The current capital delivery expenditure to 27 January 2021 is $12.33m, or 35% of the $35.4m
capital program. The delivery and completion of projects continues across the program with
ongoing recruitment of staffing resources to be finalised in the coming months to support the
design and delivery phases of the projects.
The following table and the graph shows a breakdown of expenditure as at 27 January 2021.
Capital Works Program Amount
YTD Actual Expenditure $12,328,169
Committed Expenditure $3,912,568
Remaining Capital Expenditure $19,151,590
Full Year Budgeted Expenditure $35,392,327
Risks & Opportunities
The November 2020 Capital Program Delivery Status Report identified that risk surrounding the
delivery of the Capital Program was resultant of resignations and resourcing constraints within
the Design and Delivery team. This risk will remain until these positions are filled.
The recruitment process for replacement and additional staff is currently in progress with
interviews of applicants undertaken in early January and the recent appointment of the Delivery
Coordinator who commenced on 27 January 2021. Additional appointments will continue over
coming weeks and throughout February to fill vacant project positions. As required, projects have
been re-profiled and adjusted through the budget review process to accommodate the current
resourcing impacts.
Consultation
External Consultation - Community & Stakeholder
Nil.
Internal Consultation
Project delivery staff within the Infrastructure Services Department were consulted in the
preparation of this report.
Chief Executive Officer Community Services X Corporate Services
Executive Officer Director Director
Executive Support Community Development X Financial Services
Community Facilities ICT
Libraries & Galleries Procurement & Fleet
Local Laws Property
Waste & Environmental Health Revenue Services
Executive Services Environment & Sustainable Development X Infrastructure Services
Director Director X Director
Community Engagement Building & Plumbing Services X Asset Management
Customer Service Development Assessment Buildings and Facilities
Governance Economic Development Civil Operations
People and Culture Environmental Services Disaster Management
Strategic Land Use Planning X Infrastructure Planning,
Design and Delivery
Page 40 of 100
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.