     13 July 2011                                                                           Department of
                                                                                            Transport and Main Roads


    The Jetty Specialist
    2 Industrial Avenue
    Caloundra Qld 4551



    Dear Sir


    Operational Work, Prescribed Tidal Works - Request for comments
    Pontoon - Body Corporate for Noosa Harbour, 6 Quamby Place, Noosa Heads (RP#144250)

    Thank you for your letter of 8 July 2011 about your proposal to construct a pontoon at the location
    mentioned above.

    As a concurrence agency, Maritime Safety Queensland has no objection to the proposal provided the
    following navigation and marine safety conditions are complied with.

    1.   The contractor must build the pontoon according to The Jetty Specialist, drawing: JSP-SJ-23480,
          attached to your letter dated 8 July 2011.


    2.   No part of the structure or any ship berthed at this structure is to come closer than I.5metres from
         the side boundaries of the allocated water space as shown on the submitted water allocation plan.


    3.   The structure and any part thereof must not extend beyond 18 meters as depicted in Cardno
          Drawing JSP-SJ-23480 dated 9 July 2010, Issue B.


    4.   The pontoon and all freestanding piles must be lit and clearly visible to approaching vessels. The
         contractor must position all lighting so it does not cause a risk to the safe navigation of other
          vessels.


    5.   The applicant or his agent is responsible for the removal of any existing structure above or below
         the waterline, and must contain and remove any debris. Any pile that needs to be removed must
         be totally extracted.


    6.   The ship moored at this pontoon must follow the most direct course from this structure to open
          waters and a similar direct course when returning to this pontoon.

Department of Transport and Main Roads                 Our ref     215/00003(3) P6025-MOM P6070-MOM F39
Maritime Safety Queensland                             Your ref
Marine Operations (Brisbane)                           Enquiries   James O'Connor
MacArthur Avenue East                                  Telephone +61 7 3860 3504
Pinkenba Queensland 4008                               Facsimile +61 7 3860 3571
                                                       Website     www.msq.gld.gov.au
                                                       Email       [email protected]
Log in to download the original file

Development Application - Part 2 of 2 - Title Search, ecoaccess Decision, DTMR Conditions, Correspondence & Plans.pdf · 4.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.