DR:DR: 24572-05 Your Ref: MCU24/0125 OPW24/1058 RAL24/0021 23 January 2025 Noosa Shire Council PO Box 141 TEWANTIN QLD 4565 ATTENTION: Planning & Development – Matthew Pinese RE: 73-77 EUMUNDI NOOSA ROAD RESPONSE TO INFORMATION REQUEST MCU24/0125 OPW24/1058 RAL24/0021 We refer to the above Development Application and the information request issued by Council dated 28 October 2024. Please find attached the following documents that have been revised to address the civil engineering items contained in the information request. - Tod Consulting Drawings 24572-C001-C090 - Stormwater Management Plan by Engeny To assist Council with their review of the above documents we provide the following response to the relevant items in the information request. EUMUNDI NOOSA ROAD ACCESS Item 3 & 4 – visibility for access onto Eumundi Noosa Rd. Response A plan showing visibility splay for the access has been included in the revised drawing set – refer drawing C090. Note that as the movement out of the property is a left turn only, we have provided the visibility splay to the north only. In accordance with Austroads AGTRD Part 4A, the desired SISD for a design speed of 70kph is between 141-151m (table 3.2). Due to the horizontal geometry of Eumundi Noosa Rd in this location a sight distance of approximately 125m can only be achieved, once some minor clearing is undertaken. As this is an existing road, we believe the application of the Extended Design Domain is appropriate in this situation. In accordance with table A9-A11 a sight distance of between 100-130m is adequate, which is further reduced by 4m due to the 2% upgrade of Eumundi Rd (table A7). As such the available sight distance is deemed adequate for the proposed access. The minimum gap sight distance (MGSD) is determined from table 3.6 of Austroad AGTRD Part 4A. The minimum gap time is 5 sec (table 3.5) which requires a sight distance of 97m for 70kph design speed which is also achieved for the access. Note that a gap time of up to 8 seconds is available for vehicles exiting the property. Page 1 of 3 Tod Job Number: 24572-05
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
FRONTAGE WORKS Item 6 – Kerb and Channel and bike lane. Response Frontage works including kerb and channel and a 2.0m wide bike lane are detailed on the revised drawings. EARTHWORKS Item 7 & 8 – spot levels, retaining walls and cross sections. Response Additional information for the earthworks has been added to the revised drawings, including cross sections showing bulk earthworks levels and the interface with neighbouring properties. Separate plans have been provided to show retaining wall levels and heights (TOW, BOW) and standard details. Refer plans C020 – C024. EXTERNAL DRAINAGE WORKS AND NON WORSENING Item 9 – Provide updated SWMP and drainage design details. Response A revised SWMP accompanies this response and addresses the non-worsening issue. A detention tank has been added to the design to mitigate peak flows. Stormwater long sections including HGL information have been included in the revised drawings for both the 10% and 1% AEP events. It should be noted that within the development site we have elected to pipe the 1% AEP event to the detention tank, however there will be some minor surcharging at the pit immediately downstream from the detention tank in the 1% AEP (2100) event as the downstream pipe network is only designed for a 10% AEP (2015) event. Refer also to wording in the SWMP that explains the rationale for the detention tank design and sizing. With respect to item 9 d) we consider Council’s position that there shall be no surcharging of the existing network in the 1% AEP (2100) to be unreasonable and not in consistent with standard stormwater design principles where the major event is conveyed via the road network or other overland flow paths.
Page 3
INTERNAL DRAINAGE DESIGN Item 10 & 11 – Provide stormwater drainage calculations and long sections Response Stormwater drainage calculations and long sections have been included in the revised drawing set for the 10% and 1% AEP (2100) events. We have not provided long sections or calculations for the 0.5EY as this superfluous information given the 10% AEP demonstrates the design sufficiently. As noted above we have elected to pipe the 1% AEP event within the development site, however, we have also provided an overland flow path along the northern boundary as a contingency. Downstream of the site there will be some minor surcharge of the new drainage pit immediately downstream of the detention tank (pit FI2/4 approx 95L/s) in the 1% AEP event, to convert part of the major flow to an overland flow which will be conveyed down the existing access to Starboard Avenue. Please note that the overland flow down the driveway in the 1% AEP will actually be less than the predevelopment overland flow – refer SWMP for further comments/explanation. There will also be some minor surcharge at the existing pit at the bottom of the driveway in the 10% AEP (2100) event again, due to the fact that the downstream network is designed to convey the 10% AEP( 2015) flows instead of 10% AEP 2100. As noted in the SWMP there will be no surcharge in the 10% AEP (2015) event. The overland flow capacity of the existing driveway is shown in the calculation sheet (613 L/s), which is substantially more than the proposed surcharge flow. STORMWATER QUALITY Item 12 – Provide updated SWMP and MUSIC model to include external catchments. Response Please refer to response in the updated SWMP. We trust the above is satisfactory. Should you have any queries regarding this matter, please contact the undersigned. Yours faithfully, Doug Reynolds, Consultant 07 5449 9600 | [email protected] TOD consulting engineers
Used in these records
24572-05 Response to Council information request - Engineering.pdfRelated documentApplication case desk ↗
About this file
- File size
- 258 KB (small file)
- File type
No other editions are linked here.