YTD Actual ($m)
$3.5
$3.0
$2.5
$2.0
$1.5
$1.0
$0.5
$0.0
Contributed assets
Cash contributions
Grants / subsidies
Capital Program
Actual capital expenditure (excluding commitments) is $21.2 million (YTD budget $26.6 million).
Detailed discussion of progress in the delivery of the capital works program is provided through a
separate report by the Asset Planning Manager.
Figure 5: Capital Program Delivery Performance
$25.0
YTD Budget ($m)
YTD Actual ($m)
$20.0
$15.0
$10.0
$5.0
$0.0
Capital works Other capital
Page 29 of 35
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.