Council archive · source document
Response to Information Request - REC13/0015
Very large file (44.8 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
..
~
Callaghan & Toth
5 FLOODING ASSESMENT REPORT
5.1 Existing Conditions
This site is not subject to ponding of floodwaters from the adjacent channels and the Q 100 year
ARI flood levels (Plan 02 shows the Q100 flood level). The buildings and carparks are above
the Q 100 year ARI flood levels.
5.2 Proposed Drainage System
The road surface level is proposed to be drained to an underground drainage system capable of
taking a Q10 flow. The overflow will discharge to the Bioretention Basin where it will alternate
flows to be equal to pre-development concentrations.
The habitable floor level for the proposed development is not affected by the Q 100 flood level.
The Bioretention Basin has been modelled to act as a detention/infiltration basin. The basin size
and weir size is sufficient to reduce the increase in runoff for a Q 10 and Q 100 storm back to
predevelopment levels as shown in Table 5.1. Refer to attached Detail detention basin
calculations for Q 10 Pre and Post development flow in
TABLE 5.1: Pre-Development and Post Development Discharges
Location Q5 Q10 Q100
Pre-Development 0.115 m3/s 0.133 m3/s 0.222 m3/s
Post Development 0.118m3/s 0.128 m3/s 0.233 mJ/s
6 CONCLUSIONS & RECOMMENDATIONS
An integrated water management approach has been used to assess the site’s stormwater
requirements and water management needs. In summary:
. The proposed four lots area can be treated by a treatment train consisting of one 25m2
bio-retention basin.
. This proposed treatment train achieves the current best practice load based reduction
targets as prescribed in the Water by Design Deemed to Comply Solutions -
Stormwater Quality Management (South East Queensland) version 1.0 Table A-2
-
. The new lots have sufficient flood free areas to build residential infrastructure in
accordance with Council’s requirements.
. The rainwater tank and bioretention areas are able to attenuate the runoff
concentrations back to Pre Development levels and so the development will not have an
impact on the hydrology of the receiving waters.
15
55 Lake MacDonalld Drive -
Stage 1 SMP Revl.doc May 2013 1225
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Information Request - REC13/0015Related documentApplication case desk ↗
About this file
- File size
- 44.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.