Council archive · source document
Approved Document Construction & Tree Management Plan OPW25-0206 · OPW25/0206
Plans and drawings: the text below has words only, no drawings.
Very large file (10.8 MB): may take a few minutes to open.
6 W ORK M ETHODOLOGIES A DJACENT T REES
Due to the restrictive nature of the site, a variety of methods and processes will need to be
incorporated into the project to ensure the retention and protection of the trees. The following are
examples and explanations of methodologies and processes that can be implemented when
working near retained trees.
As the construction methodology is to use support style structures and use the lay of the land,
excavation is expected to be minimal.
6.1 GENERAL EXCAVATION METHODOLOGIES
Excavations are predicted to be kept to a minimum. When excavations are necessary to improve
the levels for cabin constructions and the carpark and are being undertaken within a tree's root
zone, all necessary precautions are to be adhered to. The Project Arborist will advise on the
progression of the works and undertake root pruning as required.
• When using a mechanical excavator ground protection is necessary to minimise
compaction and damage to the surrounding ground.
• Spoil can be carefully extracted with a combination of a small bucket and ripper.
• General excavation is to be undertaken, when possible, with the bucket positioned
perpendicular to the tree, and the spoil dug away from the tree, this helps to minimise
roots being accidentally torn or fractured.
• Where possible, create a preliminary excavation and/or post-holes at the outer edges of
the required cut line using a Hydro-vacuum excavator. Roots found can be cleanly cut by
the Project Arborist. Once the preliminary cut line is completed excavation of the remaining
area outside the cut line can be dug using the appropriate attachment with all due care
and attention to the adjacent protected trees.
• Roots deemed to be pruned and removed are to be carefully cut using a sharp saw and/or
secateurs. Root removal is carried out by the Project Arborist on a root-by-root basis taking
into consideration the type of tree, distance from the cut to the tree, and the size and
number of roots found.
• Retained exposed roots are to be covered with hessian and if pedestrian or machine
access is required suitable ground protection should be used.
• Where possible excavations creating bare ground should be covered with the appropriate
material.
24_11_22_RACV Noosa_Tree Protection Procedures Page 10 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Document Construction & Tree Management Plan OPW25-0206.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.