SUPERSEDED - Approved Decision Notice - MCU25 0079 [As Published]

of 16

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                                                             Officer:            Andrew Gaffney
                                                             Direct Telephone:   07 53296284
                                                             Our Reference:      MCU25/0079:
                                                             Your Reference:     250107

               16 December 2025


               Sunrise Equities Pty Ltd TTE
               C/- URBN Town Planning Pty Ltd
               PO Box 81
               BUDERIM QLD 4556
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 10 December 2025, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              MCU25/0079

                   Street address:              4 Ventura St Sunrise Beach Qld 4567

                   Real property description:   Lot 83 RP 132135

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit Material Change of Use – Multiple Dwellings (1 x Dwelling, 3 x Small
                       Dwellings).
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

                           DEVELOPMENT PERMIT FOR MATERIAL CHANGE OF USE (MCU25/0079)
               PLANNING
                       When Conditions must be Complied With
               1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                       the use commencing, and then compliance maintained at all times while the use continues.
                       Currency Period

               ABN 97.969.214.121                                                                        PO Box 141
               noosa.qld.gov.au                                                                   Tewantin QLD 4565
               [email protected]                                                                   07 5329 6500
                                                                                                            Page 1 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025
Log in to download the original file

SUPERSEDED - Approved Decision Notice - MCU25 0079 [As Published].pdf · 513 KB (small file)

Full text of the other 15 pages

Page 2

               2.     This development approval lapses if the use has not happened by 10 December 2031,
                      unless an application to extend the currency period is approved by Council.
                      Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the tables below. The plans must be amended to incorporate
                      the amendments listed within the table below and resubmitted to Council prior to the issue
                      of any Development Permit for Operational Works*
                      The following plans require amendment.

                         Plan No.           Rev.   Plan/Document Name                            Date

                         UO2                -      Site Plan prepared by Icon Building Design    25/11/2025

                         UO3                -      Units – Ground Floor prepared by Icon 25/11/2025
                                                   Building Design

                         UO4                -      Units – First Floor prepared by Icon Building 25/11/2025
                                                   Design

                         UO5                -      Elevations   prepared    by   Icon   Building 25/11/2025
                                                   Design

                         UO6                -      Elevations   prepared    by   Icon   Building 25/11/2025
                                                   Design

                         UO8                -      Landscaping prepared by Icon Building 25/11/2025
                                                   Design

                         U11                -      Heights prepared by Icon Building Design      25/11/2025

                         U13                -      Height assessment RF1.0 prepared by Icon 22/09/2025
                                                   Building Design

                         Amendment 1        Provide revised site plan to remove the decking associated with Unit
                                            4 (existing dwelling) and provide revised landscaping plan to reflect
                                            soft landscaping in replacement of the decking.

                         Amendment 2        Provide revised plan set clearly demonstrating compliance of site
                                            coverage of 45 % / ~ 414.4m2
                                            Note: Any structures greater than 1 metre above ground level will
                                            contribute to site cover such as balconies, patios, decks, above
                                            ground swimming pools and the like.

                         Amendment 3        Provide revised plans to achieve a minimum of private open space
                                            area of 9m2 on the upper-level balconies, with a minimum width of
                                            2.5 metres accessed directly from the living spaces.

                      *(Refer to Advisory Note)
                      Nature and Extent of Approved Use
               4.     The approved development consists of Multiple dwellings (1 x dwelling, 3 x small dwellings).
                      Building Height
               5.     The maximum height of the development must not exceed 8.0 metres above ground level.




