NOOSA COUNCIL IDAS Development Application Decision Notice 4 of 7
10. A Road/Footpath Permit shall be completed and submitted for the construction of the access driveway in
accordance with Council’s Local Law No.8. If approval is given the driveway shall be constructed in
accordance with Council’s standard drawings, which will be provided at time of approval.
Roof Water & Stormwater Drainage
11. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
storage 5000 litres per dwelling) that is installed to ensure water from the tank is used for external uses
(such as watering gardens, irrigation, ornamental ponds, water features, topping-up swimming pools,
outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All rainwater tanks are to
be designed and installed in accordance with the Queensland Development Code (QDC), Part 25 –
Rainwater Tanks, and shall be part of the plumbing application in conjunction with the building approval.
The location and capacity of the tanks shall be clearly shown on the plans submitted for Building Works
approval and any overflow shall be directed to the road frontage.
12. All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
drainage permitted to drain from the site shall be discharged to Council’s kerb & channel street drainage
system in Albert Street.
13. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
14. The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
15. The site shall be connected to Council’s existing town water supply and be constructed in accordance with
Council’s standards and requirements at no cost to Council.
Earthworks
16. Filling works required on site shall be carried out in accordance with Section 3.8 of Council’s Engineering
Design Standards Manual and so as not to cause the additional ponding of water on any adjoining lands
or the blockage of, or interference with, any natural watercourses. In this regard an overland stormwater
flow path, generally in accordance with drawing number 17071-C1 dated July 2007 prepared by SCG
Consulting engineers, shall be provided adjacent to the rear boundary of the subject site to drain surface
runoff from the adjoining property to the Council drainage system located in the adjoining pathway.
17. Earthworks carried out on site shall not affect the structural integrity of any of the existing fences or
structures that border the development site. Fences that are affected shall be replaced prior to the
Building Certifier issuing the Certificate of Classification. In this regard any fences to be replaced shall be
clearly shown on the plans submitted for Operational Works approval.
Erosion and Sediment Control
18. Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
waste, will be necessary.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@a40174cb\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
00157B3E.001.pdfRelated documentPublic source context ↗
Decision Notice - 010.2007.00000763.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 30 KB (small file)
- File type
No other editions are linked here.