INFRASTRUCTURE CHARGE CALCULATION DETAILS:
The infrastructure charge is calculated in accordance with Council’s Infrastructure Charges Resolution
incorporating the charge apportionment (break-up) agreement with Unitywater in compliance with the
Sustainable Planning Act 2009 and Statutory Regulatory Provision (adopted charges) applying at the
time of issuing the notice.

Council’s infrastructure charge levied is based on the following:

Approved Development Defined Use & Quantity:
    Development Permit for Material Change of Use - Multiple housing Type 4 Conventional (4 Units)

   Development               Unit of                            % Charge
                                            Charge Rate                            % Council                          $ Amount
      Class                 Measure                            (Clause 13 (c)
                                                                                                        Qty
                                             (Table 13.1
                                                                & Table 10.3
                                                                                 Apportionment                             at
     (Table 13.1           (Table 13.1
                                            Columns 4 & 5)                          (Table 10.1)                    July 2014 Index
      Column 2)           Columns 3 & 5)                         Note: (1))
 Approved Development Defined Use & Quantity: Multiple Housing - Type 4 Conventional
 Residential               3+ dwelling         $28,000             100 %                64%              4                 $71,680.00
                                                                           Gross Infrastructure Charge =                   $71,680.00

 Discount (Credit) for Lawful Existing Defined Use & Quantity (Clause 8.4): Industrial Business Type 2 (Linen Hire)
 Industry                    m2 gfa              -$50              100 %                69%             320               -$11,040.00
                            2
 Non-Residential          m impervious
                                                 -$10              100%                 100%            580                 -$5,800.00
 Stormwater                   area
                                           Existing Lawful Use or Contribution Discount (Credit) =
                                                                                                                          -$16,840.00
                                   (Clause 8.4 - Limited to and not exceeding the Gross Infrastructure Charge)
                                                             * NET INFRASTRUCTURE CHARGE =                              * $54,840.00

The infrastructure charge payable will be allocated to Council “Trunk” infrastructure networks in
accordance with Council’s Resolution as follows:
                                                                                                                 * Net Infrastructure
 Council “Trunk” Infrastructure Network               Net Infrastructure                                           Charge Amount
                   (Table 10.2)                             Charge
                                                                                 Offset/Rebate/Other
                                                                                                                       Payable
                                                                                                                  at July 2014 Index

 Transport                                                       $19,288.00                          -$0.00                $19,288.00
 Public Parks & Land for Community
                                                              $34,184.00.00                          -$0.00                $34,184. 00
 Facilities
 Stormwater                                                        $1,368.00                         -$0.00                  $1,368.00

 * Net Infrastructure Charge Payable =                        * $54,840.00                          -$0.00              * $54,840.00

* Subject to Automatic Increase Provision until date of payment.




                                    PO Box 141                      P. (07) 5329 6500      [email protected]
                                    TEWANTIN QLD 4565               F. (07) 5329 6501      www.noosa.qld.gov.au           ICN - Page 3

Used in these records

About this file

File size
306 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

MCU14-0051_ICN-N1030_28 NannygaiStNoosaville_With-InfoNotice.pdf · 306 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.