                                                                                                    Page 2 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 3

               6.     Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
                      certifies that the buildings do not exceed the maximum height requirement of this Decision
                      Notice.
                      Performance Bond
               7.     Security in the form of a cash bond or trading bank guarantee to the sum of $20,000 must
                      be submitted to Council, to secure performance of all conditions of this approval, prior to the
                      issue of a Development Permit for Operational Works. The cash bond or trading bank
                      guarantee will be returned on performance of the conditions of approval less any costs
                      incurred by Council in respect of enforcing performance of this permit. Council reserves the
                      right to call upon the bond or guaranteed sum to effect compliance with conditions.
                      Street Identification
               8.     The street address of the development must be clearly visible and discernible from the
                      primary frontage of the site by the provision of a street number and, where appropriate, the
                      building name.
                      Water & Sewer Connections
               9.     An underground connection to reticulated water and sewerage must be provided to the
                      premises in accordance with the standards and requirements of Northern SEQ Distributor–
                      Retailer Authority (Unitywater).
               10.    A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
                      must be submitted to Council that certifies an underground connection to reticulated water
                      and sewerage has been provided to the premises.
                      Building Appearance
               11.    External design features, materials and finishes must be as shown on the Approved Plans,
                      with no inclusions or alterations made without approval in writing by Council.
               12.    External finishes of the building must be a mix of lightweight and textured external finishes,
                      with masonry areas incorporating a variety of textured finishes to break up the surface.
               13.    All deck and balcony areas must not be enclosed with shutters, louvres, glass panelling or
                      the like thus remaining as open structures, except where required to satisfy any privacy
                      condition of this Decision Notice.
               14.    External colours and finishes must be of an understated colour scheme and low-reflective
                      roofing and cladding materials.
               15.    A variation in external colours is required for each unit.
               16.    All side boundary fencing or a combination of fence and retaining wall does not exceed 2.0
                      metres in height above neighbouring ground level.
               17.    All air conditioning units or other mechanical equipment must be fully enclosed or screened
                      such that they are not visible from the street frontages nor adjoining properties.
               18.    Waste storage areas, clothes drying areas and external storage areas must be screened
                      from view of the street.
                      Protection of Privacy
               19.    To ensure privacy is protected between adjoining properties, upper level windows facing the
                      northern or southern side boundaries for Units 1 & 3 must either:
                      a.      have a minimum window sill height or 1.7 metres above floor level
                      b.      be fitted with translucent glazing;
                      c.      be fitted with a fixed external screens.




                                                                                                       Page 3 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 4

               20.    The upper level balconies for Units 1 & 3 must include either balcony planter boxes,
                      balustrading or fixed external screens, positioned in such a way to obscure direct views into
                      the habitable room windows or private open space areas of the adjoining property. Any fixed
                      external screen(s) must not extend more than 50% of the length of the balcony.
                      Landscaping Works
               21.    The development site must be landscaped. The works must be undertaken in accordance
                      with an Operational Works approval and the Noosa Plan for that specific area and must
                      include in particular:
                      a.      the works shown on the Approved Plans;
                      b.      provision of 1 street tree for every 8 metres of road frontage within the Ventura and
                              Clipper Street road reserves.
                      c.      rear courtyards of new units to be landscaped to contain a combination of ground level
                              turfing, soft landscaping and trailing vegetation to minimise the presentation of retaining
                              walls and hardscape.
               22.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
               23.    All works must be carried out in accordance with the Arborist Report Impact Assessment
                      listed within this Decision Notice
                      Community Management Statement
               24.    Any proposed Community Management Statement required for the development pursuant to
                      the Body Corporate and Community Management Act 1997 must be submitted to Council for
                      endorsement at the same time as submission of the Building Format Plan (or similar) to
                      Council for compliance assessment.
               25.    All clauses and by-laws of the proposed Community Management Statement must accord
                      with the requirements of this Decision Notice and in particular must include the following
                      additional clauses:
                      a.      The dwelling units are not permitted to be used for short term accommodation, unless
                              where identified as accepted development by the Noosa Plan or where there is a
                              Development Permit for Material Change of Use for Short Term Accommodation in
                              effect. Short term accommodation means the use of the premises for providing
                              accommodation of less than 3 consecutive months to tourists or travellers.
                      External Works – Clipper Street
               26.    Clipper Street must be upgraded for the length of its frontage to the subject site. The works
                      must be undertaken in accordance with an Operational Works approval, and must include in
                      particular:
                      a.      construction of a pedestrian footpath in accordance with the conditions of this Decision
                              Notice; and
                      b.      removal of the existing property access and reinstatement of the kerb and verge area
                              to match the balance of the site frontage, including the provision of topsoil and turf
                              where the existing verge is grassed.
                      Condition 26 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                      infrastructure.
                      External Works – Ventura Street
               27.    Ventura Street must be upgraded for the length of its frontage to the subject site. The works
                      must be undertaken in accordance with an Operational Works approval, and must include in
                      particular:



