Attachment 1—Conditions to be imposed

2401-38769 SER

 

 

No.

 

Conditions

 

Condition timing

 

Development Permit for Operational work

 

10.17.3.2.1—Operational work that is tidal works or work in a coastal management district in tidal
waters—The chief executive administering the Planning Act 2016 nominates the Director-General of the
Department of Transport and Main Roads (Maritime Safety Queensland) to be the enforcement authority
for the development to which this development approval relates for the administration and enforcement of
any matter relating to the following conditions:

 

1.

The private pontoon must be carried out generally in accordance with
the following plan:

e Site Plan, Pontoon Plan & General Notes prepared by Aqua
Pontoons, dated 15/12/2023, Drawing No. AP9383-01 and

At all times.

 

 

 

 

 

Revision 0.
2: (a) The structure must be lit/marked in accordance with the following For the duration of
specifications: works and for operation
i. section 3 of AS4282-1997 Control of the obtrusive effects of to be maintained at all
oe times.
outdoor lighting.
(b) Lighting provided must not obscure, disguise or otherwise interfere
with the safe navigation of other vessels, including the
effectiveness of navigational lighting.
3. The construction, operation and maintenance of the private pontoon, For the duration of
and any ship berthed, moored or attached to the structure, must not: works, and at all times.
(a) encroach into, pass over or under a navigation corridor
(b) be located in a high risk maritime zone
(c) impede the safe navigation of other ships or boats
(d) restrict safe access to or from neighbouring structures.
4. Remove and dispose of debris or similar obstruction encountered For the duration of
whilst undertaking the work at an appropriately licensed facility. works.
5. All piles and/or structures to be demolished, both above and below the | Prior to the completion

 

waterline must be completely extracted/removed.

 

of the works.

 

State Assessment and Referral Agency

Page 3 of 5

 
Log in to download the original file

Supporting Documents - 20 Wesley Court, Noosa Heads (PAGE).pdf · 4.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.