ECM_22874320_v1_Operational Works Application - 4 The Quarterdeck_ Noosa Heads
Our Ref: 20220659
Council Ref: RAP22/0024
19 March 2024
Chief Executive Officer
Noosa Shire Council
PO Box 141
Tewantin QLD 4565
Sent via email: [email protected]
Attention: Development Assessment Team
Dear Sir/Madam,
DEVELOPMENT APPLICATION FOR OPERATIONAL WORKS (DRIVEWAY
CROSSOVER, VEGETATION CLEARING, EARTHWORKS AND
STORMWATER/DRAINAGE) AT 4 THE QUARTERDECK, NOOSA HEADS
(LOT 67 RP88934)
Further to Council approval of Development Permit for Referral Agency Response for Dwelling House at 4
The Quarterdeck, Noosa Heads (Lot 67 RP88934), please find enclosed the following documentation to
facilitate Council’s assessment for Operational Works:
● DA Form 1;
● Engineering Design plans prepared by SCG Consulting Engineers; and
● Stormwater Clearance Details plans prepared by Gerard Smith Design.
The Council fee will be paid upon receipt of Council invoice.
The attached documentation has been prepared by the specialist consultants in accordance with the
requirement of the Noosa Planning Scheme.
In light of the recent approval (RAP22/0024) for a dwelling house, this application provides design details
for the driveway crossover, earthworks and stormwater management.
The following specific condition responses are proposed:
Condition 16
A sealed access driveway must be provided from The Quarterdeck to all parking and manoeuvring areas
of the development. The works must be undertaken in accordance with an Operational Works approval,
be generally in accordance with Gerad Smith Design’s Cross Sections – Sheet 1 (SK 501, Rev. DA3) and
Floor Plan – Bed Level 1 (SK 202, Rev. DA3), and must include in particular:
a. a driveway crossover generally in accordance with RS-049, RS-050 and any associated
addendum; and
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 1 page
Page 2
b. a surface drainage grate located at the bottom of the downward slope of the proposed
driveway and wholly within private property.
Refer to Engineering design plans prepared by SCG Consulting Engineers.
Condition 18
The site must be provided with a stormwater drainage system connecting to a lawful point of discharge.
The works must be undertaken in accordance with an Operational Works approval and the Queensland
Urban Drainage Manual and be generally in accordance with DME Project’s Response to Information
Request letter dated 10 November 2022 and Stormwater Management Sketch dated 11 November 2022.
Refer to Engineering design plans prepared by SCG Consulting Engineers.
Condition 21
Stormwater drainage easements shall be dedicated in favour of Council, excluding inter allotment
drainage, over all drain lines in private property. The final dimensions of the volumetric easement must be
provided to Council prior to the issue of an Operational Works approval and the easement must be
registered in accordance with the Approved Plans prior to commencement of use.
The final dimensions of the volumetric easement must be provided to Council prior to the issue of an
Operational Works approval and the easement must be registered in accordance with the Approved Plans
prior to commencement of use.
Refer to Stormwater clearance details plans prepared by Gerard Smith Design for dimensions of the
volumetric easement.
We thank the Council on behalf of the applicant for assessing the above application.
Based on the information provided in this application we respectfully request that Council proceed to
commence their assessment and approve the development subject to reasonable and relevant conditions.
Should you have any questions with respect to the above, please do not hesitate to contact me directly.
Yours faithfully,
Adapt Town Planning + Development Management
Liam Pinese
Managing Director
E: [email protected]