                                                                                                          Page 4 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 5

                      a.      construction of a pedestrian footpath in accordance with the conditions of this Decision
                              Notice.
                      Condition 27 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                      infrastructure.
                      Site Access and Driveways
               28.    A sealed access driveway must be provided from Clipper Street to all parking and
                      manoeuvring areas of the development. The works must be undertaken in accordance with
                      an Operational Works approval and must include in particular:
                      a.      a driveway crossover in accordance with Council standard drawings RS-049 and RS-
                              050 and any associated addendum.
                      Car Parking
               29.    A minimum of 6 car parking spaces must be provided and marked on the site. The works
                      must be undertaken in accordance with an Operational Works approval, be generally in
                      accordance with the approved plans and must include in particular:
                      a.      1 visitor parking spaces within the total;
                      b.      dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
                              Parking Facilities.
                      Pedestrian and Bicycle Facilities
               30.    Pedestrian and bicycle facilities must be provided for the development. The works must be
                      undertaken in accordance with an Operational Works approval, and must include in
                      particular:
                      a.      a 1.5m metre wide footpath within the road verge for the entire length of the site’s
                              frontage to Clipper and Ventura Street – the footpath’s width can be reduced (to a
                              minimum of 1.2m), only in locations where a 1.5m wide footpath would impede on
                              minimum clearances (i.e., street trees) or result in the creation of trip hazards for
                              pedestrians;
                      Condition 30 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                      infrastructure.
                      Stormwater Drainage
               31.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with an Operational Works
                      approval, be generally in accordance with reference document Stormwater Management
                      Report (S22-011, Rev. C) dated 17 July 2025 prepared by Westera and must include in
                      particular:
                      a.      an amended Stormwater Management Report to include 3,000 litres of rain water
                              storage per dwelling for non-potable reuse purposes.
                      b.      the treatment of rainwater to achieve the load reduction targets outlined in Acceptable
                              Outcome 6.2 of the Water Quality and Drainage Code.
                      c.      the attenuation of the post-development peak flow rate to be consistent with the pre-
                              development peak flow rate.
                      Condition 31 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                      infrastructure.
                      Services
               32.    Underground reticulated electricity and telecommunication services must be provided to
                      Units 1-3 in accordance with the standards and requirements of the relevant service provider.




                                                                                                        Page 5 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 6

               33.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               34.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               35.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               36.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               37.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               38.    All earthworks and associated retaining structures/batters, both above and below ground,
                      both temporary and permanent, must be undertaken in accordance with an Operational
                      Works approval, be generally in accordance with the approved plans and contained entirely
                      within the subject site unless written permission from the respective landowner(s) is provided
                      to Council.
               39.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               40.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               5.     REFERENCE DOCUMENTS

                Plan No.               Rev.   Plan/Document Name                                   Date

                S22-011                C      Stormwater Management Report prepared by 17/07/2025
                                              Westera

                LD1                    E      Drawing Schedule, Specifications prepared by Bird 25/11/2025
                                              Landscape Design

                LD2                    E      Finishes and Planting Schedules prepared by Bird 25/11/2025
                                              Landscape Design
                                              as annotated by Council

                LD3                    E      Details prepared by Bird Landscape Design            25/11/2025



                                                                                                      Page 6 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 7

                LP1                    E      Planting Plan - Ground            prepared     by   Bird 25/11/2025
                                              Landscape Design
                                              As annotated by Council

                                       V2     Arborist Report, Impact Assessment prepared by 20/06/2025
                                              Treesafe Australia

               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Aboriginal Cultural Heritage Act 2003
               1.     There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
                      approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                      The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
                      carries out an activity must take all reasonable and practicable measures to ensure the
                      activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
                      duty of care. Substantial monetary penalties may apply to individuals or corporations
                      breaching this duty of care. Injunctions may also be issued by the Land and Resources
                      Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
                      that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
                      of Aboriginal cultural heritage.
                      You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
                      Equitable Access and Facilities
               2.     The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      a.      the Disability Discrimination Act 1992 (Commonwealth);
                      b.      the Anti-Discrimination Act 1991 (Queensland); and
                      c.      the Disability (Access to Premises – Buildings) Standards.
                      Advertising Devices
               3.     All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
                      (Administration) 2015 including both temporary and permanent signage. All freestanding,
                      pylon or pole signs or signage that is illuminated requires approval from Council prior to being
                      installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is
                      prohibited from being erected in the Shire.
                      Development Compliance Inspection
               4.     Prior to the commencement of the use, please contact Council's Development Assessment
                      Branch to arrange a Development Compliance Inspection.
                      Infrastructure Charges
               5.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges




