Approved Decision Notice - RAL24/0014 - AS PUBLISHED
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below.
Plan No. Rev. Plan/Document Name Date
100988-2 - Proposed Subdivision of Lot 105 on SP118458 5/07/2023
prepared by Murray & Associates
Stormwater Drainage
4. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property.
Access and External Works
5. Formalised access must be provided as part of any subsequent development of Lot 2 and
Lot 100.
Services
6. Underground connections to reticulated water, sewer, electricity and telecommunication
services must be provided to Lot 2 and Lot 100 as part of any subsequent development of
Lot 2 and/or Lot 100. The connections must be in accordance with the standards and
requirements of the relevant service provider.
7. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
Easements
8. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
9. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
10. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks
11. All earthworks and associated retaining structures must be undertaken in accordance with
an Operational Works approval and contained entirely within the subject site unless written
permission from the respective landowner(s) is provided to Council.
Damage to Services and Assets
12. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
5. REFERENCE DOCUMENTS
Not applicable.
Page 2 of 6
Document Set ID: 23218826
Version: 3, Version Date: 02/09/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Decision Notice - RAL24/0014 - AS PUBLISHEDRelated documentApplication case desk ↗
About this file
- File size
- 155 KB (small file)
- File type
No other editions are linked here.