HAT
Scour Scour
Seabed [varies]
Figure 48: Preliminary design of groynes
The groyne has been designed as an emergent structure. The crest height has been nominated as approx. 1 m above HAT
to allow for wave action without significant overtopping. The base of the structure is variable to reflect changing surface
levels along the length of the structure. As a minimum the base containers should be 0.7m below the surface level [greater
at the head of the groyne] with scour containers to accommodate greater erosion.
Preliminary estimates have been prepared [Table 9]. It is noted that this is based on existing surface levels and could vary if
levels change.
Table 9: Preliminary cost estimate for 2 groynes
Qty Rate Amount
[ex-GST]
Establishment $100,000
Supply of 2.5m3 containers [standard] 175 $300 $52,000
Supply of 2.5m3 containers RP 260 $185 $48,000
Dredging to provide suitable sand stockpile 1,087 m3 $12 $13,000
Fill & placement of 2.5m3 containers 435 $280 $122,000
Project mans ement 5% $15,000
TOTAL $350,000
6.5. Dredging
There is an existing secondary southern channel [Figure 13] which is proposed to be deepened slightly to provide adequate
navigation after closure of the primary southern channel by the proposed works. Existing depths are presently approx. -0.5m
AHD. It is proposed to deepen this channel to approx -2m AHD (-1m LAT). The proposed deepening will require the
removal of approx. 10,000m3. Material is to be placed as foreshore nourishment and/or backfilling adjacent to structures as
required.
Table 10: Preliminary cost estimate for dredqin
Qty Rate Amount
ex-GST]
Establishment $100,000
Dredging / Nourishment 10,000m3 $12 $120,000
Project management 5% $10,000
TOTAL $230,000
6.6. Total Strategy
Preliminary costs associated with the complete strategy [Figure 39] are as per Table 11.
Table 11: Summary of costs
Amount
[ex-GSTJ
Submerged closure $1,280.000
Training Wall $ 407.000
Revetment Wall $ 665.000
2 Groynes S 350.000
Dredging / Nourishment $ 230.000
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application - Part 2 of 2 - Report & PlansRelated documentApplication case desk ↗
About this file
- File size
- 13.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.