                                                                                                            Page 7 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 8

                      Performance Bond Agreement
               6.     An applicant for a development application may make an agreement with an assessment
                      manager, referral agency or other person to establish the responsibilities, or secure the
                      performance, of a party to the agreement about a development condition.
                      Qualified Person
               7.     For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
                      landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
                      current experience in the field of landscape design.
                      For the purpose of preparing an Arborist Report, a qualified person is considered to be a
                      person with either:
                      a. ISA certification; or
                      b. Diploma of Arboriculture in addition to a minimum of 3 years current experience in the
                         field of arboriculture.
                      Qualified Person
               8.     For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
                      landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
                      current experience in the field of landscape design.
                      Submission of Amended Plans Required
               9.     The conditions of this Decision Notice require resubmission of plans to Council with
                      amendments. Please address the amended plan/s to Council’s Development Assessment
                      Branch with the Reference No. MCU25/0079.
                      Building and Construction Industry (Portable Long Service Leave) Levy
               10.    The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
                      Co-ordination of Operational Works Assessment
               11.    Additional application fees apply to Operational Work applications where the different
                      aspects of the works are lodged separately. Significant savings in application fees will result
                      if all works are lodged in a single application.
                      Preparation of a Preliminary Construction Management Plan
               12.    A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.    Traffic management during all phases of construction
                      b.    Adequate parking arrangements for works and deliveries;
                      c.    appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                            Devices (MUTCD)
                      d.    provision for safe vehicle and pedestrian access across the frontage of the site both
                            during daily construction and after daily construction has ceased.
                      Biosecurity Act 2014 – Fire Ant Control
               Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
               individuals and businesses are responsible for ensuring that they follow the movement controls for
               specific organic materials to help prevent the spread of fire ants within South East Queensland’s
               fire ant biosecurity zones. Movement of a fire ant carrier from within a fire ant biosecurity zone may
               need      a    biosecurity   instrument     permit.     More     information      is   available    on
               https://www.fireants.org.au/treat/business-andindustry/movement-controls




                                                                                                       Page 8 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 9

               7.     REFERRAL AGENCIES

               The referral agencies applicable to this application are:

                Concurrence                                      Referral Trigger            Response
                                                                                             2508-47661 SRA

                                       SARA at DILGP SARA        Schedule 10, Part 4,        The agency provided its
                                       at DILGP Via MyDAS2       Division 3, Table 1, Item   response on 18 August
                                       at https://prod2.dev-     1 (Planning Regulation      2025(Reference No.
                                       assess.qld.gov.au/suite   2017)                       2508-47661 SRA). A
                                       / (for assistance,                                    copy of the response is
                                       contact DILGP at 5352                                 attached
                                       9701 or
                                       email:[email protected]


               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required               Subject of the required Development Permit

                Operational Works                                 Vehicle Crossover, Stormwater Drainage,
                                                                  Earthworks, Landscaping and External Works.

                Development Permit for Building Works             All building work.

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.




                                                                                                        Page 9 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 10

               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,


               Andrew Gaffney
               Senior Development Planner | Development Assessment
               Development & Regulation


               Enc:   Appeal Rights
                      Referral Agency Response
                      Infrastructure Charge Notice
                      Approved Plans/Documents

               cc.    SARA at DILGP
                      Via MyDAS2 at https://prod2.dev-assess.qld.gov.au/suite/
                      (for assistance, contact DILGP at 5352 9701 or email [email protected])




                                                                                                            Page 10 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 11

                                       Referral Agency Response
                                       PLANNING ACT 2016 & PLANNING REGULATION 2017




                                                                                      Page 11 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

Page 12

2508-47661 SRA

SARA role: Referral agency

SARA trigger: Schedule 10, Part 4, Division 3, Table 1, Item 1 (Planning Regulation
2017)
Premises contaminated because of unexploded ordinance

SARA reference: 2508-47661 SRA

Assessment manager: Noosa Shire Council

Street address: 4 Ventura Street, Sunrise Beach

Real property description: Lot 83 on RP132135

Applicant name: Sunrise Equities Pty Ltd TTE
C/- URBN Town Planning Pty Ltd

Applicant contact details: [email protected]

Human Rights Act 2019 A consideration of the 23 fundamental human rights protected under

considerations: the Humans Right Act 2019 has been undertaken as part of this
decision. It has been determined that this decision does not limit
human rights.

Representations

 

An applicant may make representations to a concurrence agency, at any time before the application is
decided, about changing a matter in the referral agency response (chapter 1, part 7, section 30
Development Assessment Rules). Copies of the relevant provisions are in Attachment 4.

