Following 24 Remove temporary cover of geotextile, topsoil and turf following: Contractor Following On-
month maintenance or
.
Acceptance of bioretention systems on maintenance, or 80% completion of
protection
period . 80% completion of building works upstream of bioretention systems. building works.
Plant approved plantings into bioretention systems as per construction drawings.
Contractor to conduct regular watering of all planted bio-retention systems until such time as
plants are established.
Maintain bioretention system for a minimum period of 12 months, until system is accepted Off-
Maintenance.
Monitoring Hold point -
once bioretention basin underdrainage pipe work is installed -
inspection with Contractor and Following
Council to ensure in accordance with design. Council underdrainage
pipe work
Sample drainage layer, transition layer, filtration media materials must be stockpiled on-site and
installation
certification that the filtration media complies with guidelines.
The Contractor will carry out weekly inspections of the Bio-Retention Systems (Including during
Contractor
the defects liability period). The following will be examined at each inspection: Weekly
);> Sediment build up on the surface
);> Health of vegetation
);> Pondage during major storms not infiltrating into the sand
);> Erosion at the outlet
);> Pondage during minor storms
One month after installation of plants in bioretention system: Contractor
One month after
);> Field test hydraulic conductivity in accordance with FAWB guidelines. installation
Reporting );> Contractor to maintain a log of inspections, watering and other actions. );> Contractor );> As required
);> Records are to be logged and kept for verification of compliance on a need basis.
);> Bio-retention designer I Engineer shall perform inspections during construction stage and fill
out Water by Design forms for compliance.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Information Request - REC13/0015Related documentApplication case desk ↗
About this file
- File size
- 44.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.