Original source · versioned page text
Meeting minutes
GENERAL COMMITTEE MEETING | 6 OCTOBER 2026
G. Note that implementation of the Noosa Events Strategic Framework 2026-
2031 will assist to inform future event funding, sponsorship, investment and
program design to ensure alignment with Council's strategic priorities and a
balanced events portfolio.
H. Delegate to the CEO to make minor amendments or corrections if required
prior to final design and publishing of Noosa Events Strategic Framework
2026-2031
I. Subject to Council endorsement of recommendation D, the new Noosa Events
Management Policy contained in Attachment 3 repeals and replaces the
Events Policy adopted in 2019 and the Noosa Main Beach Events Policy
adopted in 2018.
J. Request that the Chief Executive Officer provide an annual report to Council
on the implementation and performance of the Noosa Events Strategic
Framework 2026-2031, including progress towards the framework's
objectives and any recommendations for improvement.
K. That upon its establishment, the Events Executive Group review current event
limits in the Events Policy to determine sustainable limits for event approvals,
having regard to cumulative impacts, including the duration for which parking
areas and recreational spaces are unavailable for public use, as well as
broader impacts on the community.
Carried.
For: Cr Brian Stockwell, Cr Karen Finzel, Cr Jessica Phillips, Cr
Tom Wegener, Cr Frank Wilkie
Against: Cr Nicola Wilson
7.2.6 NOOSA AQUATICS CENTRE UPGRADE PLAN AND NOOSA AQUATICS
FACILITIES STRATEGIC PLAN
Committee Recommendation
Moved: Cr Frank Wilkie
Seconded: Cr Karen Finzel
That Council
A. Note the report by the Sport and Active Lifestyles Manager to the General
Committee dated 6 October 2026 regarding the Noosa Aquatic Facilities
Strategic Plan and NAC Upgrade Plan,
B. Endorse the Noosa Aquatic Facilities Strategic Plan and the Noosa Aquatic
Centre Upgrade Plan, including the Prioritised Implementation Plan (PIP);
C. Refer the findings, recommendations and priority actions identified within the
Strategic Plan and PIP for consideration through future Corporate Planning,
Annual Budget, Long Term Financial Planning and Capital Works Program
processes;
D. Note that endorsement of the Strategic Plan and PIP does not constitute
approval or funding allocation for individual projects, with implementation
remaining subject to future detailed investigation and assessment, operational
requirements, funding availability and future Council consideration;
E. Authorise the Chief Executive Officer to pursue external funding opportunities,
partnerships and grant programs to support implementation of priority actions
identified within the Strategic Plan and PIP; and
F. Authorise the Chief Executive Officer to make minor changes or administrative
amendments prior to publishing the final document.
Page 7 of 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Meeting minutes.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.