A copy of this response has been sent to the applicant for their information.

For further information please contact Rosanna Nobile, Planning Officer, on (07) 5352 9777 or via email
[email protected] who will be pleased to assist.

Yours sincerely

/
il
/
Jamaica Hewston
Manager

cc Sunrise Equities Pty Ltd TTE C/- URBN Town Planning Pty Ltd, [email protected]

enc Attachment 1 - Referral agency conditions
Attachment 2 - Advice to the applicant
Attachment 3 - Reasons for early referral agency response
Attachment 4 - Representations about a referral agency response provisions

State Assessment and Referral Agency Page 2 of 5

Document Set ID: 24381517 Page 12 of 16

Version: 4, Version Date: 17/12/2025

Page 13

2508-47661 SRA

Attachment 1—Referral agency conditions

(Under chapter 3, part 3, division 1, section 56(1}(b){i) of the Planning Act 2016 the following conditions must be
attached to any development approval relating to this application)

 

 

No. | Conditions Condition timing
Development Permit: Material change of use

 

 

10.4.3.1.1 — Contaminated land (unexploded ordnance) —The chief executive administering the
Planning Act 2016 nominates the Director-General of the Department of State Development,
Infrastructure and Planning to be the enforcement authority for the development to which this
development approval relates for the administration and enforcement of any matter relating to the
following condition:

 

1. Provide certification to the Department of State Development, Prior to the
Infrastructure and Planning at [email protected] | commencement of
by an approved contractor on the Australian Government, works
Department of Defence, Unexploded Ordnance (UXO) Panel that
the:

(a) subject site has been remediated and cleared of unexploded

ordnances; or
(b) proposed use can be suitably managed on the site.

 

 

 

 

 

State Assessment and Referral Agency Page 3 of 5

Document Set ID: 24381517 Page 13 of 16
Version: 4, Version Date: 17/12/2025

Page 14

2508-47661 SRA

Attachment 2—Advice to the applicant

 

 

General advice

 

1. Terms and phrases used in this document are defined in the Planning Act 2016, its regulation
or the State Development Assessment Provisions (SDAP) (version 3.2). If a word remains
undefined it has its ordinary meaning.

2. Provide the owner, occupier and any person employed to work on the subject site the following
information:
(a) Residual UXO may still exist following remediation and all work should proceed with
due caution.
(b) The procedure to be followed by any person finding an object suspected of being
explosive ordnance or component thereof:
i. advise the police immediately
ii. do not disturb the object
ili. take action, where appropriate, to prevent it being disturbed by
(c) Another person:
i. note its approximate dimensions and general appearance
ii. note the route to its location.

 

Applicants wanting to find out more details of area management advice (AMA), current UXO
investigations and remedial search contractors, may use the following websites:
« Department of Environment, Tourism, Science and Innovation -
https://www.des.qid.gov.au/
« Commonwealth Department of Defence - http://www.defence.gov.au/uxo/!

 

 

 

 

State Assessment and Referral Agency Page 4 of 5

Document Set ID: 24381517 Page 14 of 16

Version: 4, Version Date: 17/12/2025

Page 15

2508-47661 SRA

Attachment 3—Reasons for referral agency response
(Given under chapter 3, part 3, division 1, section 56(7) of the Planning Act 2016)

 

The reasons for the SARA's decision are:

« The application is for a development permit for material change of use for multiple dwelling (4 units)
at 4 Ventura Street, Sunrise Beach formally described as Lot 83 on RP132135.

« The proposed development required referral for with substantial unexploded ordnance potential

« SARA assessed the development application against State code 13: Unexploded ordnance of the
State Development Assessment Provisions (SDAP), version 3.2.

« SARA determined that the application complied with the relevant state code, with conditions to:

© ensure works does not place another part of the environment, or human health, at risk as a
consequence of development.

Material used in the assessment of the application:

the development application material and submitted plans
Planning Act 2016

Planning Regulation 2017

the SDAP (version 3.2), as published by SARA

the Development Assessment Rules

SARA DA Mapping system

section 58 of the Human Rights Act 2019

Attachment 4—Representations about a referral agency response
provisions

 

(page left intentionally blank)

State Assessment and Referral Agency Page Sof 5

Document Set ID: 24381517 Page 15 of 16

Version: 4, Version Date: 17/12/2025

Page 16

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 16 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.