Approved Document Construction & Tree Management Plan OPW25-0206 · OPW25/0206
Plans and drawings: the text below has words only, no drawings.
Very large file (10.8 MB): may take a few minutes to open.
2 T REE P ROTEC TION G UIDELINES With the entire site being considered as a Tree Protection Zone, protection measures are to be put in place across the site. The information below is guided by the AS4970-2009 Protection of trees on development sites, industry best practices, and experience. It is designed to provide direction and information regarding the tree protection requirements. This advice is subject to change due to site conditions and the Project Arborist will advise of the best practices required onsite when the necessary site requirements have been confirmed. The information within these procedures is holistic for the site and can be incorporated into the different stages and/or locations of the project as required. It must be noted that trees are dynamic living organisms that respond to changes in their environs; repeat assessments are key to maintaining tree vitality, structural integrity, and reducing any potential risk that may arise. As such input and cooperation with the Project Arborist is essential as their environment changes. The successful retention of the trees will be bettered by the education and cooperation of all parties of the construction team during the build and the presence of the Project Arborist on site to assist and advise on tree protection or management before, during, and after, the construction phase for all works adjacent retained trees. ALL workers on the site are to be made aware of the Tree Protection Procedures and any site- specific safety measures by the main contractor prior to commencing works. 2.1 PRE-CONSTRUCTION A designated onsite foreman/supervisor from the construction company is to ensure that the Construction and Tree Management Plan is adhered to throughout the life of the project and maintain regular communication with the Project Arborist. Prior to any works commencing on the site, the Exclusion Zones shall be established as per the Construction and Tree Management Plan. The location of fencing/flagging is to be agreed with the Project Arborist and will follow guidelines set out in the section on Tree Protection Fencing. The creation of dedicated and delineated access pathways for the construction equipment and materials are to be established using Temporary Ground Protection procedures. Additional protection measures, including ground and trunk protection, are to be used where deemed necessary as the project progresses. 2.2 DURING CONSTRUCTION Access to the Exclusion Zones is prohibited or restricted to those with permission. The Project Arborist is required to attend the site when works are to be undertaken that may affect retained trees or their roots. The Project Arborist shall oversee, advise, and assist as and when 24_11_22_RACV Noosa_Tree Protection Procedures Page 3 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Document Construction & Tree Management Plan OPW25-0206.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.