2021-01-18 GC - Item 3 - Attachment 1 - Coastal Hazards Adaptation Plan for Community Consultation

of 130

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (20.8 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
The following actions will help progress the achievement of these outcomes:

 MANAGEMENT             ACTIONS FOR NEXT 5 YEARS
 RESPONSE
 AREA

 Land Use               Maintain existing development requirements.
 Planning

                        Investigate a range of backflow prevention methods and technology for parts
                        of the stormwater network identified as vulnerable

                        Investigate location, scale and design of adaptive landscape structures (e.g.
                        non-intrusive levees, innovative design features for garden beds, public
 Public                 furniture, park design and raised foreshore footpaths19) to prevent frequent,
 recreational,          shallow and low flow tidal inundation of parks and road corridors
 built, and
                        Investigate road corridor designs that are more resilient to frequent wet/dry
 Infrastructure
                        scenarios and incorporate into asset renewal plans where appropriate
 assets
                        Ensure road asset plans and upgrades for Lake Weyba Drive appropriately
                        consider inundation risks

                        Consider inundation risks as part of next review of the Noosaville Foreshore
                        Management Plan

 Foreshores and         No actions proposed.
 Natural Areas

 Other                  No actions proposed.




Other shire wide actions are also identified at the beginning of this Section.




19 Depending on the location requirements, these may range in height up to 300mm in the case of raised

footpaths, or a height consistent with safety regulations in the case of barriers (e.g. approximately waist high)
Noosa Council – Coastal Hazards Adaptation Plan 2020 - 2030 (community consultation version)            Page 54
Log in to download the original file

2021-01-18 GC - Item 3 - Attachment 1 - Coastal Hazards Adaptation Plan for Community Consultation(PDF, 20MB).pdf · 20.8 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.