A summary contract cost estimate for proposed Stage 1 works is provided in Table 13. It is noted that estimates are based
on preliminary designs. Costs assume a single establishment for all Stage 1 works. Non-contract costs (e.g. project
management) not included. It is noted that thes costs are estimates only and costs may vary. In particular, establishment
costs may vary depending on the type, size and availability of equipment to be used. Timeframe for works will depend on
the equipment to be used.
13: Summar of Preliminary Contract Costs for Proposed Stage 1
Qty Rate Amount
ex-GS
Establishment 1 $100,000
Contract documentation 1 $10,000
Northern section of curved "closure" 80m $250,000
Trainin g wall 80m $305,000
Revetment wall $530,000
Dred in / nourishment 10,000m3 $12 $120,000
Water quality testing Allowance only $30,000
TOTAL $1,345,000
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application - Part 2 of 2 - Report & PlansRelated documentApplication case desk ↗
About this file
- File size
- 13.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.